2712
|
Wednesday, November 06, 2024, 08:29 |
Aaron Tam | South Hot-Cell | Standard Operation | TM4 | TiC#9 | Target and Parasitic assemblies removal from TiC#9 |
November 5, 2024 - Aaron Tam
TiC#9 HP-SIS removed from TM4
- Top left fixing bolt shows signs of heating on it (Comparison photos attached Bolt_profile.jfif & Bolt_Tops.jfif)
- Location and orientation of darker bolt (Darker_bolt.jfif)
Parasitic Targets Removed
- Left target has residue left from ablation
See photos attached for detail |
Attachment 1: Target_first_look.jfif
|
Attachment 2: Target_first_look_ETTR.jfif
|
Attachment 3: Inside_Panel.jfif
|
Attachment 4: Darker_bolt.jfif
|
Attachment 5: VCR_and_conductor_bolts_removed.jfif
|
Attachment 6: Top.jfif
|
Attachment 7: target_left.jfif
|
Attachment 8: Right.jfif
|
Attachment 9: Bottom.jfif
|
Attachment 10: Parasitic_Target_right.jfif
|
Attachment 11: Parasitic_Target_right_(2).jfif
|
Attachment 12: Left_side_without_parasitic.jfif
|
Attachment 13: Back_of_target_left.jfif
|
Attachment 14: Back_of_target_right.jfif
|
Attachment 15: Extraction_electrode.jfif
|
Attachment 16: Bolt_profile.jfif
|
Attachment 17: Bolt_Tops.jfif
|
|
2676
|
Tuesday, September 10, 2024, 12:41 |
Aaron Tam | South Hot-Cell | Standard Operation | TM4 | TiC#9 | Target TiC#9 HP-SIS installed onto TM4 |
September 9, 2024 - Aaron Tam
- Water from waterline found puddled on source-tray and containment box.
- Water was wiped up as much as possible, but likely still in containment box
- leaving to dry overnight
- Target inserted into Hotcell with nuts for the parasitic target. 4/4 socket nuts installed on upstream flange, and 3/4 installed on downstream flange
September 10, 2024 - Aaron Tam
- TiC#9 HP-SIS installed onto TM4
- Leak check passed after retightening VCR joint
- Target Electrode Conductor screws torqued to 130 inch-lbs
- Electrical test passed
- Containment box cover reinstalled
Photos attached |
Attachment 1: 089c5872-091d-484b-9b9c-dda8444b217b.jfif
|
Attachment 2: 566cae27-5562-4934-b23a-5c99af810900.jfif
|
Attachment 3: cc853ae8-5896-46f3-9f21-f6ede8c82626.jfif
|
Attachment 4: ffdf443c-2656-499a-9d0a-01ddef2f954a.jfif
|
|
2664
|
Friday, August 16, 2024, 15:32 |
Aaron Tam | South Hot-Cell | Standard Operation | TM4 | Ta#68 LP-SIS | Target Ta#68 loaded onto TM4 |
Target Ta#68 loaded onto TM4
-leak check passed
-Target electrode conductor screws torqued to 130 in-lbs
-electrical check passed
Containment box cover re-installed
photo attached |
Attachment 1: Ta-68_Installed.jfif
|
|
2697
|
Tuesday, October 01, 2024, 12:40 |
Aaron Tam | South Hot-Cell | Standard Operation | TM2 | Ta#67 | Target Ta#67 Removed from TM2 |
October 1, 2024 - Aaron Tam
Ta#67 LP-SIS removed from TM2
Ta#67 is sitting in SHC awaiting PIE
TM2 Containment Box Cover has not been reinstalled
Photos of target removal and module attached |
Attachment 1: Containment_Box.jfif
|
Attachment 2: Containment_Box_Cover_Internal.jfif
|
Attachment 3: Target_Fasteners_on.jfif
|
Attachment 4: Target_Fasteners_off.jfif
|
Attachment 5: Service_Tray_no_Target.jfif
|
Attachment 6: Ta#67_Left.jfif
|
Attachment 7: Ta#67_Right.jfif
|
Attachment 8: Ta#67_Top.jfif
|
Attachment 9: Ta#67_Bottom.jfif
|
|
2655
|
Monday, August 12, 2024, 15:55 |
Aaron Tam | South Hot-Cell | Standard Operation | TM2 | Ta#67 LP-SIS | Target Loading |
Ta#67 Target loaded onto TM2
Leak check passed
Electrical test passed after loosening off target electrode conductor screws, and torqueing by feel
|
|
588
|
Wednesday, January 22, 2014, 15:20 |
Anders Mjos | South Hot-Cell | Standard Operation | | UC#8 | Target Inspection - post beam |
The Target Assembly was inspected with Chad, Jens Henning and Anders today.
