871
|
Wednesday, March 25, 2015, 10:37 |
chad fisher | South Hot-Cell | Development | | | TM2 optics tray build |
TM2 optics tray build is continuing. Going well. Hope to have assembly and alignment finished by Friday.
|
Attachment 1: 20150325_101718.jpg
|
|
Attachment 2: 20150325_101735.jpg
|
|
Attachment 3: 20150325_102024.jpg
|
|
|
885
|
Monday, April 13, 2015, 08:59 |
David Wang | ITE | Standard Operation | | | Target Hall Scheduled Activities April 07 - June 26 2015 |
See attachments 1, 2 for target hall schedule from 07 April to 26 June 2015. The first TM1 move which is scheduled on 16 April 2015 could be delayed because of SHC operator availability. I will update the schedule once Don confirms the move date with Isaac.
Updated the schedule. The TM1 move has been re-scheduled to Friday, 17 April 2015. See attachments 3,4. |
Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
|
|
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp
|
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
|
|
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp
|
|
886
|
Wednesday, April 15, 2015, 09:01 |
Anders Mjos | Conditioning Station | Development | | | Archiver variables added by Controls |
The following variable have been added to the archiver (as per work request)
TCS:TS5:RDTEMP
TCS:TCM1:EE:RDTEMP
TCS:TCM1:COIL1:RDTEMP
TCS:TCM1:TBHT:RDTEMP
TCS:TCM1:TGHT:RDTEMP
TCS:TCM1:MSP:RDTEMP
TCS:TCM1:HVC1:RDTEMP
TCS:TCM1:HS:RDTEMP
TCS:FC:SCALECUR
TCS:COL:SCALECUR
TCS:TK2:RDLEVEL
TCS:TK2:RDLEVEL
TCS:DIF1:RDFLOW
TCS:CHILL:RDHRS
The archiver was restarted.
|
|
903
|
Tuesday, April 28, 2015, 11:09 |
Anders Mjos | ITW | Maintenance | | | Resistance measured of TGHT and TBHT lines to ITW |
The new TBHT and TGHT power supplies were brough up to high current; 350 A and 420 A respectively. The TGHT power supply was limited by PLC to 420 A. The resistance calculated for both the TBHT and TGHT copper lines from the electrical services room to the ITW pit was 1.35 mOhm. See attached spreadsheet for details.
Dave Morris has been contacted to correct the current limit for the TGHT supply to 600 A. |
Attachment 1: Resistance_from_Electrical_Room_to_Target_Station.xlsx
|
|
909
|
Monday, May 04, 2015, 13:32 |
Anders Mjos | Conditioning Station | Maintenance | | | TK2 expansion tank topped up |
Caled cyclotron ops to open P23 and confirmed penthouse valve open.
Filled up TK2 to 21 in water leve. |
|
913
|
Monday, May 11, 2015, 10:45 |
Anders Mjos | Conditioning Station | Maintenance | | | RGA electronics box installed |
The communications chip has been replaced. The electronics box has been grounded (see attached pdf). |
Attachment 1: 2015-05_RGA_GND_connection.pdf
|
|
|
930
|
Wednesday, June 03, 2015, 11:22 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall Scheduled Activities April 07 - July 21 2015 |
I revised the Target Hall schedule to July 21 2015. It is the time new TM2 with ZrC target started at ITW.
