Message ID: 2802     Entry time: Wednesday, May 07, 2025, 13:41
Author: Aaron Tam 
Category: North Hot-Cell 
Type: Standard Operation 
Module: TM2 
Target/Number: UC#49  
Subject: UC#49 SIS w/ Gasline Install 

May 7th, 2025 - Aaron Schmidt, Aaron Tam 

UC#49 Handover - good

  • April 30th - Initial fit check was performed
    • This is a new procedure that allows time for any potential modifications to be made. 
  • May 7th ~9:00am Target taken out of glovebox and tested for fit
  • Target legs and mounting bolts all thread in nicely. Bottom 2 conductor leg mounting holes have slightest misalignment.
  • Target bagged, and brought to ISAC Hot-cells anteroom

Target inserted into NHC - successful

  •  Target loaded onto cart without issue

Target Install - Complicated 

  • Gas line gasket dislodged upon fully inserting target onto source-tray guide-pins
  • During the attempt to remove target from source-tray, East manipulator tong cable hopped off a pully
    • This is the same slave manip that was recently replaced ID: 2799 
  • Attempts to reinstall the gasket proved unsuccessful, and gasket was ultimately lost under the source-tray
  • 3 more gaskets were inserted into the Hot cells, with the same unsuccessful outcome
    • gaskets lost underneath source-tray
  • One attempt to install a side loading gasket was tried
    • stopped after the first try as the tool is liable to fling the gasket to a critical area 
  • Aaron Schmidt made a new tool to install a male-side gasket
    • This proved to be successful (photo shown)
  • The rest of the install procedure was successful 
    • without the East manipulator functional, west manipulator was used
    • west manipulator has a smaller tong opening to avoid cable hopping 
    • Finishing at 3:00pm UC target exposed to air for ~6 hours

 

Attachment 1: Cable_hopped_on_East_Manip.jpg  116 kB  | Show | Hide all
Attachment 2: unsuccessful_method_1.jpg  132 kB  | Show | Hide all
Attachment 3: unsuccessful_method_2.jpg  128 kB  | Show | Hide all
Attachment 4: Gasline_Gasket_installed.jpg  120 kB  | Show | Hide all