The following controls-related items were installed for the SMP project:

- Cable tray

- Main control panel

- Motor starter box

- Wiring from limit switches and rotation motor to main control panel

- Air fittings at supply (quick disconnect)

- Main air supply hose from supply to control panel (quick disconnect)

- Air tubing from lid control valve at control panel to lid cylinders

 

Air fittings stem off existing air supply lines on the South wall, below a manual shutoff valve. A quick disconnect was installed. When SMP is not in use, manual shutoff valve should be left off.

 

Main control panel and motor starter box were mounted on the North wall. Wire duct runs from the main control panel to the grated floor. Cabling/air runs underneath the mezzanine platform, along existing and new cable tray, to the SMP.

 

Cable tray was installed on the South wall, from the corner to the SMP module. A cutout was made to accommodate for existing tubing. An additional ~1 ft. of tray will be added to the end, near the corner, at a future time.

 

Remainder of installation work to be done before commissioning:

- Mount and install new Opto-22 module
- Chain new Opto-22 module to existing one (power, comms) below mezzanine on North wall

Attachment 1: IMG_20190417_100838.jpg  1.030 MB  | Show | Hide all
Attachment 2: IMG_20190417_100843.jpg  1.592 MB  | Show | Hide all
Attachment 3: IMG_20190517_162230.jpg  1.264 MB  | Show | Hide all
Attachment 4: IMG_20190517_162305.jpg  459 kB  | Show | Hide all
ELOG V2.9.2-2455