Entry  Friday, January 27, 2017, 08:44, chad fisher, South Hot-Cell, Standard Operation, TM2, Ta#50, UCx #18 - Ta Feibiad Dummy installed. Target Change Waterline interference TM2_Waterline_interference.jpg
On Tuesday, January 24th UCx#18 was removed from TM2 and Ta febiad dummy installed. I encountered the same issue mounting the new target as last time.
Was able to determine that the issue is the routing of the waterlines to the right-hand (as viewed from the operator) high current tube heater. The lines
interfer the the target mounting plate (bottom right hand corner).
Entry  Tuesday, June 30, 2015, 12:37, chad fisher, South Hot-Cell, Standard Operation, TM1, UCx#12, UCx #12 Removal 
UCx#12 has been removed from TM1 and placed in a pail with argon.
Right leg (B) of target is clearly broken.
Containment Box cover re-installed and module ready to move.
Entry  Wednesday, August 04, 2021, 17:24, David Wang, North Hot-Cell, Standard Operation, TM2, UCx34#, UCX 34# on TM2 electical check and HS leak check at NHC. UCX34_TM2_electrical_check.pdf
The job is done with Matt at NHC. All TGHT and TBHT bolts are torque wrench tight in NHC. HS leak check result is good.
helium pressurized HS line at TCS. No leak. 
Entry  Thursday, April 24, 2025, 12:53, Aaron Tam, North Hot-Cell, Standard Operation, TM4, UC#48, UC#48 IGLIS Install onto TM4 Misaligned_target_leg.jpg86b48e1a-3507-4650-864b-841e638ab62e.jpg
C. Fisher, A. Schmidt, A. Tam
UC#48 Handover satisfactory

    Target taken out of glovebox and tested for fit
    The left most triplet conductor leg was seen to be slightly misaligned,
Entry  Tuesday, November 26, 2024, 14:52, Aaron Tam, South Hot-Cell, Standard Operation, TM3, UCx#47 , UC#47 LP-SIS w/ gas Install 6x
 November 26, 2024 - Aaron Tam 
Handover from TPO and inspection

    Completed
    Some modification to the center Inner-Outer conductor had to be made (hole enlarged as tab was slightly short)

Target
Entry  Monday, March 12, 2012, 10:03, chad fisher, South Hot-Cell, Standard Operation, TM1, UC#3, UC#3 Removal IMG_0610.JPGIMG_0616.JPG
UC#3 was removed from TM1 this morning. Upon removing the oven heater bolts BOTH legs fell demonstrating that both sides of the oven tube have
broken off from the central block.
Target was put into a can under argon for disposal after the module is removed from the cell.
Entry  Thursday, February 06, 2020, 13:31, Adam Newsome, Spent Target Vault, Standard Operation, , UC#29, UC#29 moved to vault location 6A, in pail 225 
 UC#29 in pail 225 was moved to the storage vault, location 6A. Field measured at 22.4 mSv/hr at ~1m. 
Entry  Wednesday, May 01, 2019, 07:49, chad fisher, South Hot-Cell, Standard Operation, TM4, UC#26, UC#26 removal 20190501_072940[1].jpg
UC#26 has been removed from TM4.
Entry  Monday, June 26, 2017, 11:47, chad fisher, South Hot-Cell, Standard Operation, TM4, Ta#52, UC#20 Removed Ta#52 installed 
UC#20 has been removed from TM4 and put in a bucket back-filled with argon. Ta#52 has been installed onto TM4 with new fasteners. High current torqued
to 130 in lbs.
Entry  Tuesday, May 16, 2017, 13:23, chad fisher, South Hot-Cell, Standard Operation, TM4, UC#20, UC#20 Installed 
UCx#19 has been removed from TM4 and UCx#20 installed.
UCx#19 still had water in it at pressure and sprayed when the VCR was undone. It was quickly re-tightened but not before significant water pooled
beside the main Mykroy standoff and table. Contacted Anders would suggested to soak it up with some wipes and continue, which I did.
Entry  Tuesday, August 02, 2016, 13:32, chad fisher, South Hot-Cell, Standard Operation, TM4, UC#16, UC#16 Removed #17 installed 
UCx#16 has been removed from TM$ and UCx#17 installed, high current conductors toqued to 130 in lbs.
 
