Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ISAC, Page 114 of 141  Not logged in ELOG logo
ID Date Author Category Typedown Module Target/Number Subject Text Attachments
  1918   Friday, May 10, 2019, 10:23 chad fisherSouth Hot-CellRepair  West Entrance module wire scanner replacementWest entrance module - visible broken or
disconnected wire visible on old/existing
wire scanner. Wire scanner removed, new one
 20190509_085908.jpg20190510_101235.jpg 
  1920   Monday, May 13, 2019, 11:22 David WangITWRepair  ITW entrance module has been connnected.Entrance module has been connected back
to ITW. Everything is normal.
  
  1942   Thursday, June 13, 2019, 10:55 David WangConditioning StationRepairTM4 TM4 HV test at TCS without source tray.I brought up TCS bias to 57.5 KV on TM4
without source tray at TCS. It was kept at
this level about 1.0 hours. Some intermediate
  
  1947   Monday, July 08, 2019, 14:56 Carla BabcockConditioning StationRepairTM4Dummy HP SIS targetFirst TM4 conditioning with new source trayRamping up TM4 with new source tray in.
Current condition: new source tray but no
water running in lines B, D or window. Multipin
  
  1948   Tuesday, July 09, 2019, 09:15 Carla BabcockConditioning StationRepairTM4Dummy HP SIS targetConditioning TM4 w/ new ST up to 45kVLeft TM4 at 40kV overnight with no previous
heating. There was only one real spark which
turned off TP2 but ops turned it back on.
  
  1949   Wednesday, July 10, 2019, 11:59 Carla BabcockConditioning StationRepairTM4Dummy HP SIS targetConditioning TM4 w/ new ST up to 50kVDavid raised the bias to 49.5kV. Module
is still sparking mainly on top. Humidity
is super high.
  
  1956   Monday, July 29, 2019, 16:17 Carla BabcockConditioning StationRepairTM4Dummy LP SISNew leak on EE water line while testing new In sealsOriginal Problem:
Leaks on the B and D copper blocks,
probably due to corrosion between the blocks
 13_PM.png15_PM.png 
  1958   Tuesday, August 06, 2019, 01:13 Carla BabcockConditioning StationRepairTM4Dummy HP SIS targetChecks on EE line leak fix and window line leak (not fixed)TM4 has developed 4 leaks so far:

    Line B - seems to be solved
with an indium gasket (some testing already
  
  1966   Friday, August 16, 2019, 08:51 David WangConditioning StationRepairTM4 TM4 waterlines helium pressure test at TCS.LD base leak rate, 0.0Xe-9atm.cc/sec. Helium
pressure, 70psi. 5 minutes each circuit.
No response on all water line except containment
  
  1968   Friday, August 16, 2019, 14:23 Carla BabcockITERepairTM2ZrC#8TM2 electrical checks in ITERamped voltage on TM2 up to 30kV with no
problems. Bias current is at 29uA, same as
original TM2 bias current (see archiver for
  
  1975   Wednesday, September 04, 2019, 13:53 chad fisherSouth Hot-CellRepairTM4 TM3 CB to TM4The TM3 containment box has been installed
onto TM4. No issues, leak checked ok.
 
  
  1984   Thursday, September 12, 2019, 09:26 David WangITWRepairTM4 ITW bad vacuum issue and trouble shoot.ITW secondary vacuum was bad in last two
days after TM4 was connected in ITW. Today
when check the exit 2 module, I found a small
  
  2019   Thursday, October 31, 2019, 08:49 Anders MjosConditioning StationRepair  Water leak on non-active cooling water circuitYesterday a leak was discovered in the
ISAC-I experimental hall. The leak appears
to be at the connection between the evaporator
  
  2040   Friday, January 03, 2020, 13:15 Adam NewsomeCraneRepair  Target Hall Crane PLC Module/Battery ReplacementThe Target Hall Crane bridge and trolley motion
was lost after a period of the crane having
power disconnected over winter holidays.
  
  2074   Friday, February 28, 2020, 09:36 David WangITERepair  Entrance module TP1S broken piesces clean up. Using the camera,  Frank and I inspected
the broken  blades in vacuum duct bending
section. We are pretty sure some of 
  
  2083   Thursday, March 12, 2020, 13:48 David WangITERepair  Entrance module TP1S broken piesces clean up.The broken pieces in ITE entrance vacuum
pit are vacuumed out.  At SHC, There
are 4 pieces on module collimator block top, 
  
  2095   Friday, May 22, 2020, 13:26 David WangITWRepair  ITW water leak.A water leak was found on a fitting connecting
ITW dump return line pressure gauge on top
of exit module. TM tank flange, o-ring slot
 itw_water_leak_001.JPGitw_water_leak_005.JPGitw_water_leak_009.JPGitw_water_leak_013.JPG 
  2101   Thursday, June 11, 2020, 12:36 David WangSafe Module ParkingRepairTM3 TM3 containment box and service tray field measurement. At 15cm distance: Containment box   
  2108   Friday, June 19, 2020, 11:21 David WangITERepairTM4P2N test.ITE TP3 is replaced.ITE TP3 is replaced. ITE is under vacuum
again. All turbo pumps are started successfully.
Current draw on pumps are normal so far.
  
  2129   Tuesday, July 28, 2020, 09:26 chad fisherSouth Hot-CellRepair  Entrance Module Wire ScannerEntrance module wire scanner has been replaced.
Pictures to follow.
  