Entry  Tuesday, November 14, 2023, 12:13, Nadia Jorgenson, Service Bridge, Repair, First Festooning Car "H" channel replacement  Festooning_car_H_channel_deformation.pngFestooning_car_H_channel_bottom_face.png
Entry  Wednesday, October 18, 2023, 12:35, Jason Zhang, Service Bridge, Development, O503 Bridge and Outrigger integration testing 
Entry  Friday, September 15, 2023, 10:15, Adam Newsome, Trolley, Maintenance, Lift Trolley: mirror actuation mechanism repair/upgrade PXL_20230915_164811247.jpg
Entry  Thursday, September 14, 2023, 13:51, Adam Newsome, Trolley, Maintenance, Lift Trolley: upgrades to camera tilt mechanism PXL_20230914_193143524.jpg
Entry  Thursday, September 07, 2023, 13:21, Jason Zhang, Service Bridge, Development, Outrigger #1 and #2 individual testing complete 
Entry  Thursday, August 03, 2023, 10:43, Adam Newsome, Trolley, Development, Previous generation video trolley decommissioned 
Entry  Friday, July 28, 2023, 12:05, Adam Newsome, Cyclotron, Development, Maintenance ladders: end caps added PXL_20230728_184520962.jpg
Entry  Wednesday, April 26, 2023, 11:19, Adam Newsome, Cyclotron, Standard Operation, Vault Shield Door Closed 
Entry  Friday, March 31, 2023, 13:22, Adam Newsome, Cyclotron, Standard Operation, Lid down operation - 2023 Elevation_System_Checklist_-_March_31_2023.pdf
Entry  Tuesday, March 28, 2023, 12:02, Nadia Jorgenson, Service Bridge, Repair, Outrigger 1 Failure and Repair Outrigger_1_Repair_2023.png
Entry  Friday, February 03, 2023, 08:27, Eric Lahe, Elevation Jack, Maintenance, Elevating System Jack Inspection  Elevation_System_Checklist_-_Jan312023.xlsx
Entry  Thursday, February 02, 2023, 07:05, maicodallavalle, Service Bridge, Repair, Hinged Festoon Rail at Cyclotron  
Entry  Monday, January 30, 2023, 12:20, Adam Newsome, Cyclotron, Standard Operation, Lid up operation - 2023  2023_Synchro_Counts.xlsx2023_Jacks_Infrared_Data.xlsx
Entry  Friday, January 27, 2023, 12:12, Adam Newsome, Infrastructure, Development, Vault crane - inspection, remote pendant installation 
Entry  Thursday, October 06, 2022, 17:15, Adam Newsome, Elevation Jack, Maintenance, Preventative Maintenance: MCC-E elevating system motor contactors Elevating_System_Motor_Contactors_2022-10-06.png
Entry  Wednesday, June 29, 2022, 12:12, Adam Newsome, Probe, Development, LE1/LE2 Probe Frame - Updates PXL_20220629_175832571.jpg
Entry  Tuesday, May 10, 2022, 11:31, Nadia Jorgenson, Cyclotron, Standard Operation, Vault Shield Door Closed 
Entry  Tuesday, May 10, 2022, 11:30, Nadia Jorgenson, Cyclotron, Repair, Cracked Festooning Rail Bushing Removed Festooning_Bushing_Cracked.jpg
Entry  Tuesday, May 10, 2022, 11:26, Nadia Jorgenson, Cyclotron, Repair, Festooning rail rope and pulley system re-routed 
Entry  Wednesday, May 04, 2022, 12:07, Adam Newsome, Trolley, Development, Tool Trolley: Brass air fittings replacement complete 