Message ID: 1218     Entry time: Friday, April 29, 2016, 08:01
Author: David Wang 
Category: Conditioning Station 
Type: Maintenance 
Module: TM2 
Target/Number:  
Subject: TM2 leak check at TCS, helium pressure test 

Anders and I finished the most part of TM2 water lines helium pressure test yesterday.I list the system parameters and test result as below:

TCS  IG1: 9.8XE-8 torr,  TCS IG2: 9.6Xe-7 torr, TCS IG1S: 3.5XE-9 torr, TCS CG1A: 10 m torr

Helium pressure: 70 psi. Test time: 5 minutes for each individual circuit.  1 hour for all  lines together test.

 Leak detector base leak rate:0.0 X E -9 atm.cc/sec, base pressure 0.0X E-4 torr. LD was always restored or closely restored to the bottom  scale after each individual test.

 

Circuit Result (atm.cc/sec)
EE 0.0X E-9
Target Oven + 0.0X E-9
Coil 1   P-Q 0.0X E-9
Target Oven - 1.0X E-9
Tube Heater- 4.1X E-9
Tube heater+ 1.6X E-8
Coil 2    R-U 6.6X E-9
MSP 1.4X E-7
All above together (1 hour) 2.3X E-7
HS Open circuit . No test
Window Open circuit.  No test.
GE  7.2X E-7

The HS and Window lines will be tested later with new target installed and  window line gaskets restored.