ID |
Date |
Author |
Category |
Type |
Subject |
Text |
 |
28
|
Thursday, January 23, 2014, 18:47 |
Grant Minor | Elevation Jack | Standard Operation | Cyclotron Lid-Up Report - 22 Jan 2014 | Yesterday Grant Minor (me), Maico Dalla
Valle, Dan Louie, and Arthur Leung worked
with Operations to perform the Cyclotron |
6x |
64
|
Thursday, March 26, 2015, 15:48 |
Grant Minor | Elevation Jack | Standard Operation | Cyclotron Lid-Up 26 March 2015 | Lid was raised today (2nd time during 2015
shutdown) for additional inflector work.
Dan and Maico report that the lid |
|
41
|
Monday, March 03, 2014, 15:07 |
Grant Minor | Elevation Jack | Standard Operation | Cyclotron Lid-Down Report Monday 3-March-2014 | The Cyclotron Lid Down was successfully
completed today on Work Permit C2014-03-03-6.
The system only tripped twice on |
|
103
|
Monday, January 08, 2018, 09:04 |
Maico Dalla Valle / Jason Kapalka | Cyclotron | Standard Operation | Cyclotron Lid Up | Remote Handing is ready for January, 8 2018
Cyclotron lid up. Elevating system service
has been completed.
|
|
68
|
Thursday, April 16, 2015, 15:26 |
Grant Minor | Elevation Jack | Maintenance | Cyclotron Elevating System Maintenance Rotation Record - Updated 16 Apr 2015 | |
|
143
|
Tuesday, May 10, 2022, 11:30 |
Nadia Jorgenson | Cyclotron | Repair | Cracked Festooning Rail Bushing Removed | We removed the left bushing that
is around the air cylinder on the festooning
rail, right outside the cyclotron. It was |
|
29
|
Friday, January 24, 2014, 14:10 |
Travis Cave | Cyclotron | Standard Operation | Copper blockers | The copper blockers have been removed from
the cyclotron and placed into the coffins. |
|
66
|
Friday, March 27, 2015, 11:25 |
Travis Cave | Cyclotron | Standard Operation | Copper Blockers | Copper Blockers have been removed from
the cyclotron and one ladder has been installed. |
|
169
|
Monday, February 26, 2024, 11:52 |
Adam Newsome | Cyclotron | Repair | Controls issue - CAMAC power supply | An issue was encountered on 2024-02-23
when attempting to operate the lift trolley.
|
|
61
|
Tuesday, March 10, 2015, 10:24 |
chad fisher | Elevation Jack | Maintenance | Contaminated equipment update | The harness, carabineer, and shock packed
used during the ISAC hot cell swipe have
been checked seperately by Mike and he has |
|
113
|
Wednesday, September 04, 2019, 15:29 |
Adam Newsome | Trolley | Maintenance | Connector faceplate and tubing upgrade | Tool Trolley:
The connector faceplate was replaced
with a new version to allow for more space |
|
88
|
Thursday, April 07, 2016, 11:04 |
Travis Cave | Cyclotron | Standard Operation | Closed the shield door | The shield door on the B2 level of the
RH building has been closed. |
|
60
|
Monday, March 09, 2015, 11:55 |
chad fisher | Elevation Jack | Maintenance | Checking for contamination on fall arrest equip. | Fall equipment from the lockers in the
RH shop have been checked for contamination
and the lockers themselves have been swiped. |
|
176
|
Thursday, May 16, 2024, 12:33 |
Riley Sykes | Service Bridge | Maintenance | Center Post Bearing | Center post bearing on service bridge
inspected, turned freely by hand and regreased
with Molub-Alloy 777-1 ES |
|
175
|
Tuesday, May 14, 2024, 10:53 |
Riley Sykes | Carrier | Maintenance | Carrier underrail wheels maintenance | All 4 Under rail wheels serviced
and cleaned. All Timken bearings repacked
with grease. No defects in any bearing set. |
|
177
|
Friday, May 31, 2024, 08:57 |
Riley Sykes | Carrier | Maintenance | Carrier Drive motor/gear reducer | Motor/Gearbox unit removed from carrier
and fully inspected and serviced. Oil changed
on May 29th using Mobil 600 W Super Cylinder |
|
69
|
Tuesday, July 28, 2015, 11:47 |
Dan McDonald | Trolley | Maintenance | Camera trolley service | Serviced the Camera trolley this morning
as per Mike Gallops service outline. |
|
96
|
Friday, March 03, 2017, 13:30 |
Jason Kapalka | Cyclotron | Standard Operation | CP continuity test | Performed continuity test at Cyclotron center
post with RH and Operations group members
using the service bridge,
|
|
43
|
Monday, April 28, 2014, 10:20 |
Dan McDonald | Service Bridge | Maintenance | Bridge orbit reduction box | Noticed oil leaking out of reduction box,
scan and swipe, disconnect e motor and all
related cables from bridge, remove motor |
|
161
|
Tuesday, November 14, 2023, 12:38 |
Nadia Jorgenson | Service Bridge | Maintenance | Bridge Orbit Counter Work in 2023 | All the bearings on both
the upper and lower wheel were replace to |
|