Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-Cyclotron, Page 2 of 10  Not logged in ELOG logo
ID Date Author Category Type Subjectdown Text Attachments
  62   Tuesday, March 17, 2015, 13:04 maicodallavalleCyclotronMaintenanceUpper Bearings Station #5 and #10The Upper bearings on Station #5 and Station
#10 have been serviced. The Upper Bearing
were disassembled. The old gear was removed
  
  23   Thursday, April 11, 2013, 19:00 Grant MinorElevation JackMaintenanceUpper Bearing at Jack Station 9 + Fall Protection UpgradesThere was a brief access period to the
Cyclotron vault during April 9 to 12, 2013
due to other Cyclotron issues.
 station_9_ceiling_anchors_SRLs_10april2013-002.JPGstation_9_ceiling_anchors_SRLs_10april2013-003.JPGstation_9_ceiling_anchors_SRLs_10april2013-004.JPGstation_9_ceiling_anchors_SRLs_10april2013-006.JPG 
  75   Tuesday, January 19, 2016, 17:59 Grant MinorElevation JackDevelopmentUpper Bearing Fall Protection Installation - Stations 1, 2, 6, 7, 8, 11, & 12The installation of the upper bearing fall
protection equipment was completed last week
by Dan and Maico.
 22x 
  46   Tuesday, January 13, 2015, 16:46 Grant MinorElevation JackDevelopmentUpper Bearing Fall Protect Guardrails TRH1217 Installed on Stns 8,10, 3, 4 & 55 x TRH1217 Upper Bearing Service Platform
assemblies were installed between January
6th and January 13th at Stations 8, 10, 3,
 9x 
  26   Friday, January 17, 2014, 07:53 Travis CaveTrolleys servicedStandard OperationTrolley checksAll trolleys work electrically and control
wise. One encoder was found non functioning
on the upper resonator trolley for the vertical
  
  141   Wednesday, May 04, 2022, 12:07 Adam NewsomeTrolleyDevelopmentTool Trolley: Brass air fittings replacement completeAll of the old brass air fittings on the
Tool Trolley have now been swapped over to
push-connect style fittings. As these are
  
  179   Friday, May 31, 2024, 12:47 Riley SykesTrolleys servicedMaintenanceTool Trolley Scheduled Maintenance 60 month service completed. Bearings
for drive motor wheels regreased, Reducer
repacked with Molub Alloy 777-1 ES,
 Tool_Trolley_Drive_Motor.jpg 
  1   Monday, June 27, 2011, 10:38 John WongGeneralRoutineTesting RH elog    
  18   Thursday, March 14, 2013, 19:57 Grant MinorCyclotronRepairTank lid upper / over travel limit checkToday Grant Minor, Dan Wright, Arthur Leung,
and Dan Louie checked the height difference
between the tank lid upper travel limit switch
 cyclotron_over_travel_limit_check_Station10_14Mar2013_003.JPGcyclotron_over_travel_limit_check_Station1_14Mar2013_001.jpg 
  16   Friday, March 08, 2013, 18:42 Grant MinorCyclotronRepairTank lid not at upper limit and resulting effectsThis morning during routine service bridge
work in the Cyclotron tank, it was observed
by Travis Cave that the cable tray for the
 Contact_btwn_cable_tray_and_upper_equip_8Mar2013.PNGJack_upper_limit_switch_not_engaged_8Mar2013.pngJack_upper_limit_switch_engaged_8Mar2013.pngCyclotron_height_stick_half_inch_from_roof_8Mar2013.JPGCyclotron_height_stick_final_position_8Mar2013.jpg 
  70   Thursday, September 17, 2015, 18:38 Grant MinorElevation JackMaintenanceStation 9 Jack Worm Gear Inspection - unusual wear markings 16Sept2015Unusual wear markings were observed on
the Station 9 jack (not sure if L or R jack?)
during a visual inspection.
 8x 
  71   Wednesday, September 30, 2015, 11:26 Isaac EarleElevation JackStandard OperationStation 9 Jack Right Side - Unusual Wear InvestigationThe following people were consulted
regarding the unusal wear noticed on jack
station #9 right side
 7x 
  72   Wednesday, September 30, 2015, 11:52 Isaac EarleElevation JackStandard OperationStation 9 Jack Left Side - Inspection & Service StatusThe left side jack was disassembled and
cleaned.  It was discovered that the
left side had been rebuilt with a new jack
 15x 
  112   Tuesday, January 22, 2019, 07:18 Dan McDonaldElevation JackMaintenanceStation 11-12 jack swap and hoist plate instalPrior to commencing work on jacking stations
we installed a wall mounted come along plate
as per Jason kapalkas instructions  
  
  98   Tuesday, March 14, 2017, 11:23 Jason KapalkaCyclotronStandard OperationStart/end of shutdown photo and video surveyThe start of shutdown photo and video survey
was performed in the Cyclotron tank by the
RH group using the 
 Cyclotron_Video_Inspecting_Guidelines_(RevX_20170314).xlsx 
  32   Wednesday, January 29, 2014, 15:08 Bevan MossCyclotronStandard OperationShielding and Port Hole Covers The Shielding and the Port Hole Covers
have all been installed. No issues with the
installation have caused any problems. This
  
  91   Tuesday, January 31, 2017, 14:41 Travis CaveCyclotronStandard OperationShield installation200, 400, 500, 600, and a pallet of 700
series of shield have been installed in the
cyclotron.
  
  136   Wednesday, January 19, 2022, 09:50 Travis CaveShieldingStandard OperationShield door is now open The shield door is now open on the
RH B2 level.
  
  58   Friday, March 06, 2015, 14:38 Travis CaveCyclotronStandard OperationShield RemovalAll shields and ladders have been removed
from the tank, all the port holes have been
uncovered, the tank seal has been vacuumed,
  
  126   Wednesday, January 13, 2021, 11:35 Adam NewsomeShieldingMaintenanceShadow Shields Inspection - 2021 ShutdownAll shadow shields which are remotely placed
inside the cyclotron during shutdown were
inspected by Adam Newsome and Chris Peterson
  
ELOG V2.9.2-2455