  1515   Monday, May 01, 2017, 08:53 chad fisherSouth Hot-CellRepairTM3 Fiberglass removalFiberglass, capton tape and tie straps
have been removed from TM3.
  
  1517   Monday, May 01, 2017, 13:11 David WangSouth Hot-CellRepairTM3 Electrical Check on TM3 after fibergalss is moved in SHC. RU( coil 1), F (anode), and 60kv bias(HS,
Gasline, and MSP)  are shorted together.
Other lines are good.  They are measured
  
  1520   Tuesday, May 02, 2017, 18:33 Aurelia LaxdalSouth Hot-CellRepairTM3no targetTM3 HV tests at atmosphere for Each Line(s) after the Fiber Glass removal May 2, 2017Today a HV test at atmosphere was performed
for Each Line(s), while floating the other
lines. THIS TEST AT ATMOSPHERE IS THE FIRST
  
  1532   Wednesday, May 10, 2017, 14:00 Anders MjosSouth Hot-CellDevelopment ITE-Ta-LP-FEBIADTest target examinationChad and Anders inspected the test target
in the hot cell today. The lid had been previously
removed.
  
  1535   Tuesday, May 16, 2017, 10:28 Travis CaveSouth Hot-CellStandard OperationTM4UC#19module movedTM#4 with UC#19 has been moved from ITE
to the south hot cell.
  
  1536   Tuesday, May 16, 2017, 13:23 chad fisherSouth Hot-CellStandard OperationTM4UC#20UC#20 InstalledUCx#19 has been removed from TM4 and UCx#20
installed.
UCx#19 still had water in it at pressure
  
  1537   Tuesday, May 16, 2017, 14:18 Travis CaveSouth Hot-CellStandard OperationTM4UC#20Electrical CheckTM#4 with UC#20 has had the electrical
check done on it  at the south hot cell,
see attached for details
 TM4_UC20_Elec_chk_SHC.PDF 
  1539   Wednesday, May 17, 2017, 08:31 David WangSouth Hot-CellStandard OperationTM4 Leak check on TM4 HS line at SHCChad and I finished leak check on HS line
with UCx target installed on it.  Base
Leak rate:0.0X 10^-9 atm.cc/sec, Base pressure
  
  1550   Tuesday, June 06, 2017, 13:42 chad fisherSouth Hot-CellStandard OperationTM2SiC#36Ta#51 removed SiC#36 installedThis afternoon Ta#51 was removed from TM2
and SiC#36 installed.
All new fasteners used. High current
  
  1562   Thursday, June 22, 2017, 11:10 chad fisherSouth Hot-CellMaintenance  In cell airlineThe in cell airline has preemptively been
replaced. The hose was, as far as I know
the original.
  
  1565   Monday, June 26, 2017, 11:42 Travis CaveSouth Hot-CellStandard OperationTM4UC#20Module move TM#4 with UC#20 has been moved from
the east target station to the south hot
cell. Also the shield plug was remotely installed
  
  1566   Monday, June 26, 2017, 11:47 chad fisherSouth Hot-CellStandard OperationTM4Ta#52UC#20 Removed Ta#52 installedUC#20 has been removed from TM4 and put
in a bucket back-filled with argon. Ta#52
has been installed onto TM4 with new fasteners.
  
  1568   Tuesday, June 27, 2017, 10:26 David WangSouth Hot-CellStandard OperationTM4Ta#52Leak check on TM4 HS line at SHCLD base LR:0.0Xe-9 atm.cc/sec. No leak
has been found during the check.  The
HS line will be helium pressurized at TCS
  
  1573   Thursday, June 29, 2017, 11:12 Anders MjosSouth Hot-CellStandard OperationTM4UC#20Post Irradiation Examination (PIE)The target was inspected by Chad and Anders.
Photos are available on DocuShare.
It was noticed that the target tube heater
  
  1589   Tuesday, August 01, 2017, 14:39 Travis CaveSouth Hot-CellStandard OperationTM2SiC#36Electrical CheckThe electrical check of TM#2 with SiC#36
attached. Post beam at the south hot cell.
See attached results allow the before beam
 TM2_SiC36_SHC_elec_chk.PDFTM2_SiC36_Postbeam_SHC_elec_chk.PDF 
  1591   Wednesday, August 02, 2017, 15:13 David WangSouth Hot-CellStandard OperationTM2 SHC, TM2 leak check on HS line.HS line is leak checked at SHC this afternoon
by helium spay.  Leak detector base
LR 0.0 XE-9atm.cc/sec. Base pressure 0.0Xe-4
  
  1597   Tuesday, August 15, 2017, 09:27 Anders MjosSouth Hot-CellStandard OperationTM2SiC#36Electrical Check of target in SHC

    

       
            
  
  1603   Monday, August 28, 2017, 12:07 chad fisherSouth Hot-CellStandard OperationTM4UCx#21Ta#52 removed UCx#21 installedTa#52 has been removed from TM$ and UCx#21
installed with new mounting and high current
hardware. High current fasteners torqued
  
  1605   Monday, August 28, 2017, 14:40 Travis CaveSouth Hot-CellStandard OperationTM4UC#21Electrical CheckThe results of the electrical check of
TM#4 with UC#21 attached.
 TM4_UC21_elecchk_SHC.PDF 
  1617   Tuesday, September 19, 2017, 10:40 chad fisherSouth Hot-CellMaintenance  South East Manipulator MaintenenceEntered hot cell to preform replacement
of slave tong cable. Existing cable shows
no signs of wear so it has been re-installed.
  