  2309   Friday, February 25, 2022, 10:22 Adam NewsomeSouth Hot-CellDevelopment  Addition of E-Stops and Turntable Vertical Motion Limit SwitchTwo changes have been made to the control
system to the South Hot Cell:

    Addition of two emergency
  
  2318   Friday, May 06, 2022, 10:12 Adam NewsomeSpent Target VaultMaintenance  Annual Inspection of Mini-Storage VaultThe annual inspection of the mini-storage
vault was performed today. The following
items were checked:
  
  2366   Wednesday, September 14, 2022, 13:45 Adam NewsomeSpent Target VaultDevelopment  Storage Vault: cable replaced and e-chain upgradeThe motor cable for the storage vault was
replaced as the old one was showing signs
of wear. The U-track that the old cable ran
 PXL_20220914_183329159.jpg 
  2375   Friday, October 07, 2022, 14:46 Adam NewsomeSouth Hot-CellDevelopment  Addition of lift table to E-stop circuitA modification was made to integrate the
hot cell's lift table into the E-stop circuit.
See work permit I2022-10-07-1
 ISAC_SHC_Lift_Schematic_updated_20221007.jpgPXL_20221007_185635660.MP.jpgPXL_20221007_185649720.jpg 
  2389   Tuesday, November 22, 2022, 10:37 Adam NewsomeNorth Hot-CellStandard OperationTM4 TM4 Move - ITE to NHCTM4 was moved from ITE to NHC with C#4.
  
  2393   Wednesday, November 23, 2022, 12:10 Adam NewsomeConditioning StationStandard OperationTM4UCx#41TM4 Move - NHC to TCSTM4 was moved from the North Hot Cell to
the Target Conditioning Station with UCx#41.
  
  2394   Thursday, November 24, 2022, 11:32 Adam NewsomeSpent Target VaultStandard OperationTM4C#4C#4 Spent Target Moved to Storage VaultC#4 spent target was moved to the storage
vault, in pail 277. Dose rate at approximately
1 m when leaving the hot cell was 164 mSv/h.
 Target_Index_2022-11-24.pdf 
  2395   Tuesday, November 29, 2022, 11:03 Adam NewsomeITEStandard OperationTM4C#4TM4 Move - TCS to ITETM4 was moved from the Conditioning Station
to the East Target Station with C#4. 
  
  2398   Friday, December 16, 2022, 16:35 Adam NewsomeSpent Target VaultStandard Operation  Pails measured, moved to mini-storage vaultThe following five pails were moved to
the mini-storage vault today under work permit
I2022-12-16-1:
 Target_Index_2022-12-16.pdf 
  2399   Friday, December 16, 2022, 16:39 Adam NewsomeCraneStandard Operation  Crane powered off for holidays[edit 2023-01-03] The crane was powered
back on this morning - there do  not appear
to be any faults and it seems that the crane
  
  2400   Friday, January 06, 2023, 09:41 Adam NewsomeSpent Target VaultStandard Operation  Pails moved to mini-storage vaultThe following three pails were moved from
the main storage vault to the mini-storage
vault:
 Target_Index_2023-01-06.pdf 
  2422   Monday, March 06, 2023, 11:31 Adam NewsomeNorth Hot-CellRepair  Spare Telemanipulator: Y-Motion Linear Actuator RepairThe linear actuator used for the Y-motion
motor assistance on the spare telemanipulator
was replaced and tested. It was observed
  
  2431   Friday, April 14, 2023, 10:01 Adam NewsomeAssembly/Bench TestRepair  Assaying Turntable RepairThe spent target assaying turntable was
repaired. It was tested today with a load
exceeding the maximum it would need to handle
  
  2436   Wednesday, May 03, 2023, 11:04 Adam NewsomeCraneMaintenance  Pail Handling Tool - Annual InspectionThe pail handling tool which is used to
move 5 gallon pails around the target hall
was inspected by A. Newsome, N. Jorgenson,
 PXL_20230503_172503014.jpgPXL_20230503_172457837.jpgPXL_20230503_172454009.jpg 
  2441   Friday, May 12, 2023, 09:56 Adam NewsomeSpent Target VaultStandard Operation  Emergency Close Mechanism Test The emergency close
mechanism for the Storage Vault door was
  
  2460   Tuesday, June 20, 2023, 12:37 Adam NewsomeAssembly/Bench TestDevelopment  Modifications to wire ropes for pails within existing F-308sBased on a request from CNL (attached),
modifications were made to the wire ropes
protruding through the tops of F-308s to
 6x 
  2462   Wednesday, June 21, 2023, 14:39 Adam NewsomeSafe Module ParkingMaintenance  Annual electrical and mechanical inspection of Safe Module ParkingAn annual electrical and mechanical inspection
was performed on the  SMP today by Adam Newsome,
Travis Cave, Eric Lahe, Maico Dalla Valle,
 PXL_20230621_210144119.MP.jpgPXL_20230621_210546559.jpgPXL_20230621_210146892.jpg 
  2468   Friday, July 28, 2023, 10:09 Adam NewsomeSpent Target VaultMaintenance  Main Storage Vault: Bearing LubricationBearings for the main storage vault door
were lubricated on 2023-07-28. It is unknown
when this was last done. It is suggested
  
  2469   Friday, July 28, 2023, 10:21 Adam NewsomeSpent Target VaultMaintenance  Mini Storage Vault: Bearing LubricationThe bearings on the mini storage vault
were lubricated. It is suspected that this
has never been done. It is suggested that
 PXL_20230728_162515733.jpg 
  2470   Tuesday, August 01, 2023, 09:06 Adam NewsomeCraneDevelopment  Measuring Tape and Camera Removed from Target Hall CraneIn an effort to clean up the camera installation
on top of the ISAC target hall crane to resolve
a fault, the position measuring tape and
  