UCx#16 did not show the standard arcing marks on the 9 pin connector.
Entry  Tuesday, April 21, 2015, 17:14, Isaac Earle, South Hot-Cell, Standard Operation, TM1, UC#12, UC#12 Installed in TM1 IMG_4836.JPGIMG_4833.JPG
On Friday April 17th, UC#12 target was installed in TM1.  One of the copper water lines was bent slightly as the target was lifted into the module
which caused ~15 minute delay due to difficulty getting the VCR nut threads to engage.  Other than this the install went smoothly.
During replacement of the containment box panel two of the threaded holes were found to be stripped.  One on the top at the center, the other
Entry  Thursday, March 08, 2018, 14:10, David Wang, ITW, Maintenance, , , Two small water leak has been found in ITW.  
Two small water leaks have been found on ITW High active water system.  One is from an unused 1/4" copper valve stem. another is on supply 1.5"
 supply line valve body top sealing. Both of them are seeping water from  seal. 1/4" copper valve will be replaced with a new one. 1.5" supply
 line valve will be replaced by an old valve with all new seals. I have  all spare parts in hand.  At present, water supply to ITW are stooped to
Entry  Wednesday, March 01, 2023, 09:27, David Wang, Cooling, Maintenance, , , Two filters on HALCW resin circuit have been replaced.  
Two filters on HALCW resin circuit have been replaced. O-ring 235# were changed on both filter cartridge houses.  25micron  10"x 2.5"
3M cartridge new filters  are used. Old filters are not very dirty. They are bagged and stored in vacuum pit. Residual water from cartridge houses
are collected and stored in high active storage jug with sealed cap.  No leak on resin circuit before and after the job. 
Entry  Tuesday, April 01, 2025, 09:47, Frank Song, North Hot-Cell, Repair, , , Two NHC light bulbs replacement Image_(3).jpgImage_(4).jpgImage_(5).jpgImage_(6).jpgImage_(7).jpg
2 broken lights of NHC were replaced in Target Hall. see pics attached.
Entry  Monday, April 04, 2022, 10:44, Nadia Jorgenson, South Hot-Cell, Repair, , , Turntable Chain Repair Hot_Cell_Chain_1.jpgHot_Cell_Chain_2.jpg
 Last week we repaired the South Hot Cell turntable chain/sprocket. Chain was loose
and there was a few section where the chain was not lining up properly with the sprockets.
3 issues were discovered:
Entry  Tuesday, September 05, 2017, 06:33, David Wang, Conditioning Station, Standard Operation, TM4, , Turned off TCS water system and vacuum system. 
Argon vent and disconnect TM4 at TCS.
Entry  Monday, July 10, 2017, 10:19, David Wang, Conditioning Station, Standard Operation, TM4, , Turned off TCS water system 
Prepare for TM4 move tomorrow morning.
Entry  Thursday, September 24, 2015, 07:00, David Wang, Conditioning Station, Maintenance, TM4, Ta#46, Turned off TCS all vacuum pumps and water pumps. 
TCS:MP1 back up pressure went up too high (700mtorr).I turned off all the pumps.The TCS is under vacuum still. TCS water  package cooling fans showed
error on control page.The water pumps are stopped  also.
Restarted the vacuum pumps 40 minutes after stopping. Everything is back to normal. The MP1 back up pressure need to be monitored frequently before
Entry  Tuesday, December 01, 2015, 06:41, David Wang, Conditioning Station, Standard Operation, TM4, UC#14, Turned off TCS all vacuum pumps and water pumps. 
I turned off TCS vacuum and water pumps. The TSC and TM4 are still under vacuum condition.