  RH-ISAC, Page 129 of 138  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
ID Date Author Category Type Module Target/Number Subject
  188   Tuesday, September 25, 2012, 14:33 David WangITWStandard OperationTM1Nb#7TM1connected in ITW

TM 1 is in ITW now. All connections are done. The turbo pumps had been started this afternoon. The vacuum looks good so far. The water interlock check which related to TM1 are done. They are good. All TM1 water signals are visually checked and they are strong.  The rest interlock check ( MCR XT page) will be finished before shielding blocks moving. The MAA is locked and ITE is ready for proton beam.        

  187   Tuesday, September 25, 2012, 10:34 Travis CaveITWStandard OperationTM1Nb#7module move

TM#1 with Nb#7 moved from the conditioning station to the west target station. Move went well.

  186   Thursday, September 20, 2012, 09:16 David WangConditioning StationStandard OperationTM1Nb#7TM1 Nb#7 target heat shield helium pressure check is done.

Leak detector pumped down to base LR1.3xE-9 atm.cc/sec, and BP 8xE-3 torr. All high vacuum gauge readings at CS and TM1 are at low -6 range from 1.2xE-6torr to 4.6x E-6 torr. Applied 80 psi helium  to heat shield circuit for 5minutes and there is no any response on leak detector. The heat shield circuit is leak tight.

  185   Thursday, September 20, 2012, 08:45 Travis CaveConditioning StationStandard OperationTM1Nb#7Electrical check

Electrical check was done at the conditioning station this morning results are on the attached PDF.

  184   Wednesday, September 19, 2012, 11:24 Travis CaveConditioning StationStandard OperationTM1Nb#7module move

TM#1 with Nb#7 was moved from the south hot cell to the conditioning station. Move went well.

  183   Wednesday, September 19, 2012, 11:23 Travis CaveSouth Hot-CellStandard OperationTM1Nb#7Electrical check

TM#1 with Nb#7 attached was electrically checked at the south hot cell yesterday, see attached pdf for details. Some notes about this test the oven to the 60kV common is 2Mohm this was noticed on the target prior to installation on the module, and the 60kV common to chassis is low at 874Mohm (low as in a non infinite value).

  182   Tuesday, September 18, 2012, 13:47 chad fisherSouth Hot-CellStandard OperationTM1Nb#7Nb #7 install Cover Baseline

Nb #7 was installed and tested today.

Inside face of the containment box cover was cleaned with methanol and a baseline picture taken in an effort to track deposits and marking as requested bty Anders.

  181   Tuesday, September 18, 2012, 13:41 David WangSouth Hot-CellStandard OperationTM1Nb#7leak check heat shield circuit

Chad and i did a leak check on TM1 heat shield circuit with new Nb#7 target installed. It took about 5 mins pump down the circuit to leak rate 0.0x E-9atm.cc/sec and 0.0x E-4 torr on leak detector.

All vacuum lines and joints which connected to the leak detector had been helium sprayed and they are leak  tight. Chad sprayed helium on each VCR joints for 2 seconds every time. During 45sec waiting time, there is no any response on leak detector. Chad repeated same test again for double checking and we got same result. Chad finally flushed the helium around the target heat shield for 10 seconds.we waited for 45minute and found no response on the leak detector. The heat shield circuit is leak tight at this stage. I will do a helium pressure test on this circuit when TM1 is in CS and under vacuum.

  180   Tuesday, September 18, 2012, 09:13 Travis CaveSouth Hot-CellStandard OperationTM1no targetmodule move

TM#1 moved from the south west silo to the south hot cell, move went well.

  179   Friday, September 14, 2012, 10:45 Travis CaveSpent Target VaultStandard Operation UCx#4Spent target move

UCx#4 has been moved from the south hot cell to the spent target vault. The target was placed in pail #99 and now resides in spot 3C of the vault. It measured 55.3mSv/hr at ~1m from the hot cell. See attached PDF for further spent target vault details.

  178   Thursday, September 13, 2012, 13:27 Travis CaveSouth Hot-CellStandard OperationTM1no targetmodule move

TM#1 has been moved from the south hot cell to the south west silo. Move went well.

  177   Thursday, September 13, 2012, 11:03 Travis CaveSouth Hot-CellStandard OperationTM1UCx#4module move

TM#1 with UCx#4 has been moved from the west target station to the south hot cell. Move went well.

  176   Wednesday, September 12, 2012, 11:59 David WangITWStandard OperationTM1UCxTM1 disconnected in ITW

I removed 5 shielding blocks from ITW to block storage area, and disconnected TM1 in ITW. After UCx run,  the radioactive level around the turbo pumps and primary vacuum lines are pretty high. This affect the general field inside the ITW pit around working area.i took 15 minuts to finish the job and i got 0.1msvr dose. the general field around my working area is about 350 usv/h.

  175   Wednesday, September 12, 2012, 07:00 David WangITEStandard OperationTM4NiO #1ITM4 in ITE connected and pumping down

TM4 had been connected in ITE. Six turbo pump had been started . thepumpming diwn is very good so far. The water interlock check on ITE and TM4 had been finished and everything is good.All water signals are strong and constant by visually checking.

  174   Friday, September 07, 2012, 10:37 Travis CaveConditioning StationStandard OperationTM4NiO#1Electrical check

Electrical check of the TM#4 with NiO#1 was done again today. see attached file for results.

  173   Friday, September 07, 2012, 09:47 Travis CaveSpent Target VaultStandard Operation UO#3Spent target move

The spent UO#3 was moved from the south hot cell to the storage vault. It was in pail 98 and placed in spot 1A of the vault, the field measured upon removal from the hot cell were 42mSv/hr. See attached PDF for vault details.

  172   Friday, September 07, 2012, 08:54 David WangConditioning StationStandard OperationTM4NiO #1TM4 NiO #1 target heat shield helium pressure check is done.

leak detector pumped down to 0.0xE-9 atm.cc/sec, and 0.0xE-4 torr. All high vacuum gauge readings at CS and TM4 are at low -6 range from 2.2xE-6torr to 4.2x E-6 torr. Applied 80 psi helium  to heat shield circuit for 5minutes and there is no any response on leak detector. The heat shield circuit is leak tight.

  171   Wednesday, September 05, 2012, 14:40 Travis CaveConditioning StationStandard OperationTM4NiO#1Electrical check

See attached PDF for details. 60kV Common to the target is low at 343k but I've been told will work. Test will be done again on Friday after it has sat a few days under vacuum.

  170   Wednesday, September 05, 2012, 14:36 chad fisherSouth Hot-CellStandard OperationTM4NiO #1UOx removal NiO installation

UOx was removed from TM4 yesterday and NiO#1 installed.

Video was taken.

Main stand-off insulators continue to deteriorate.

  169   Wednesday, September 05, 2012, 11:55 Travis CaveConditioning StationStandard OperationTM4NiO#1module move

TM#4 with NiO#1 has been moved from the south hot cell to the conditioning station. Move went well.