2015-06-04, Updated the schedule with new PDF view. See attachments 3, 4 |
Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_July_21__2015.pdf
|
|
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp
|
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
|
|
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp
|
|
945
|
Friday, June 12, 2015, 13:27 |
David Wang | South Hot-Cell | Standard Operation | | | TM2 new source tray has been remotely transferred from TH into SHC successfully. |
TM2 new source tray has been remotely transferred into SHC successfully. The transfer table has been moved back to TH within 1 hour. I swiped the table and found about 150counts contamination. It is much better comparing to last time using since we removed this table out of SHC as quick as we can. The table will be cleaned with windex after Target Hall is surveyed. |
|
948
|
Monday, June 15, 2015, 14:14 |
David Wang | South Hot-Cell | Standard Operation | | | Target Hall Scheduled Activities April 07 - July 21 2015 |
Weekly update Target Hall schedule 2015-06-15. See attachment 1,2
2015-06-19, Update the schedule on the end of the week. See attachment 3,4 |
Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
|
|
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp
|
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp
|
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
|
|
|
957
|
Tuesday, June 23, 2015, 10:55 |
chad fisher | South Hot-Cell | Repair | | | Left Manipulator Repair |
The master wrist/tong cable has been replaced on the left manipulator. Everything appears to function well so far. |
|
959
|
Tuesday, June 23, 2015, 16:49 |
Anders Mjos | Conditioning Station | Development | | | TCS is beeing migrated to ISAC |
by controls group (Dave Morris).
Friday, June 26, 2015
TCS has been migrated to ISAC controls. Access is possible on a per user basis from isacepics1.triumf.ca |
|
968
|
Tuesday, June 30, 2015, 09:47 |
chad fisher | South Hot-Cell | Repair | | | manipulator repair |
The right hand manipulator has been repaired. It took 43 minutes and I received ~ 0.56 mSv |
|
975
|
Thursday, July 02, 2015, 11:51 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#12 | Spent target moved |
UC#12 has been moved from the south hot cell and placed into storage. It is in pail #125 and in spot 1C of the vault it had a reading of 25.1mSv/hr upon removal from the south hot cell. See PDF for vault details. |
Attachment 1: Vault_Storage_July_2_2015.pdf
|
|
|
977
|
Friday, July 03, 2015, 09:27 |
Anders Mjos | Conditioning Station | Development | | | Controls working on access control in EPICS |
Some reboots will be done. |
|
981
|
Tuesday, July 07, 2015, 10:50 |
Anders Mjos | Conditioning Station | Development | | | EPICS migration update - archiver |
- The archiver is now merged with ISAC - data available under Utilities - Archiver Retrieval
- Old archiver data is available under Utilities -> Archiver Retrieval - old
- Strip tool save/load and export files under /data/tcsdata
- Login via isacepics1.triumf.ca. TCS button on ISAC menu
|
|
982
|
Tuesday, July 07, 2015, 12:12 |
David Wang | Conditioning Station | Repair | | | CS TP1S replacement |
CS TP1S had been replaced with a new TP-301 pump this morning.The old pump was broken last week. |
|
999
|
Thursday, July 16, 2015, 07:38 |
David Wang | ITE | Standard Operation | | | Target Hall Scheduled Activities April 07 - August 07 2015 |
Update the TH schedule according to present TM2 refurbishment process. See attachments 1,2
2015-07-20 , Update the TH schedule after some changes on TM2 and TM4 arrangement. See attachments 3,4 |
Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdf
|
|
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.mpp
|
Attachment 3: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
|
|
Attachment 4: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp
|
|
1006
|
Tuesday, July 21, 2015, 12:29 |
David Wang | ITE | Maintenance | | | target pit Hepa filter |
Target pit Hepa filter has been replaced today. There is 500 counts on swipe which is taken inside of the replaced filter. The field measurement on the filter wood box is less than 0.5 usv/hr on contact. Right now,The outlets of the old filter are sealed with thick plastic and duct tape. The whole filter is wrapped with plastic sheet and tape. It has been moved to SHC ante room. It will be moved out of there by Tony.N soon with RPG help. |
|
1007
|
Tuesday, July 21, 2015, 12:38 |
David Wang | ITW | Repair | | | ITW external water leak on dump circuit has been fixed. |
The leaking 1/8 NPT(M)-1/4NPT(F) adapter on the ITW dump circuit is replaced. |
|
1010
|
Thursday, July 23, 2015, 10:23 |
David Wang | ITE | Standard Operation | | | Target Hall Scheduled Activities April 07 - August 019 2015 |
Update Target Hall schedule after the changing on TM2 process. See attachment 1,2 |
Attachment 1: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdf
|
|
Attachment 2: Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp
|