ID Date Author Category Type Module Target/Number Subjectdown
  2029   Thursday, November 14, 2019, 13:52 Travis CaveSpent Target VaultStandard Operation UC#22,23,24Targets repackaged

 The targets UC#22,23,24 have been repackaged into the newer stronger pails, and have been placed back in the mini vault with new numbers. See attached PDF for details.

Attachment 1: Target_Index_2019-11-14_Mini_Vault.pdf
Target_Index_2019-11-14_Mini_Vault.pdf Target_Index_2019-11-14_Mini_Vault.pdf
  2322   Thursday, May 19, 2022, 11:42 Travis CaveSpent Target VaultStandard Operation Sic#39, Ta#59, C#2, UC# 32 & 30Targets moved to the mini vault.

 Sic#39, Ta#59, C#2, UC# 32 & 30 have been moved from the spent target vault to the mini vault. See the attached pdf for details of the vaults.

Attachment 1: Target_Index_2022-05-19.pdf
Target_Index_2022-05-19.pdf
Attachment 2: Mini_Vault_Target_Index_2022-05-19.pdf
Mini_Vault_Target_Index_2022-05-19.pdf Mini_Vault_Target_Index_2022-05-19.pdf
  2592   Wednesday, May 15, 2024, 10:06 Travis CaveSpent Target VaultStandard Operation UC#38,40 Ta#62,63 SiC#44Targets moved to the mini vault.

 Targets UC#38,40 Ta#62,63 SiC#44 have been moved from the spent target vault to the mini vault in preparation for F-308 loading. See attached PDFs for details.

Attachment 1: Mini_Vault_Index_2024-05-15.pdf
Mini_Vault_Index_2024-05-15.pdf Mini_Vault_Index_2024-05-15.pdf
Attachment 2: Target_Index_2024-05-15.pdf
Target_Index_2024-05-15.pdf
  1653   Thursday, October 26, 2017, 13:20 Travis CaveSpent Target VaultStandard Operation SiC#30,ZrC#7,Ta#44,TiC#4, and Ta#41Targets moved to mini storage

SiC#30,ZrC#7,Ta#44,TiC#4, and Ta#41 have been moved from the spent target storage to the mini storage. See attached PDF for details of the orders of the pails in the mini vault.

Attachment 1: Mini_Vault_Storage_October_26_2017.pdf
Mini_Vault_Storage_October_26_2017.pdf Mini_Vault_Storage_October_26_2017.pdf Mini_Vault_Storage_October_26_2017.pdf Mini_Vault_Storage_October_26_2017.pdf
  594   Wednesday, February 05, 2014, 14:12 Travis CaveSpent Target VaultStandard Operation  Targets moved from mini storage to F-308s

All targets in the mini storage (4) have been moved from there and placed into the F-308s and those have been moved to the mech services room.

  681   Thursday, June 12, 2014, 09:42 Travis CaveSpent Target VaultStandard Operation  Targets moved from mini storage to F-308s

Five targets have been moved from the spent target storage to the mini storage. The targets that were moved are UCx #'s 6,7,8 , SiC #28, and Nb #6.

Attachment 1: Vault_Storage_June_12_2014.pdf
Vault_Storage_June_12_2014.pdf Vault_Storage_June_12_2014.pdf Vault_Storage_June_12_2014.pdf Vault_Storage_June_12_2014.pdf
Attachment 2: Mini_Vault_Storage_June_12_2014.pdf
Mini_Vault_Storage_June_12_2014.pdf Mini_Vault_Storage_June_12_2014.pdf Mini_Vault_Storage_June_12_2014.pdf Mini_Vault_Storage_June_12_2014.pdf
  1908   Thursday, April 18, 2019, 10:04 Travis CaveSouth Hot-CellMaintenance Ta#50, SiC#34, Ta#46, Ta#47, and Ta#45Target transfer from old pail to new pail.

 Targets Ta#50 and SiC#34 have been transferred from their old pails to new ones. Ta#50 was done on April 12th 2019 it was moved from pail #148 to pail #200 and a new field measurement was done and found to be 3.57mSv/hr. SiC#34 was done on April 18th 2019 it was moved from pail #143 to pail # 206 and a new field measurement was done and found to be 2.20mSv/hr. Both measurements were done by the RAM that is mounted at the south hot cell.

