Thursday, March 12, 2015, 13:33, Anders Mjos, South Hot-Cell, Standard Operation, TM1, ThO#1, Target inspection
|
Chad, Anders and Alex inspected the target this morning. The target had no significant visible damage to the container. Some material was deposited on
the Extraction Electrode.
Phots on DocuShare |
Tuesday, April 17, 2012, 10:15, chad fisher, South Hot-Cell, Standard Operation, TM1, Nb#6, Target inserted into south hot cell
|
Nb#6 has been inserted into the south hot cell in preparation for ionstallation onto TM1. During the pre-insertion inspection I noticed that I could
see the foil installed into the ionizer tube and that in did not seem to be seated or concentric to the tube itself. I had Anders and Friedhelm check this
and they deemed that it was ok. |
Tuesday, June 05, 2012, 12:20, Bevan Moss, South Hot-Cell, Standard Operation, TM1, Ta#38, Target inserted into HC
|
Ta#38 has been placed into the south hot cell. Swipes of the tool port were taken there was a count of 600 on the floor and 150 on the walls and top. |
Wednesday, February 02, 2022, 11:05, David Wang, Crane, Standard Operation, , , Target hall overhand crane annual insepection.
|
Tom Kauss finished target hall overhead crane annual inspection today. The crane works fine. He issued new inspection tag and e-logged the job.
|
Thursday, January 03, 2019, 13:41, David Wang, Crane, Repair, , , Target hall crane PLC issue.
|
Target hall crane did not work properly after power outage during Christmas time. The only movement could be operated is crane rotation. Power is supplied
crane. The control board on N-S, E-W and up-down movement showed F51 error code which is tripped limit.. All these clues pointed to a PLC control
problem. Don dale was asked for help. He used the crane control PLC program on an old computer in RH control room reset the PLC system. Everything |
Friday, January 27, 2023, 07:11, David Wang, Crane, Standard Operation, , , Target hall Crane annual inspection has beend done.
|
Tom Kauss inspected target hall crane yesterday. The crane works fine. Tom has this inspection record in his file. The inspection tag has been issued.
|
Friday, January 27, 2023, 07:15, David Wang, Crane, Standard Operation, , , Target hall Crane annual inspection has beend done.
|
Tom Kauss finished TH crane annual inspection yesterday. The crane woks fine. Tom has this inspection record in his file. The crane inspection
tag has been issued for 2023. |
Thursday, October 24, 2013, 15:43, Anders Mjos, South Hot-Cell, Standard Operation, TM4, Ta#41, Target conductance
|
The conductance check on the electrical check was found to be outside of accepted values for the TBHT at 7.0 mOhm. A successful attempt to reduce the
conductance was made by re-tightening the bolts on the TGHT legs in the SHC. Grant operated the manipulator and torqued the bolts to about 1/8 of a turn
with the air ratchet. The conductance across the TGHT (A-B) could be improved from 7.0 mOhm to 6.2 mOhm by re-tightening the bolts. The value is still |
Thursday, October 24, 2013, 15:54, Grant Minor, South Hot-Cell, Standard Operation, TM4, Ta#41, Target conductance
|
Anders Mjos wrote:
The conductance check on the electrical check was found to be outside of accepted values for the TBHT |
Friday, October 25, 2013, 14:09, Travis Cave, South Hot-Cell, Standard Operation, TM4, Ta#41, Target conductance
|
Anders Mjos wrote:
The conductance check on the electrical check was found to be outside of accepted values for the TBHT |
Monday, October 03, 2011, 11:54, chad fisher, South Hot-Cell, Standard Operation, TM1, UCx#2 - TaC#1, Target change UCx#2-TaC#1
|
UCx#2 has been removed from Tm1 and put in a bucket with a slow argon feed and a lid placed lossely on top.
TaC#1 ITW has been installed and is awaiting testing at the cell. |
Wednesday, November 06, 2024, 08:29, Aaron Tam, South Hot-Cell, Standard Operation, TM4, TiC#9, Target and Parasitic assemblies removal from TiC#9 17x
|
November 5, 2024 - Aaron Tam
TiC#9 HP-SIS removed from TM4
Top left fixing bolt shows signs of heating on it (Comparison photos attached Bolt_profile.jfif & Bolt_Tops.jfif)
|
Tuesday, September 10, 2024, 12:41, Aaron Tam, South Hot-Cell, Standard Operation, TM4, TiC#9, Target TiC#9 HP-SIS installed onto TM4   
|
September 9, 2024 - Aaron Tam
Water from waterline found puddled on source-tray and containment box.
Water was wiped up as much as possible, but
likely still in containment box
leaving to dry overnight
Target inserted into Hotcell with nuts for the parasitic target. |
Friday, August 16, 2024, 15:32, Aaron Tam, South Hot-Cell, Standard Operation, TM4, Ta#68 LP-SIS, Target Ta#68 loaded onto TM4
|
Target Ta#68 loaded onto TM4
-leak check passed
-Target electrode conductor screws torqued to 130 in-lbs |
Tuesday, October 01, 2024, 12:40, Aaron Tam, South Hot-Cell, Standard Operation, TM2, Ta#67, Target Ta#67 Removed from TM2 9x
|
October 1, 2024 - Aaron Tam
Ta#67 LP-SIS removed from TM2
Ta#67 is sitting in SHC awaiting PIE |
Monday, August 12, 2024, 15:55, Aaron Tam, South Hot-Cell, Standard Operation, TM2, Ta#67 LP-SIS, Target Loading
|
Ta#67 Target loaded onto TM2
Leak check passed
Electrical test passed after loosening off target electrode conductor screws, and torqueing by feel |
Wednesday, January 22, 2014, 15:20, Anders Mjos, South Hot-Cell, Standard Operation, , UC#8, Target Inspection - post beam
|
The Target Assembly was inspected with Chad, Jens Henning and Anders today.
The Target Container was broken.
Material was deposited on the Heat Shield around the Target Center Block
Material
was deposited on the IG-LIS source.
Electrical checks to ground (HS)
The Extraction Electrode passed the electrical |
Wednesday, September 02, 2015, 09:26, David Wang, ITE, Standard Operation, , , Target Hall schedule from Sep 08th 2015 to Dec 25th 2015    
|
I attach new Target Hall schedules here for 2015 fall and winter runs (beam schedule 129). The TH excel sheet schedule for beam 129 is included also.
Weekly update of Target Hall Schedule.See Attachments 3,4 |
Friday, September 25, 2015, 07:56, David Wang, Conditioning Station, Standard Operation, , , Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 
|
weekly update see attachment |
Tuesday, October 06, 2015, 13:25, David Wang, ITE, Standard Operation, TM4, , Target Hall schedule from Sep 08th 2015 to Dec 25th 2015 
|
Weekly update target hall schedule. See attachment 1,2. |
|