- The Target Container was broken.
- Material was deposited on the Heat Shield around the Target Center Block
- Material was deposited on the IG-LIS source.
- Electrical checks to ground (HS)
- The Extraction Electrode passed the electrical check at 1000V
- The Exit Electrode (c) held only 40V at 22 kOhm
- The IG Electrode 1 (f) held 250V at 390 MOhm
- The IG Electrode 2 (g) held only 40V at 22 kOhm
- IG 1 and IG 2 both held 250V at 450 MOhm to Exit Electorde (c)
- No spark marks were observed on the 9-pin connector
See photos of the inspection on DocuShare |
|
1062
|
Wednesday, September 02, 2015, 09:26 |
David Wang | ITE | Standard Operation | | | Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 |
I attach new Target Hall schedules here for 2015 fall and winter runs (beam schedule 129). The TH excel sheet schedule for beam 129 is included also.
Weekly update of Target Hall Schedule.See Attachments 3,4 |
Attachment 1: Target_Hall_shedule_129_Sep_to_Dec.xlsx
|
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
|
|
Attachment 3: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
|
Attachment 4: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
|
|
Attachment 5: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
|
|
1082
|
Friday, September 25, 2015, 07:56 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 |
weekly update see attachment |
Attachment 1: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
|
|
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
|
|
1094
|
Tuesday, October 06, 2015, 13:25 |
David Wang | ITE | Standard Operation | TM4 | | Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 |
Weekly update target hall schedule. See attachment 1,2. |
Attachment 1: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
|
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
|
|
|
1097
|
Tuesday, October 13, 2015, 10:53 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 |
Weekly update schedule. TM3 evaluation schedule in Nov is added.
update the schedule after the cancellation of TM2 from SHC to CS trip.see attachments 3,4 |
Attachment 1: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
|
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
|
|
Attachment 3: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
|
|
Attachment 4: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
|
|
1124
|
Monday, November 16, 2015, 08:04 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 |
Update TH schedule according to changes. See attachment 1,2 .
update TH schedule weekly. See attachments 3,4 |
Attachment 1: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
|
|
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
|
Attachment 3: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
|
|
Attachment 4: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
|
|
1142
|
Monday, November 30, 2015, 11:46 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 |
Weekly update TH schedule according to changes. see attachment 1,2 .
