Message ID: 1908     Entry time: Thursday, April 18, 2019, 10:04
Author: Travis Cave 
Category: South Hot-Cell 
Type: Maintenance 
Module:  
Target/Number: Ta#50, SiC#34, Ta#46, Ta#47, and Ta#45 
Subject: Target transfer from old pail to new pail. 

 Targets Ta#50 and SiC#34 have been transferred from their old pails to new ones. Ta#50 was done on April 12th 2019 it was moved from pail #148 to pail #200 and a new field measurement was done and found to be 3.57mSv/hr. SiC#34 was done on April 18th 2019 it was moved from pail #143 to pail # 206 and a new field measurement was done and found to be 2.20mSv/hr. Both measurements were done by the RAM that is mounted at the south hot cell.

 

April 24 2019

Target Ta#46 has now been transferred to a new pail with a number 207 from pail 143 it was 3.62 mSv/hr when removed from the south hot cell.

 

April 25 2019

Target Ta#47 has now been transferred to a new pail with a number 201 from pail 137 it was 2.25mSv/hr when removed from the south hot cell. The bag that the target was in has shown signs of degradation.

Target Ta#45 has now been transferred to a new pail with a number 202 from pail 124 it was 1.45mSv/hr when removed from the south hot cell. The bag that the target was in was destroyed. Also in the pail was a shutter, IMG Gauge, some altem parts, wire and bolts.

The extraction electrode from Ta#47 was added to this pail as it was left behind from last transfer.

ELOG V2.9.2-2455