Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ISAC, Page 122 of 138  Not logged in ELOG logo
ID Date Author Category Typedown Module Target/Number Subject Text Attachments
  1668   Tuesday, December 19, 2017, 10:41 Anders MjosCraneMaintenance  Crane powered downThe target hall crane has been powered
down by Don today in preparation for the
power shutdown over the Holidays.
  
  1669   Thursday, December 21, 2017, 15:11 Anders MjosConditioning StationMaintenance  Powered down devicesPowered down mechanical pumps in ISAC-I
Experimental hall, vacuum gauge and turbo
pump controllers in ISAC-I B2 North Hot Cell
  
  1674   Tuesday, January 02, 2018, 15:17 Anders MjosConditioning StationMaintenance  Tested chillerTested all 3 compressors and MP2   
  1675   Thursday, January 04, 2018, 13:28 Anders MjosConditioning StationMaintenance  Troubleshooting IG1STCS:IG1S is reporting vacuum levels that
seem to be too low (1E-10 to 1E-8 Torr).
The gauge was connected to the controller
  
  1683   Monday, January 29, 2018, 06:51 David WangConditioning StationMaintenanceTM1 TCS and TM1 vacuum pumps switched offTCS and Tm1 vacuum pumps are switched off
this morning. TM1 TP1and TP2 work fine during
this test period. Tm1 will be moved back
  
  1687   Wednesday, February 14, 2018, 10:06 Anders MjosITWMaintenanceTM2 Replaced parker couplings on Window cooling lineBy Anders & David. Couplings will be
taken apart for inspection.
  
  1688   Friday, February 16, 2018, 13:46 Anders MjosITWMaintenanceTM2 Parker coupling inspectionFindings and photos from the inspections
attached. The inspection was conducted by
Anders, David and Maico.
 Used_Parker_FS251_Inspection.pdf 
  1694   Thursday, March 08, 2018, 14:10 David WangITWMaintenance  Two small water leak has been found in ITW. Two small water leaks have been found on
ITW High active water system.  One is from
an unused 1/4" copper valve stem. another
  
  1696   Thursday, April 05, 2018, 11:29 David WangITWMaintenance  ITH MP1 replacementITH MP1 is replaced today with a new style
pump.The new pump is 0.75 inch higher than 
old pump on inlet and exhaust so a new solid
  
  1702   Thursday, April 19, 2018, 10:27 Travis CaveITWMaintenance  Entrance module move The west entrance module has been
moved from the west target station to the
silo.
  
  1715   Thursday, May 17, 2018, 11:30 Anders MjosConditioning StationMaintenanceTM4 HV test/conditioning of damaged source trayBIAS only. Water lines looped on top. Containment
box off.
Thursday, May 17, 2018, 11:20: Vacuum
 TM4_2018-05-18_Water_Leak.docx 
  1744   Friday, June 29, 2018, 10:12 chad fisherSouth Hot-CellMaintenance  Manipulator Tong Cable ReplacementTuesday, June 26 the broken tong cable
was replaced on the west manipulator in the
south hot cell. Wednesday the tong cable
  
  1746   Friday, June 29, 2018, 10:27 chad fisherSouth Hot-CellMaintenance  South Hot Cell Filter ChangeAt the end of manipulator repair Thursday
the ventilation pre-filter in the hot cell
was changed. Old filter remains in the hot
  
  1752   Wednesday, July 11, 2018, 15:09 Anders MjosITWMaintenanceTM2Nb#8Uncovered ITW to toubleshoot 2A2M19The 2A2M19 beam profile monitor did not
work and was e-faulted.
After initial troubleshooting 2 blocks were
  
  1766   Tuesday, August 07, 2018, 10:44 Travis CaveSouth Hot-CellMaintenance  Entrance module move The west entrance module has been
moved from the west target station to the
south hot cell, for a bellows replacement.
  
  1794   Tuesday, September 25, 2018, 08:48 chad fisherSouth Hot-CellMaintenance  Window leak and torqueThe south hot cell window has been found
to be leaking oil. Upon inspection yesterday
I found that the bolts compressing the gasket
 hot_cell_window_gasket_change_procedure.pdf 
  1808   Tuesday, October 23, 2018, 11:32 David WangSouth Hot-CellMaintenance  ITW RV4S leak check.ITW RV4S (A and B) are leak checked. They
are good.  
  
  1820   Thursday, November 08, 2018, 09:27 chad fisherSouth Hot-CellMaintenance  South East Manipulator cable replacementThe handle cable on the east manipulator
of the south hot cell has been replaced.
Old cable showed signs of wear but had no
  
  1858   Monday, January 14, 2019, 07:07 David WangConditioning StationMaintenanceTM2 Restarted TCS vacuum system .No issue.   
  1861   Tuesday, January 22, 2019, 09:56 David WangITWMaintenanceTM2 ITW water system maintenance.ITW water system maintenance is done. All
working paddle wheels and coils are replaced.
ITW water system polyurethane tubes are replaced
  
ELOG V2.9.2-2455