 

April 24 2019

Target Ta#46 has now been transferred to a new pail with a number 207 from pail 143 it was 3.62 mSv/hr when removed from the south hot cell.

 

April 25 2019

Target Ta#47 has now been transferred to a new pail with a number 201 from pail 137 it was 2.25mSv/hr when removed from the south hot cell. The bag that the target was in has shown signs of degradation.

Target Ta#45 has now been transferred to a new pail with a number 202 from pail 124 it was 1.45mSv/hr when removed from the south hot cell. The bag that the target was in was destroyed. Also in the pail was a shutter, IMG Gauge, some altem parts, wire and bolts.

The extraction electrode from Ta#47 was added to this pail as it was left behind from last transfer.

  499   Tuesday, October 08, 2013, 14:58 Anders MjosSouth Hot-CellStandard Operation SiC#29Target to Heat Shield electrical short

The SiC#29 CTL target has been taken apart with the help of Isaac and Chad. Electrical measurements were done between Target and Heat Shield as the target was disassembled. Work was done on October 2nd, 4th, 7th and 8th.

The megger showed about 30kOhm at 50V with the following changes

  • Bolts for CTL block loosened
  • Above bolts removed
  • CTL block pulled away from Heat Shield
  • CTL block removed
  • Heat Shield lid removed
  • Bolts for target removed
  • Shims between target and insulators

The megger showed about 50kOhm at 100V with the following changes

  • Target removed. Measured between cathode restraint and HS.

The megger showed OL at 540V with No 3 insulator removed. A measurement on No 3 insulator while it was sitting on the HS showed 70kOhm at 120V confirming that the insulator can no longer hold voltage.

While taking off the coil retainer plate, Chad noticed that all bolts were not tight.

Photos are available on DocuShare.

  66   Thursday, January 05, 2012, 11:40 Travis CaveSpent Target VaultStandard Operation  Target swapping

Looks like the UC target s #1 and #2 were found invalidprize winners for their all inclusive trip to Chalk River and have thus been placed back in to storage for the next draw. In their place a pair of lucky Ta targets won, seems to be Ta lucky draw this year, Ta#28 and #29 have been placed in the mini storage for several fabulous day and wondrous nights, before being whisked away on their all inclusive one way trip to Chalk River. See attachments for the status of both vaults.

Attachment 1: Vault_Storage_January_5_2012.pdf
Vault_Storage_January_5_2012.pdf Vault_Storage_January_5_2012.pdf Vault_Storage_January_5_2012.pdf Vault_Storage_January_5_2012.pdf
Attachment 2: Mini_Vault_Storage_January_5_2012.pdf
Mini_Vault_Storage_January_5_2012.pdf Mini_Vault_Storage_January_5_2012.pdf Mini_Vault_Storage_January_5_2012.pdf Mini_Vault_Storage_January_5_2012.pdf
  2300   Tuesday, January 25, 2022, 12:49 David WangITE/ITWStandard Operation  Target station vacuum system visual inspection.

Two shielding blocks  above vacuum station at TH west end were opened for inspection. Checked ITH:MP1, MP2 lubricant color and level through sight gauge on pumps. They are still ok.  Restored the shielding blocks.  Checked ITM:MP1 by decay tank (Mirror checked  sight gauge by north wall). Added lubricant to ITM:MP1 to middle level on sight gauge.  

  2709   Thursday, October 24, 2024, 10:42 Travis CaveSpent Target VaultStandard Operation SiC#44Target repacked moved to the mini vault.

 On October 22 2024 the spent SIC#44 returned from CNL was repacked in a new pail it was in pail 275 and repacked into pail 298 it was 2.34mSv/hr when removed from the south hot cell.

It was placed in the very back of the mini vault. 

Attachment 1: Mini_Vault_Index_2024-10-24.pdf
Mini_Vault_Index_2024-10-24.pdf Mini_Vault_Index_2024-10-24.pdf
  2582   Friday, May 03, 2024, 12:20 Travis CaveSpent Target VaultStandard Operation Ta#66Target repacked

 The Ta#66 target was repacked after the parasitic target was removed it was place in a new pail (#290) and place back in spot 5B of the vault. See attached PDF for further details.