Update TH schedule before the weekend. see attachment 3,4 |
Attachment 1: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
|
|
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
|
Attachment 3: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
|
|
Attachment 4: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
|
|
1367
|
Friday, September 30, 2016, 14:34 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule for beam schedule 131(Sep-Dec, 2016) |
Weekly update TH schedule for beam schedule 131. See attachments 1,2 |
Attachment 1: Target_Hall_shedule_131_Sep_to_Dec.mpp
|
Attachment 2: Target_Hall_shedule_131_Sep_to_Dec.pdf
|
|
|
1354
|
Monday, September 19, 2016, 08:28 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule for beam schedule 131(Sep-Dec, 2016) |
Post new target hall Excel sheet schedule for beam schedule 131. See attachment 1,2
Post new target hall MS project schedule for beam schedule131. See attachment 3,4 |
Attachment 1: Target_Hall_shedule_131__Sep_to_Dec_2016.pdf
|
|
Attachment 2: Target_Hall_shedule_131__Sep_to_Dec_2016.xlsx
|
Attachment 3: Target_Hall_shedule_131_Sep_to_Dec.mpp
|
Attachment 4: Target_Hall_shedule_131_Sep_to_Dec.pdf
|
|
|
1384
|
Wednesday, October 26, 2016, 12:33 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Target Hall schedule for beam schedule 131(Sep-Dec, 2016) |
Update TH schedule after job delay on TM2 Febiad target. Everything should be back to schedule on last two targets. See attachments. |
Attachment 1: Target_Hall_shedule_131__Sep_to_Dec_2016.pdf
|
|
Attachment 2: Target_Hall_shedule_131_Sep_to_Dec.mpp
|
Attachment 3: Target_Hall_shedule_131_Sep_to_Dec.pdf
|
|
|
1397
|
Tuesday, November 15, 2016, 07:53 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Target Hall schedule for beam schedule 131(Sep-Dec, 2016) |
Update TH schedules . See attachments |
Attachment 1: Target_Hall_shedule_131_Sep_to_Dec.pdf
|
|
Attachment 2: Target_Hall_shedule_131_Sep_to_Dec.mpp
|
Attachment 3: Target_Hall_shedule_131__Sep_to_Dec_2016.pdf
|
|
|
1339
|
Thursday, August 25, 2016, 13:59 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule for beam schedule 130 (Apr- Sep, 2016) |
Weekly update schedule. See attachment 1,2. |
Attachment 1: Target_Hall_shedule_130_Apr_to_Sep.pdf
|
|
Attachment 2: Target_Hall_shedule_130_Apr_to_Sep.mpp
|
|
1170
|
Friday, March 18, 2016, 09:34 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Target Hall schedule for beam schedule 130 (Apr- Sep) |
I would like to post the spreadsheet of target hall schedule for beam schedule 130(Apr to Sep) first. The MS project of TH schedule for beam schedule 130 is under construction, and will be posted later. |
Attachment 1: Target_Hall_shedule_130_Apr_to_Sep_2016.xlsx
|
Attachment 2: Target_Hall_shedule_130_Apr_to_Sep_2016.pdf
|
|
|
1215
|
Monday, April 25, 2016, 12:18 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule for beam schedule 130 (Apr- Sep) |
Post MS project and Excel target hall schedule for beam schedule 130 see attachments 1,2
Update TH schedule 130 with TM3 jobs involved in.see attachments 4,5.
2016-04-29. Weekly update schedule according to changes. See attachments 6,7. |
Attachment 1: Target_Hall_shedule_130_Apr_to_Sep.pdf
|
|
Attachment 2: Target_Hall_shedule_130_Apr_to_Sep_2016.pdf
|
|
Attachment 3: Target_Hall_shedule_130_Apr_to_Sep.mpp
|
Attachment 4: Target_Hall_shedule_130_Apr_to_Sep.pdf
|
|
Attachment 5: Target_Hall_shedule_130_Apr_to_Sep.mpp
|
Attachment 6: Target_Hall_shedule_130_Apr_to_Sep.mpp
|
Attachment 7: Target_Hall_shedule_130_Apr_to_Sep.pdf
|
|
|
1222
|
Wednesday, May 04, 2016, 12:01 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule for beam schedule 130 (Apr- Sep) |
Update schedule weekly. See attachment 1,2,3. |
Attachment 1: Target_Hall_shedule_130_Apr_to_Sep_2016.pdf
|
|
Attachment 2: Target_Hall_shedule_130_Apr_to_Sep.mpp
|
Attachment 3: Target_Hall_shedule_130_Apr_to_Sep.pdf
|
|