Friday, March 27, 2015, 11:29, David Wang, Conditioning Station, Standard Operation, TM4, Ta#45, TM4 is connected at CS
|
TM4 has been connected at CS which includes high current cables, water lines, EE cable, and Enizel lens cable. The HV cover has been installed
onto the TM4 service cap.The CS water system is started. All water signals are good so far. Anders will start HV and heaters conditioning
on next Monday. |
Monday, March 30, 2015, 07:38, David Wang, ITE, Standard Operation, TM4, , TH Shut Down Activities Schedule Feb 23th- Apr 15th update
|
Updated schedule this morning after last Fridays ISAC facility support group meeting.
Updated schedule on 2015-April -02. See attachments 3,4. The scheduled all shut down jobs are done on time.The TM2 move to SHC will be delayed
to May.There will be a new beam running time TH activities schedule (start from April 15) replacing this shut down schedule on next time weekly update. |
Monday, March 30, 2015, 09:03, Anders Mjos, Conditioning Station, Standard Operation, TM4, Ta#45, Ta#45 Conditionoing
|
Monday, March 30, 2015, 08:59: Reset chiller by switching on off power (fault 2)
Monday, March 30, 2015, 09:02: Switched on CHILL:CP2, TS5 at 34 C
Monday, March 30, 2015, 10:24 : Cage locked. EE to GND. BIAS and EL ON. |
Wednesday, April 01, 2015, 06:56, David Wang, Conditioning Station, Standard Operation, TM4, Ta#45, TM4 has been disconnected at CS.
|
TM4 has been disconnected at CS. The CS and TM4 is venting for move. Anders stopped vacuum and water system yesterday. |
Wednesday, April 01, 2015, 10:52, Travis Cave, ITE, Standard Operation, TM4, Ta#45, Module move
|
TM#4 with Ta#45 has been moved from the conditioning station to the east target station. |
Wednesday, April 01, 2015, 13:08, David Wang, ITE, Standard Operation, TM4, , Replaced ITE tank to module 42X0.275 o-ring
|
I replaced ITE tank to module 42 ID X 0.275 o-ring. The o-ring is changed once a year before the first beam time. The flanges was cleaned and the new
o-ring was installed. It works fine. |
Wednesday, April 01, 2015, 13:12, David Wang, ITE, Standard Operation, TM4, Ta#45, TM4 has been connected in ITE
|
TM4 has been connected in ITE. ITE six turbo-pumps have been started. So far so good. |
Friday, April 10, 2015, 15:40, David Wang, ITE, Standard Operation, TM4, , 5 Shielding blocks have been transferred from ITW to ITE.
|
5 shielding blocks have been transferred to ITE. The ITE is configured to take proton beam. |
Monday, April 20, 2015, 07:27, David Wang, ITE, Standard Operation, TM4, , Target Hall Scheduled Activities April 07 - June 26 2015
|
Weekly target hall schedule update.2015-04-20
weekly target hall schedule update 2015-04-27 attachments 3,4. |
Monday, June 01, 2015, 11:23, Travis Cave, ITE, Standard Operation, TM4, Ta#45, Module moved
|
TM#4 with Ta#45 has been moved from the east target station to the south hot cell. |
Monday, June 01, 2015, 14:24, Travis Cave, South Hot-Cell, Standard Operation, TM4, Ta#45, Electrical Check
|
Post beam electrical check on the Ta#45 target installed on TM#4. See attached PDF. |
Tuesday, June 02, 2015, 06:51, David Wang, South Hot-Cell, Standard Operation, TM4, , Target Hall Scheduled Activities April 07 - June 26 2015
|
Target Hall schedule weekly update. All jobs are finished on time so far. |
Tuesday, June 02, 2015, 09:43, chad fisher, South Hot-Cell, Standard Operation, TM4, SiC#31, SiC#31 installed
|
Ta #45 has been removed from TM4 and SIC#31installed. |
Tuesday, June 02, 2015, 10:39, Travis Cave, South Hot-Cell, Standard Operation, TM4, SiC#31, Electrical Check
|
Electrical check on TM#4 with SiC#31. See attached PDF for details. |
Tuesday, June 02, 2015, 11:54, Travis Cave, Conditioning Station, Standard Operation, TM4, SiC#31, Module moved
|
TM#4 with SiC#31 has been moved from the south hot cell to the conditioning station. |
Tuesday, June 02, 2015, 14:32, David Wang, South Hot-Cell, Standard Operation, TM4, SiC #31, Leak check on TM4 HS water line with new SiC #31 target. at SHC
|
Chad and I leak checked TM4 HS water line with SiC #31 target installed. leak rate:0.0xE-9atm.cc/sec. No leak. The line will be helium pressurized
at CS later.
2015-06-03, helium pressure test the line at CS. 70psi 3 minutes. leak rate 0.0xE-9 atm.cc/sec. No leak. See attachments |
Tuesday, June 02, 2015, 14:38, David Wang, Conditioning Station, Repair, TM4, , replace broken TM4 IG1
|
TM4 IG1 filament was broken during last run at ITE. The broken filament is replaced with a new one today when TM4 is located at CS.
2015-06-03 , Leak checked the new 25 conflat gasket today. No leak. See attachments |
Tuesday, June 02, 2015, 14:39, David Wang, Conditioning Station, Standard Operation, TM4, SiC #31, TM4 and CS turbo- pumps are started .
|
TM4 and CS turbo-pumps are started this afternoon. Everything is good so far. |
Wednesday, June 03, 2015, 13:01, Anders Mjos, Conditioning Station, Standard Operation, TM4, SiC#31, Conditioning SiC#31
|
PNG1 connected to PNG in service cap (as per David W)
Wednesday, June 03, 2015, 12:59: Water on
Wednesday, June 03, 2015, 13:04: Staging enabled. |
Wednesday, June 03, 2015, 13:51, David Wang, Conditioning Station, Standard Operation, TM4, SiC #31, TM4 is connected at CS
|
TM4 has been connected at CS. CS HV cover is installed.I made a pair of new cooling lines for TM window cooling at CS. The TM4 containment box window
cooling line is connected to the HVC spare circuit now. I checked water flow visually, and it is good. The TM4 is ready for conditioning.See attachment
for window cooling modification. |
|