Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ISAC, Page 15 of 139  Not logged in ELOG logo
ID Date Author Category Typedown Module Target/Number Subject Text Attachments
  392   Tuesday, July 02, 2013, 10:58 Travis CaveConditioning StationStandard OperationTM1UC#6module moveTM#1 with UC#6 has been moved from the
conditioning station to the west target station,
move went well.
  
  393   Wednesday, July 03, 2013, 08:43 chad fisherSouth Hot-CellStandard Operation  Ta#39 Transfered to spent target storage vault    
  394   Wednesday, July 03, 2013, 08:44 chad fisher, Travis CaveSouth Hot-CellStandard Operation  Ta#39 Transfered to spent target storage vaultTa#39 has been transferred to spent target
storage vault. Ta#39 was placed into pail
#106 and placed into spot of 4C of the spent
 Vault_Storage_July_3_2013.pdf 
  395   Wednesday, July 03, 2013, 10:43 Travis CaveSouth Hot-CellStandard OperationTM3no targetmodule moveTM#3 with no target and no source tray
was moved from the north east silo to the
south hot cell the move went well.
  
  396   Thursday, July 04, 2013, 11:37 David WangITWStandard OperationTM1UCxI reconnected TM1 to ITW. I  reconnected TM1 to ITW on
02 July.The pumping down is good so far.
TM1 water interlock check is good also.
  
  398   Friday, July 05, 2013, 10:02 Bevan MossConditioning StationStandard OperationTM3No source trayTM3 module move to TCSTM3 has been moved from the south hot cell
to the conditioning station. David and I
completed the move. All went well.
  
  399   Tuesday, July 09, 2013, 14:26 David WangITWStandard OperationTM1UCx5 shielding blocks had been transferred from ITE to ITW5 shielding blocks had been  transferred
from ITE to ITW.  The  ITW is configured
to take proton beam.
  
  400   Tuesday, July 16, 2013, 13:09 David WangITEStandard OperationTM4 TM4 has been disconnected in ITE.TM4 has been disconnected in ITE. All water
lines on TM4 have been purged. ITE is venting
now.
  
  403   Thursday, July 18, 2013, 10:08 Travis CaveConditioning StationStandard OperationTM3no targetmodule moveTM#3 with no target and no source tray
has been moved from the conditioning station
to the north east silo, move went well.
  
  404   Monday, July 22, 2013, 15:52 Bevan MossConditioning StationStandard OperationTM3No Source TrayHV testing update   I have fallen behind on the
HV testing that has been completed on TM3.
Data can be found on docushare in the TM3
  
  405   Tuesday, July 23, 2013, 10:55 Travis CaveITEStandard OperationTM4Ta#40module moveTM#4 with Ta#40 has been moved from the
east target station to the south hot cell
move went well.
  
  406   Tuesday, July 23, 2013, 13:33 Travis CaveSouth Hot-CellStandard OperationTM4Ta#40Electrical checkResults of electrical check on Ta#40 target
on TM#4 post beam at the south hot cell
 TM#4_Ta#40_SIS_Tgt_Elec_Chk_post.PDF 
  407   Wednesday, July 24, 2013, 08:40 Travis CaveSouth Hot-CellStandard OperationTM4SiC#29Electrical checkElectrical check on TM#4 with SiC#29 has
been done. The reading of the magnet coil
and 60kV common is low at 750 ohms, normally
 TM#4_SiC#29_FEBIAD_Tgt_Elec_Chk.PDF 
  408   Wednesday, July 24, 2013, 14:40 Travis CaveConditioning StationStandard OperationTM4SiC#29module moveTM#4 with SiC#29 has been moved from the
south hot cell to the conditioning station
move went well.
  
  409   Wednesday, July 24, 2013, 17:46 David WangConditioning StationStandard OperationTM4Sic 29#Started 3 turbo pumps on CS for TM43 turbo pumps on TM4 and CS have been started.
The pumping down is good so far, The TM4
PNG1 reading is more than 10 times higher
  
  410   Thursday, July 25, 2013, 09:37 Travis CaveConditioning StationStandard OperationTM4SiC#29Electrical checkElectrical check of TM#4 with SiC#29 attached.
Results are pretty much the same as yesterday
for the coil to 60kV common, and anode to
 TM#4_SiC#29_FEBIAD_TgtElecChkCS_.PDF 
  411   Thursday, July 25, 2013, 10:08 David WangConditioning StationStandard OperationTM4SiC #29TM4 HS helium pressure test andTM4 connection at CSBevan and I did a helium pressure test
on TM4 HS water circuit at CS. The leak detector
is pumped to the bottom scale(E-9 atm.cc/sec
  
  412   Friday, July 26, 2013, 11:06 David WangSouth Hot-CellStandard Operation  The steel shielding plug has been put on theSHC top in target hallto reduce the radioactive shining from 
SHC Ta# 40 target.
  
  413   Monday, July 29, 2013, 14:32 Travis CaveSpent Target VaultStandard Operation Ta#40Spent target moveSpent target Ta#40 has been placed into
storage. The target was placed in pail #107
and was put into slot 5A of the vault. It
 Vault_Storage_July_29_2013.pdf 
  414   Tuesday, July 30, 2013, 10:44 Travis CaveITEStandard OperationTM4SiC#29module moveTM#4 with SiC #29 has been moved from the
conditioning station to the east target station,
move went well.
  
ELOG V2.9.2-2455