Attachment 1: Target_Index_2024-05-03.pdf
Target_Index_2024-05-03.pdf
  2685   Wednesday, September 18, 2024, 13:40 Aaron TamSouth Hot-CellStandard OperationTM3TiC#8Target removal

 TiC#8 HP FEBIAD removed from TM3

Target sitting in SHC

1 Coil Conductor bolt fell under source tray 

Photo Dump uploaded

Attachment 1: Cover_Outside.jfif
Attachment 2: Cover_Inside.jfif
Attachment 3: Arc_Sign_(as_seen_before).jfif
Attachment 4: Arc_Sign_2_(as_seen_before).jfif
Attachment 5: View_High.jfif
Attachment 6: Bolts_Removed.jfif
Attachment 7: Source_Tray_no_target.jfif
Attachment 8: Taget_Bottom.jfif
Attachment 9: Target_Left.jfif
Attachment 10: Target_Top.jfif
Attachment 11: Target_right.jfif
Attachment 12: Camera_Angle_2.jfif
Attachment 13: Bolt_location_2.jfif
  1763   Wednesday, August 01, 2018, 15:12 Anders MjosSouth Hot-CellStandard OperationTM2UC#23Target mounted - water leak on HS line

The heat shield water lines were not purged ahead of target exchange in the hot cell. This resulted in water leaking onto the new target assembly (heat shield) when the cooling lines were opened at top and bottom (for connecting leak detector). Excess water was wiped up with paper towels.

Attachment 1: 20180801_180130904_iOS.jpg
20180801_180130904_iOS.jpg
  1436   Thursday, February 09, 2017, 09:24 David WangConditioning StationDevelopment  Target module window cooling lines at TCS.

Target module window  cooling lines at TCS has been modified to use spare 2 channel in TCS: WFB1. The old cooling lines used a spare channel in TCS WFB2(HVC channel) are removed and capped. After change, TCS window cooling lines will be interlocked with heaters. The test run on new lines are good. No leak  on all fittings, and signals on flow and temperature are good.   Control people will be noticed on this change for their following up job.

  1685   Tuesday, February 13, 2018, 13:54 Anders MjosITEStandard OperationTM4SiC#37Target module disconnected

TM disconnected by David and Yasmine Feb 8th

  1686   Tuesday, February 13, 2018, 13:56 Anders MjosITWStandard OperationTM2Ta#55Target module disconnected

TM disconnected by David and Yasmine Feb 8th. One of the water couplings were leaking for a short while when disconnected. NCR 10836 submitted by Max

  1753   Monday, July 16, 2018, 17:41 Anders MjosITEStandard OperationTM4UC#22Target module disconnected

The water and electrical connections were disconnected today as protons remained off after power interruption during the weekend. Vacuum is still connected and operating.

 The vacuum system are disconnected 2018-07-17.  See attachment .

Attachment 1: TM4_UCx_22#__disconnection_check_list_1.pdf
TM4_UCx_22#__disconnection_check_list_1.pdf
Attachment 2: TM4_UCx_22#__disconnection_check_list_2.pdf
TM4_UCx_22#__disconnection_check_list_2.pdf
  1817   Monday, November 05, 2018, 14:27 Anders MjosConditioning StationStandard OperationTM2UC#25Target module disconnected

Frank and Anders disconnected the water and electrical connections this afternoon after the target was conditioned over the weekend. The heater ramping program ran with the wrong gauge selected, causing the vacuum to go higher than planned. The module will be moved to ITW tomorrow.

  223   Wednesday, December 05, 2012, 15:53 Anders MjosSouth Hot-CellStandard Operation UCx#5Target inspection - target tube broken

The target was inspected today.

It was found that the target tube had broken on both sides of the centre block in the region that contain target material. The Ta-foil heat shield was removed from the let side tube to allow inspection.

Photos can be found on DocuShare:
https://documents.triumf.ca/docushare/dsweb/View/Collection-9357