ID Date Author Categorydown Type Module Target/Number Subject Text Attachments
  1134   Wednesday, November 25, 2015, 11:55 Travis CaveConditioning StationStandard OperationTM4UC#14Module moved and electrical check.TM#4 with UC#14 was moved from the south
hot cell to the conditioning station. 
Here are the results of the electrical check
 TM4_UC14_elecchk_SHC.PDF 
  1137   Wednesday, November 25, 2015, 15:37 Anders MjosConditioning StationStandard OperationTM4UC#14Conditioning Wednesday, November 25, 2015, 15:36:
RGA on

Thursday, November 26, 2015,
  
  1138   Thursday, November 26, 2015, 06:25 David WangConditioning StationStandard OperationTM4UC#14TM4 vacuum has been connected in TCS.TM4 vacuum has been connected in TCS. All
vacuum pumps were started yesterday. The
pumping down of TM4 and TCS are good so far.
  
  1139   Thursday, November 26, 2015, 07:34 David WangConditioning StationStandard OperationTM4UC#14Helium pressure test on TM4 HS line at CS I did helium pressure test on TM4 HS line
at TCS this morning.  70psi helium 3
minutes, 0.0xE-9 atm.cc/sec base leak rate.
  
  1140   Thursday, November 26, 2015, 07:37 David WangConditioning StationStandard OperationTM4UC#14TM4 has been connected at CSTM4 has been connected at TCS. The water
system is started. The TCS HV cover for TM4
is installed also. Basically, The TM4 is
  
  1142   Monday, November 30, 2015, 11:46 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015Weekly update TH schedule according to
changes. see attachment 1,2 .
Update TH schedule before the weekend.
 Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp 
  1143   Tuesday, December 01, 2015, 06:41 David WangConditioning StationStandard OperationTM4UC#14Turned off TCS all vacuum pumps and water pumps.I turned off TCS vacuum and water pumps.
The TSC and TM4 are still under vacuum condition.
  
  1145   Tuesday, December 01, 2015, 11:47 Anders MjosConditioning StationMaintenanceTM4UC#14Short on Extraction Electrode After conditioning over the weekend
the EE developed a short. This was confirmed
by measuring the resistance between EE and
  
  1148   Thursday, December 10, 2015, 13:17 Anders MjosConditioning StationStandard Operation  Blank off flangeThursday, December 10, 2015, 13:17: Roughing
Thursday, December 10, 2015, 14:56:
Started TP1S
 TCS_Blank_Off.png 
  1149   Friday, December 18, 2015, 11:42 Anders MjosConditioning StationRepair  Vacuum gauges not reading correctly It was found that the conversion
from voltage to vacuum (Torr) in EPICS is
not correct for the XGS-600 controllers in
  
  1150   Monday, December 21, 2015, 13:27 Anders MjosConditioning StationRepair  Vacuum gauges not reading correctly

    

       
            
  
  1154   Friday, February 12, 2016, 13:00 David WangConditioning StationStandard Operation  2016 Winter Shut Down Target Hall Schedule 2016 Winter shut down target hall schedule.
See attachments1,2.
 update the schedule weekly.
 6x 
  1157   Thursday, February 25, 2016, 06:52 David WangConditioning StationStandard Operation  stop CS vacuum pumps.I stopped the conditioning station vacuum
pumps. The CS is still under vacuum without
venting.
  
  1163   Friday, March 04, 2016, 13:58 David WangConditioning StationStandard Operation  2016 Winter Shut Down Target Hall ScheduleUpdate Schedule according to changes.See
attachment1, 2.
 Re-post it after some minor
 8x 
  1165   Monday, March 14, 2016, 15:22 David WangConditioning StationStandard OperationTM2 2016 Winter Shut Down Target Hall Scheduleupdate schedule according to change. See
attachment 1,2
 
 2016_winter_shut_down__target_hall_schedule.pdf2016_winter_shut_down__target_hall_schedule.mpp 
  1169   Friday, March 18, 2016, 08:34 Travis CaveConditioning StationStandard OperationTM2no targetmodule movedTM#2 with no target has been moved to the
conditioning station from the south hot cell.
  
  1170   Friday, March 18, 2016, 09:34 David WangConditioning StationStandard OperationTM2 Target Hall schedule for beam schedule 130 (Apr- Sep)I would like to post the spreadsheet of
target hall schedule for beam schedule 130(Apr
to Sep) first. The MS project of TH schedule
 Target_Hall_shedule_130_Apr_to_Sep_2016.xlsxTarget_Hall_shedule_130_Apr_to_Sep_2016.pdf 
  1171   Friday, March 18, 2016, 09:42 David WangConditioning StationStandard OperationTM2 TM2 vacuum sysytem has been connected at TCSTM2 vacuum system has been connected at
TCS. Started roughing pump. Everything is
good so far.
  
  1173   Friday, March 18, 2016, 13:13 Travis CaveConditioning StationStandard OperationTM2SiC#32Electrical CheckElectrical checks of the TM#2 with the
old SiC#32 and without the target. See attached
PDFs.
 TM2_SiC32_postbeam.PDFTM2_elec_chk_notgt_CS.PDF 
  1174   Monday, March 21, 2016, 10:25 David WangConditioning StationRepairTM2 TM2 Helium pressure Test Result in TCS and ITWTM2 has been helium pressure tested in
ITW and TCS. They are both tested with 70psi
helium, each circuit for 3minutes. 
  