Entry  Friday, May 18, 2012, 08:17, chad fisher, South Hot-Cell, Standard Operation, TM4, SiC#27, SiC#27 Installed 
SiC#27 has been installed onto TM4. Fit was very good. All electrical connections double checked with mirror.
Pictures can be found at: http://documents.triumf.ca/docushare/dsweb/View/Collection-8530
 
Entry  Friday, May 18, 2012, 08:29, Travis Cave, South Hot-Cell, Standard Operation, TM4, SiC#27, Electrical check TM#4_SiC#27_pre_beam.PDF
TM#4 with SiC#27 has had its electrical check. See attached PDF for details.
Entry  Friday, May 18, 2012, 08:37, David Wang, South Hot-Cell, Standard Operation, TM4, sic 27, leak check on heat shield circuit 
Chad and I leak checked the heat shield circuit after sic 27 target  installed. It took 20minutes  to pump down the circuit to the leak
detector bottom scales. The leak detector is calibrated today,and all the vacuum lines and connections are leak checked by spraying helium. Chad sprayed
helium to each vc fittings for 2 seconds. There is no any response on leak detector . The test repeated one time and the result is same. Chad flushed 
Entry  Tuesday, June 05, 2012, 12:20, Bevan Moss, South Hot-Cell, Standard Operation, TM1, Ta#38, Target inserted into HC 
Ta#38 has been placed into the south hot cell. Swipes of the tool port were taken there was a count of 600 on the floor and 150 on the walls and top. 
Entry  Wednesday, June 06, 2012, 13:36, chad fisher, South Hot-Cell, Standard Operation, TM1, Ta#38, Target Change Nb#6 - Ta#38 
Nb#6 was removed from TM1...it looked very clean.
Ta#38 was installed onto TM1...fit well.
Isaac Earle did this change with supervision in an effort to cross train.
Entry  Wednesday, June 06, 2012, 14:33, David Wang, South Hot-Cell, Standard Operation, TM1, Ta38, leak check heat shield circuit 
Chad and I did a leak check on heat shield circuit after target is installed on TM1.The leak detector pumping down is smooth. The base leak rate is 0.0xE-9
atm.cc/sec. The base pressure is 0.0xE-4torr. Chad checked helium flow downstairs and sprayed helium to each joints for 2 seconds.The first joints is good
and there is no any response on leak detector.we double checked it again and got the same result. On the second joint, Chad sprayed helium 2second. After
Entry  Friday, June 08, 2012, 15:00, Don Jackson, South Hot-Cell, Standard Operation, TM1, Nb#6, Electrical Check Nb#6 at end of run Nb#6_End_of_Run.JPG
Megger check values were low but still within operational range.
Entry  Friday, June 08, 2012, 15:03, Don Jackson, South Hot-Cell, Standard Operation, TM1, Ta38, Electrical Check on new Ta38 at hot cell Ta38_New_Target.JPG
Megger checks were exceptionally high (good).  Readings taken less than 2 hours after reading low values from end of run on Nb#6.  Tests
on Ta38 will be repeated at conditioning station later.
Entry  Wednesday, June 20, 2012, 11:39, Grant Minor, South Hot-Cell, Development, TM3, N/A, TM3 Planned Activites at South Hot Cell Jun 20 to 29 2012 


Normal
0




false
false
false

EN-CA
X-NONE
X-NONE

Entry  Thursday, June 21, 2012, 14:00, Travis Cave, South Hot-Cell, Repair, TM3, no target, module move 
TM#3 has been moved from the south west silo to the south hot cell for the start of its second refurb/repair. The fields of the module when it was lowed
in was 2msv/hr.
Entry  Thursday, June 21, 2012, 14:30, chad fisher, South Hot-Cell, Repair, TM3, N/A, TM3 Refurbishment Start 
Started refurb of TM3.
Planned activities:
Inspection
Entry  Thursday, June 21, 2012, 14:33, chad fisher, South Hot-Cell, Repair, TM3, N/A, Pictures TM3 June 21st 8x
Here are the pictures from today...there is video too but it is not uploaded yet.
Entry  Monday, June 25, 2012, 07:53, chad fisher, South Hot-Cell, Repair, TM3, N/A, TM3 Refurb. Work 
On Friday, June 22 the following work was carried out.

    Further inspection of the source tray.
    Testing of existing tray removal and installation tool...it works fine, there was
just a specific method for proper coupling to the target module. There was no documentation for this tool, so it took a little bit of insight with
Entry  Tuesday, June 26, 2012, 14:10, David Wang, South Hot-Cell, Repair, TM3, , TM3 heat shield and window circuits leak check is done. 
Chad and i did a leak check on TM3 heat shield and window circuits.Both circuits are pumped easily down to the bottom leak rate and base pressure on
the leak detector. There are two VCR caps on heat shield circuit. Chad sprayed helium on both of them   ( tested individually,2 seconds every time
) . There is no response on leakdetecor during 45 seconds waiting time. On window circuit there are 2 VCR joints. Chad sprayed helim on these joints(2seconds
Entry  Tuesday, July 03, 2012, 12:26, Travis Cave, South Hot-Cell, Standard Operation, TM4, SiC#27, module move 
TM#4 with SiC#27 moved from the east station to the south hot cell. Fields at East MAA were 127mSv/hr and the fields at the south hot cell was 77.5 mSv/hr.
Entry  Wednesday, July 04, 2012, 11:33, Travis Cave, South Hot-Cell, Standard Operation, TM4, UO#3, Electrical check TM#4_UO#3_elec_check.PDF
Electrical check of TM#4 with  UO#3 attached at the south hot cell see attached PDF for full results. It has been noted that the Anode to 60kV common
is of a low value after consulting with Friedhelm Ames it was determined will will run with what we have.
Entry  Wednesday, July 18, 2012, 16:49, Grant Minor, South Hot-Cell, Development, , , South Hot Cell Ventilation Alarm Trip 
Today (Wednesday July 18th) at around 4:15 pm I was taking a small tour  group from VECC into the Target Hall.  In the process of discussing the  mechanical
design of the Target Modules and South Hot Cell turntable I  inadvertently lifted the Aluminum Hatch Cover of the Hot Cell about 2  inches in an effort
to explain something.  This tripped the ventilation  alarm before I realized what I was doing.  I evacuated the visitors from  the Target Hall, checked
Entry  Wednesday, July 18, 2012, 16:49, Grant Minor, South Hot-Cell, Development, , , South Hot Cell Ventilation Alarm Trip 
Today (Wednesday July 18th) at around 4:15 pm I was taking a small tour  group from VECC into the Target Hall.  In the process of discussing the  mechanical
design of the Target Modules and South Hot Cell turntable I  inadvertently lifted the Aluminum Hatch Cover of the Hot Cell about 2  inches in an effort
to explain something.  This tripped the ventilation  alarm before I realized what I was doing.  I evacuated the visitors from  the Target Hall, checked
Entry  Tuesday, July 31, 2012, 10:50, Travis Cave, South Hot-Cell, Standard Operation, TM1, Ta#38, module move 
TM#1 with Ta#38 has been moved from the west target station to the south hot cell, no problems with the move.
Entry  Tuesday, July 31, 2012, 12:24, chad fisher, South Hot-Cell, Standard Operation, TM1, UCx#4, UCx#4 Installed 
Starting at 11:00 am and finishing at 12:10 Ucx#4 previous target was removed and UCx#4 installed and leak checked on TM1.
During module move to the hot cell UCx#4 was housed in a bag under argon.