2530
|
Thursday, January 25, 2024, 07:24 |
David Wang | Crane | Standard Operation | | | targe hall annual crane inspection | Tom Kauss finished TH crane annual inspection
yesterday. The crane woks fine. Tom has
this inspection record in his file. The crane |
|
2531
|
Thursday, January 25, 2024, 07:27 |
David Wang | Crane | Standard Operation | | | Inspection of target module lifting frames ITA0494-1997-01 and ITA0494-1997-02 | Tom Gauss inspected two target module
lifting frames ITA0494-1997-01 and ITA0494-1997-02
yesterday. He certified the use of these |
|
2532
|
Thursday, January 25, 2024, 07:31 |
David Wang | Crane | Standard Operation | | | Inspection oftareg hall crane below hook attachment pins and plates ITA6550-01 | Tom Kauss inspected target hall crane below
hook attachment pins and plates ITA6550-01
yesterday. He certified the use of these |
|
2538
|
Tuesday, February 06, 2024, 13:28 |
David Wang | ITW | Maintenance | | | ITW exit 1 module has been disconnected and reconnected for o ring replacement | ITW exit 1 module was disconnected
for Exit module flange o -ring replacement
yesterday. After oring replacement, the module |
|
2539
|
Tuesday, February 06, 2024, 13:36 |
David Wang | ITW | Maintenance | | | ITW exit 1 module tank flange o ring has been replaced. | ITW exit 1 module tank flange o ring has
been replaced. the old o r-ing was completely
flat in slot without elastic property. |
|
2540
|
Friday, February 09, 2024, 12:52 |
Adam Newsome | Spent Target Vault | Standard Operation | | | F-308 flask loading - five flasks loaded | Today (2024-02-09), five flasks were loaded
in preparation for shipment with the following
targets: SiC#41, SiC#42, Nb#9, UC#36, Ta#58. |
|
2541
|
Monday, February 12, 2024, 18:44 |
Carla Babcock | ITW | Maintenance | | | ITW annual HV testing | ITW was set up for HV testing - water is
running and at a high resistivity due to
injected N. Einzel lens is attached to ground. |
|
2542
|
Wednesday, February 14, 2024, 11:32 |
Adam Newsome | Spent Target Vault | Standard Operation | | UCx#43 | Spent Target Move | Spent target UCx#43 (pail 289) was moved
from the South Hot Cell to the Storage Vault,
placed in location 2A. Dose rate at 1m was |
|
2543
|
Wednesday, February 14, 2024, 11:34 |
Adam Newsome | Spent Target Vault | Standard Operation | | Misc. | Three pails moved from main vault to mini vault | In preparation for F-308 loading, three
pails were moved from the main storage vault
to the mini storage vault. The following |
|
2544
|
Thursday, February 15, 2024, 13:52 |
David Wang | ITW | Standard Operation | | | ITW entrance module and exit 1 module leak check after module move and tank flange orings replacement. | ITW entrance module and exit 1 module
leak check on module service cap/top air
to vacuum seals and module to tank flange |
|
2545
|
Thursday, February 15, 2024, 17:40 |
Carla Babcock | ITE | Standard Operation | | | ITE annual HV testing | ITE was set up for HV tests - this time
the module plug was not in so the BIAS and
EE had to be bypassed. NOTE: ITE:BIASPLC |
|
2546
|
Friday, February 16, 2024, 10:57 |
Adam Newsome | Spent Target Vault | Standard Operation | | | F-308 flask loading - three flasks loaded | Today (2024-02-16), three flasks were loaded
in preparation for shipment with the following
targets: UCx#39, UCx#41 and C#3. |
|
2547
|
Friday, February 16, 2024, 11:48 |
David Wang | Cooling | Maintenance | | | high active water transferr to holding tank | 100 liters of high active water from HALCW
system( mostly from s-tank and pipe lines
closing to pumps) are transferred to holding |
|
2548
|
Friday, February 23, 2024, 06:36 |
David Wang | ITE | Maintenance | | | ITE entrance module has been disconnected. | ITE entrance module has been disconnected
per document 190510. Its a preparation job
for next month module moving out to SHC. |
|
2550
|
Thursday, March 14, 2024, 14:54 |
David Wang | ITE | Maintenance | | | ITE entrance module has been moved from ITE pit to TCS. | ITE entrance module has been moved from
ITE pit to TCS. The move is smooth.ITE entrance
module top tank flange and o ring slot are |
|
2552
|
Thursday, March 21, 2024, 11:35 |
Ferran Boix Pamies | ITE | Development | | | Wiring of new thermocouple PLC module | Thursday, March 21, 2024, 11:33 Three
channels are available now for thermocouple
readouts from the Target multipin. Wiring |
|
2553
|
Monday, March 25, 2024, 10:53 |
David Wang | ITE | Repair | | | ITE entrance module has been moved from TCS to ITE. | ITE entrance module has been moved from
TCS to ITE. The move is smooth. |
|
2554
|
Monday, March 25, 2024, 10:55 |
David Wang | ITE | Standard Operation | | | ITE entrance module has been reconnected in ITE pit. | ITE entrance module has been reconnected
in ITE pit per document 190510. |
|
2556
|
Wednesday, March 27, 2024, 09:52 |
David Wang | ITE | Standard Operation | | | ITE entrance module top and module flange o-ing to tank have been leak checked. | ITE entrance module top and module flange
o-ing to tank have been leak checked. no
leak at 0.0xe-9 atm.cc/sec. things are double |
|
2558
|
Wednesday, April 03, 2024, 10:48 |
chad fisher | South Hot-Cell | Maintenance | | | SE Manipulator wrist swap | On April 2, 2024 the wrist on the SE manipulator
of the SHC (Serial # 7986) was swapped with
a rebuild unit originally from SW position |
|