304
|
Wednesday, April 17, 2013, 15:17 |
Bevan Moss | Conditioning Station | Standard Operation | TM3 | N/A | Turbo Pumps Failed | Both Turbo pumps on TM3 have failed.
They were both attempted to start in soft
mode. TP2 could only achieve ~19kpm and TP1 |
|
|
305
|
Friday, April 19, 2013, 10:48 |
Bevan Moss | Conditioning Station | Maintenance | TM3 | N/A | Turbo Pump 2 replaced | Turbo Pump 2 has been replaced on
TM3. I got a count of 350 on the sleeve of
my tank suit. |
|
|
306
|
Friday, April 19, 2013, 10:48 |
Bevan Moss | Conditioning Station | Maintenance | TM3 | N/A | Turbo Pump 2 replaced | Turbo Pump 2 has been replaced on
TM3. I got a count of 350 on the sleeve of
my tank suit. |
|
|
39
|
Tuesday, October 25, 2011, 16:57 |
Bevan Moss | Conditioning Station | Standard Operation | TM4 | | Turbo Pump 1 issues | Roughing on TM1 started at ~15:00 today
by ~16:30 the module had reached a pressure
of ~200 mTorr and the turbo pumps were turned |
|
|
267
|
Monday, March 18, 2013, 12:03 |
Bevan Moss | Conditioning Station | Repair | TM4 | CS Test Target #1 | Turbo Pump 1 Failure and Venting | Over the weekend Turbo pump one failed.
It was attempted to restart the turbo in
soft start but that also failed. Although |
|
|
271
|
Tuesday, March 19, 2013, 13:49 |
Bevan Moss | Conditioning Station | Standard Operation | TM4 | CS Test Target #1 | Tubros Started | Turbo Pumps have been started and
are in normal operation. TP1 which has recently
been replaced was started in soft start and |
|
|
41
|
Friday, October 28, 2011, 09:30 |
chad fisher | South Hot-Cell | Repair | TM4 | | Tube Heater + Leak Check C.B. | Base Pressure: 0.0x10-4
Stable Leak Rate: 0.0x10-9
Leak check of tube heater circuit, |
|
|
1675
|
Thursday, January 04, 2018, 13:28 |
Anders Mjos | Conditioning Station | Maintenance | | | Troubleshooting IG1S | TCS:IG1S is reporting vacuum levels that
seem to be too low (1E-10 to 1E-8 Torr).
The gauge was connected to the controller |
|
|
1896
|
Thursday, March 21, 2019, 09:56 |
chad fisher | South Hot-Cell | Repair | TM2 | | Tray insertion | This morning new water block fasteners
and gas line capture nut fasteners were inserted
into the hot cell. Window waterline blank |
|
|
1883
|
Tuesday, March 05, 2019, 14:29 |
chad fisher | South Hot-Cell | Repair | | | Tray Transfer Fixture Repair Complete | Repair of the tray transfer fixture is
complete (minus testing).
A distorted ball nut lock plate was |
|
|
199
|
Wednesday, October 31, 2012, 11:24 |
David Wang | ITE | Standard Operation | TM4 | | Transfer five shielding blocks from ITW to ITE. | Bevan and I transferred five shielding
blocks from ITW to ITE. ITE is ready for
taking proton beam. |
|
|
1882
|
Tuesday, March 05, 2019, 09:38 |
chad fisher | South Hot-Cell | Repair | | | Transfer Fixture Repair | Transfer fixture has been remotely disassembled
to the point where the ball nut lock plate
assembly can be inserted into the tool port |
|
|
1048
|
Wednesday, August 26, 2015, 09:54 |
Anders Mjos | Conditioning Station | Maintenance | | | Topped up water in TCS:TK2 | Filled to 24.9 in |
|
|
1233
|
Monday, May 16, 2016, 10:48 |
Anders Mjos | Conditioning Station | Maintenance | | | Topped up water in TCS:TK2 | Filled from 15 to 25 in |
|
|
2527
|
Monday, January 22, 2024, 10:16 |
David Wang | ITE | Standard Operation | TM4 | UCx# | Tm4 waterlines helium pressure test and TM service cap helium leak check. | Tm4 waterlines helium pressure test and
TM service cap helium leak check was done
last Friday. All water lines were pressurized |
|
|
1714
|
Tuesday, May 15, 2018, 10:21 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Tm4 water circles helium pressur test result |
Helium pressure test on TM4 water lines
is done this morning. 70 psi helim , 1 minutes |
|
|
2534
|
Friday, January 26, 2024, 11:53 |
David Wang | Safe Module Parking | Standard Operation | TM4 | | Tm4 has been moved to SMP. | TM4 has been moved to SMP. The move is
smooth. I started SMP vacuum pump. The TM4
and SMP vessel is under vacuum now. |
|
|
2601
|
Tuesday, May 28, 2024, 10:13 |
David Wang | ITW | Standard Operation | TM4 | UCx#45 | Tm4 has been moved from TCS to ITW. | Tm4 has been moved from TCS to ITW.
the move is smooth. |
|
|
2651
|
Friday, August 09, 2024, 18:18 |
David Wang | ITW | Standard Operation | TM4 | TiC#7 | Tm4 has been moved from ITW to SMP. | Tm4 has been moved from ITW to SMP. the
move is successful. |
|
|
2594
|
Tuesday, May 21, 2024, 11:46 |
David Wang | ITW | Standard Operation | TM4 | LP febiad empty. | Tm4 has been moved from ITW to SHC. | Tm4 has been moved from ITW to SHC. the
move is smooth. |
|