ID |
Date |
Author |
Category |
Type |
Subject |
Text |
|
|
153
|
Wednesday, April 26, 2023, 11:19 |
Adam Newsome | Cyclotron | Standard Operation | Vault Shield Door Closed | The vault shield door has been closed and
seal inflated. The operation was performed
with no issue. |
|
|
152
|
Friday, March 31, 2023, 13:22 |
Adam Newsome | Cyclotron | Standard Operation | Lid down operation - 2023 | The lid down operation
took place on Mar. 31, 2023. |
|
|
151
|
Tuesday, March 28, 2023, 12:02 |
Nadia Jorgenson | Service Bridge | Repair | Outrigger 1 Failure and Repair |
During
the 2023 shutdown outrigger 1 failed. While |
|
|
150
|
Friday, February 03, 2023, 08:27 |
Eric Lahe | Elevation Jack | Maintenance | Elevating System Jack Inspection | Annual Jack Inspection: The annual
elevation system inspection has been completed
(Jan 31,2023). |
|
|
149
|
Thursday, February 02, 2023, 07:05 |
maicodallavalle | Service Bridge | Repair | Hinged Festoon Rail at Cyclotron | The Hinged section of the festoon rail
at Cyclotron has a piston to keep rail in
the up position for shutdown work (Bridge |
|
|
148
|
Monday, January 30, 2023, 12:20 |
Adam Newsome | Cyclotron | Standard Operation | Lid up operation - 2023 | The lid up operation
took place on Jan. 30, 2023. |
|
|
147
|
Friday, January 27, 2023, 12:12 |
Adam Newsome | Infrastructure | Development | Vault crane - inspection, remote pendant installation | The vault crane annual inspection was completed
by Tom Kauss.
|
|
|
146
|
Thursday, October 06, 2022, 17:15 |
Adam Newsome | Elevation Jack | Maintenance | Preventative Maintenance: MCC-E elevating system motor contactors | Under work permit C2022-10-04-1,
the motor contactors for jack motors 1 through
12 were replaced. The contactors showed signs |
|
|
145
|
Wednesday, June 29, 2022, 12:12 |
Adam Newsome | Probe | Development | LE1/LE2 Probe Frame - Updates | The LE1/LE2 Probe Frame was mounted on
the Upper Resonator Trolley in the mockup
with the intention of confirming functionality |
|
|
144
|
Tuesday, May 10, 2022, 11:31 |
Nadia Jorgenson | Cyclotron | Standard Operation | Vault Shield Door Closed | The vault shield door
has been closed and seal inflated. The operation |
|
|
143
|
Tuesday, May 10, 2022, 11:30 |
Nadia Jorgenson | Cyclotron | Repair | Cracked Festooning Rail Bushing Removed | We removed the left bushing that
is around the air cylinder on the festooning
rail, right outside the cyclotron. It was |
|
|
142
|
Tuesday, May 10, 2022, 11:26 |
Nadia Jorgenson | Cyclotron | Repair | Festooning rail rope and pulley system re-routed | The rope and pulley system that is used
to raise the festooning rail across the vault
shield door has been re-routed. It now makes |
|
|
141
|
Wednesday, May 04, 2022, 12:07 |
Adam Newsome | Trolley | Development | Tool Trolley: Brass air fittings replacement complete | All of the old brass air fittings on the
Tool Trolley have now been swapped over to
push-connect style fittings. As these are |
|
|
140
|
Wednesday, April 27, 2022, 16:05 |
Adam Newsome | Cyclotron | Standard Operation | Lid down operation - 2022 | The lid down operation
took place on Apr. 27, 2022. |
|
|
139
|
Monday, March 21, 2022, 13:14 |
Adam Newsome | Trolley | Repair | Video Trolley Mk 1 - Radial Limit Switch Replacement | An issue was observed in which radial motion
on the Video Trolley Mk 1 did not respond
to commands. After troubleshooting, it was |
|
|
138
|
Tuesday, February 08, 2022, 11:39 |
Adam Newsome | Cyclotron | Development | Radiation Survey - sampling rate error | When attempting to perform the radiation
survey, the program displayed an error at
startup stating that the software was not |
|
|
137
|
Friday, February 04, 2022, 11:52 |
Adam Newsome | Cyclotron | Standard Operation | Lid up operation - 2022 | The lid up operation
took place on Feb. 4, 2022. |
|
|
136
|
Wednesday, January 19, 2022, 09:50 |
Travis Cave | Shielding | Standard Operation | Shield door is now open | The shield door is now open on the
RH B2 level. |
|
|
135
|
Tuesday, August 31, 2021, 14:28 |
Adam Newsome | Trolleys serviced | Development | Upper Resonator Trolley - Finger Cylinders Replaced | The two support fingers on the upper resonator
trolley were bent due to excessive loading
during cylinder toggling. |
|
|
134
|
Wednesday, June 16, 2021, 09:59 |
Adam Newsome | Service Bridge | Development | Bridge Lift Mechanism Refurbishment (Phase 1 of 2) - Complete | The following items from Phase 1 of 2 of
Bridge Lift Mechanism Refurbishment (O504)
are complete: |
|