1149
|
Friday, December 18, 2015, 11:42 |
Anders Mjos | Conditioning Station | Repair | | | Vacuum gauges not reading correctly | It was found that the conversion
from voltage to vacuum (Torr) in EPICS is
not correct for the XGS-600 controllers in |
|
1150
|
Monday, December 21, 2015, 13:27 |
Anders Mjos | Conditioning Station | Repair | | | Vacuum gauges not reading correctly |
|
|
1154
|
Friday, February 12, 2016, 13:00 |
David Wang | Conditioning Station | Standard Operation | | | 2016 Winter Shut Down Target Hall Schedule | 2016 Winter shut down target hall schedule.
See attachments1,2.
update the schedule weekly. |
6x |
1157
|
Thursday, February 25, 2016, 06:52 |
David Wang | Conditioning Station | Standard Operation | | | stop CS vacuum pumps. | I stopped the conditioning station vacuum
pumps. The CS is still under vacuum without
venting. |
|
1163
|
Friday, March 04, 2016, 13:58 |
David Wang | Conditioning Station | Standard Operation | | | 2016 Winter Shut Down Target Hall Schedule | Update Schedule according to changes.See
attachment1, 2.
Re-post it after some minor |
8x |
1165
|
Monday, March 14, 2016, 15:22 |
David Wang | Conditioning Station | Standard Operation | TM2 | | 2016 Winter Shut Down Target Hall Schedule | update schedule according to change. See
attachment 1,2
|
 |
1169
|
Friday, March 18, 2016, 08:34 |
Travis Cave | Conditioning Station | Standard Operation | TM2 | no target | module moved | TM#2 with no target has been moved to the
conditioning station from the south hot cell. |
|
1170
|
Friday, March 18, 2016, 09:34 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Target Hall schedule for beam schedule 130 (Apr- Sep) | I would like to post the spreadsheet of
target hall schedule for beam schedule 130(Apr
to Sep) first. The MS project of TH schedule |
 |
1171
|
Friday, March 18, 2016, 09:42 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 vacuum sysytem has been connected at TCS | TM2 vacuum system has been connected at
TCS. Started roughing pump. Everything is
good so far. |
|
1173
|
Friday, March 18, 2016, 13:13 |
Travis Cave | Conditioning Station | Standard Operation | TM2 | SiC#32 | Electrical Check | Electrical checks of the TM#2 with the
old SiC#32 and without the target. See attached
PDFs. |
 |
1174
|
Monday, March 21, 2016, 10:25 |
David Wang | Conditioning Station | Repair | TM2 | | TM2 Helium pressure Test Result in TCS and ITW | TM2 has been helium pressure tested in
ITW and TCS. They are both tested with 70psi
helium, each circuit for 3minutes. |
|
1175
|
Monday, March 21, 2016, 11:30 |
David Wang | Conditioning Station | Repair | TM2 | | TM2 and TCS vacuum pumps are stopped | I stopped TM2 and TCS vacuum pumps. It
will be vented and disconnected this afternoon
for tomorrow moving. |
|
1176
|
Monday, March 21, 2016, 15:27 |
David Wang | Conditioning Station | Repair | TM2 | | TM2 has been disconnected at TCS | TM2 vacuum system has been disconnected
at TCS. Venting is in process now. |
|
1180
|
Thursday, March 24, 2016, 13:15 |
David Wang | Conditioning Station | Standard Operation | TM1 | | TM1 and TCS vacuum system has been connected | TM1 and TCS vacuum system have been connected.
All turbo-pumps are started. The pumping
down is fine. |
|
1181
|
Thursday, March 24, 2016, 13:55 |
Travis Cave | Conditioning Station | Standard Operation | TM1 | no target | module moved | TM#2 has been moved from the south hot
cell to the south west silo and TM#1 was
moved from the north east silo to the conditioning |
|
1182
|
Tuesday, March 29, 2016, 08:38 |
David Wang | Conditioning Station | Standard Operation | TM1 | | TM1 water lines helium pressure check at TCS | TM1 water lines helium pressure check at
TCS is done. 70 psi helium was applied to
water circuits. Leak detector base leak rate |
    |
1183
|
Wednesday, March 30, 2016, 08:40 |
David Wang | Conditioning Station | Standard Operation | | | 2016 Winter Shut Down Target Hall Schedule | update the schedule according to changes.See
attachment1, 2. |
 |
1184
|
Wednesday, March 30, 2016, 11:00 |
Travis Cave | Conditioning Station | Standard Operation | TM1 | no target | Electrical Check | The results of the TM#1 electrical check
from the 29th of March 2016 |
|
1187
|
Friday, April 01, 2016, 13:58 |
Travis Cave | Conditioning Station | Standard Operation | TM1 | UC#15 | module moved | TM#1 has been moved from the conditioning
station to the south hot cell, had UC#15
installed and then moved back to the conditioning |
|
1188
|
Friday, April 01, 2016, 14:41 |
David Wang | Conditioning Station | Standard Operation | TM1 | | TM1 and TCS vacuum system has been connected. TCS control page white out. | I can not start the TCS pumps due to control
page white out. Control group is working
on this issue. |
|