Entry  Tuesday, January 29, 2013, 16:28, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair (ground fault) 
Restored shielding over 1A triplet chase.
 
Uncovered Q16 and set up RH bridge with lead blankets over Q16. 
Entry  Monday, January 28, 2013, 16:28, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair (ground fault) 6x
Rad survey map from last Friday (25 January) here.
 
Found exposed thermal switch cable in triplet service chase.
Entry  Friday, January 25, 2013, 15:15, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair (ground fault) 20130125_tripletrepair_IMG_0071.JPG20130125_tripletrepair_IMG_0067.JPG
Today: Uncovered 1A triplet cable chase and reconfigured shielding. D. Preddy will continue with diagnosing ground fault on Monday.
Entry  Thursday, January 24, 2013, 17:05, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair (ground fault) 20130124_tripletrepair_IMG_0047.JPG20130122_tripletrepair_IMG_0011.JPG20130124_tripletrepair_IMG_0040.JPG
Continued with work on finding ground fault on 1A triplet;
 
Uncovered Q15 & 16 to 1AS1 area. See photo below for setup.
Entry  Wednesday, January 23, 2013, 15:51, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair (ground fault) 20130123_tripletrepair_P1020666.JPG20130123_tripletrepair_P1020664.JPG20130123_tripletrepair_P1020669.JPG
Continued work on finding ground fault in 1A triplet magnets;
 
D. Preddy connected ohmeters to 1AQ14 & 15 power supplies with power leads disconnected. Ohmmeters were connected from magnet power leads to
Entry  Tuesday, January 22, 2013, 16:02, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair 20130122_tripletrepair_IMG_0018_webm.jpg
1.5 day work delay due to plant group unavailable on the 21st of January. Gardner air compressor was being moved.
 
Today:
Entry  Friday, January 18, 2013, 14:40, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair 20130118_tripletrepair_RHB_5431-web_m.jpg
Completed uncovering shielding and RH setup over 1A Q14 triplet area, see photo for RH setup.
Entry  Wednesday, January 16, 2013, 17:03, Keith C Ng, Primary Beamlines, Repair, 1A triplet repair 
Moved 18' blocks away from triplet area in preparation for uncovering triplet. Plastic laid down up stream of t2 target station for short term storage
of 6' layered blocks.
Entry  Tuesday, January 15, 2013, 16:37, Keith C Ng, Primary Beamlines, Maintenance, 1AVA8 valve o ring replacement 
Job completed today and shielding block over valve restored.
- He leak checked valve and accessible up stream joints, no leaks found.
- J McKinnon checked power supplies for nearby steering magnets before and after covering valve. supplies working ok.
Entry  Monday, January 14, 2013, 16:36, Keith C Ng, Primary Beamlines, Maintenance, 1AVA8 valve o ring replacement 
continued with o ring replacement, replaced all relevant o ring seals on valve (valve body seal and actuator arm dynamic seals).
- valve re installed and services reconnected.
- valve cycled and checked; valve, limit switches ok.
Entry  Friday, January 11, 2013, 15:44, Keith C Ng, Primary Beamlines, Maintenance, 1AVA8 valve o ring replacement 
Assisted vacuum group with removing 1AVA8:
- uncovered valve area and set up remote handling bridge over valve.
- shut off pneumatic supply to valve to render valve in mid position (shut off valve in 1A tunnel). disconnected electrical services and air supply
Entry  Wednesday, October 24, 2012, 11:53, Keith C Ng, M9, Repair, M9 T2 blank off complete 201211_m9t2repair.xlsx
Shielding around m9 t2 restored as of 11:45, vacuum levels still the same since 19 October.
- Work permit returned.
- A dose record of the job is attached as a spread sheet. Total dose for all workers is 1.89 mSv for the job.
Entry  Monday, October 22, 2012, 15:48, Keith C Ng, M9, Repair, M9 T2 clean up and shield restoration 20121022_RH1_02_0092.JPG20121022_RH1_02_0081.JPG20121022_RH1_02_0082.JPG
Today;
Restoring shielding at M9 T2 area and cleaning up RH setup.
 
Entry  Friday, October 19, 2012, 18:21, Grant Minor, M9, Development, 8" double-ring test samples of EPDM and BUNA-N (Nitrile) BC_RUBBER_SUPPLY_PS_VA-B18799.pdf20121019_RH2_02_0025.JPG20121019_RH2_02_0027.JPG20121019_RH2_02_0029.JPG20121019_RH2_02_0031.JPG
Today I picked up two 2FT x 4Ft x 0.125" thick strips of stock EPDM and BUNA-N (Nitrile) material from BC Rubber Supply.  A copy of the Packing
Slip is attached.  Here is the information from the Sample Sheet:
 
Entry  Friday, October 19, 2012, 16:48, Keith C Ng, M9, Repair, M9 T2 Joint Repair cont. 20121019_RH1_01_0081.JPG20121019_RH1_01_0082.JPG20121019_RH2_02_0004.JPG
Today:
Cleaned up work site and removed extraneous poles and tooling. Radioactive parts stored in lead flask now located on TNF.
- Two pins, an RH bullet bolt and indium ring (tb22148) were put into lead flask for storage, flask now located on TNF.
Entry  Thursday, October 18, 2012, 16:28, Keith C Ng, M9, Repair, M9 T2 joint repair cont. T2_Remote_Leak_Check.PDF20121018_m9q2_waterleak.jpg
Today:
Completed leak check of M9 T2 area: joint(s) are He leak tight. Remote He lines checked as well, see attached.
 
Entry  Thursday, October 18, 2012, 08:26, Keith C Ng, M9, Repair, M9 T2 joint repair cont. 
Yesterday:
Installed indium blank off at M9 T2 joint and pumped down at 15:20 to 15:45 overnight. 1ACG7 (T2 vacuum pressure) reads between 6.0E-3mT and 2.0E-2
mT as of 8:15 today.
Entry  Tuesday, October 16, 2012, 19:50, Grant Minor, M9, Repair, M9T2 Joint Repair - Status Update 16 Oct 2012 M9T2_Joint_Repair_-_Status_Update_16_Oct_2012.pdf
See attached.
Entry  Tuesday, October 16, 2012, 19:47, Grant Minor, M9, Repair, Inspection of failed double-indium thru-ring TB22148 TB22148_thru_ring_inspT2_15oct2012.pdfTB22148_thru_ring_inspQ1_15oct2012.pdf
See inspection notes attached for failed M9T2 double-indium thru-ring TB22148, inspected on Oct 15th 2012.
Ring was approximately 3 mSv/hr on contact and 100 uSv/hr at 0.5 m.
Total dose accumulated during inspection on dosimeter 122 was 0.1 mSv
Entry  Monday, October 15, 2012, 17:03, Keith C Ng, M9, Repair, M9 T2 joint repair cont. 
Today:
- Removed pins and removed indium through ring. Joint fully open at 14.5 to 15 turns of retraction mechanism.
- Did initial video inspection of T2 and Q1 flanges, some residual indium on knife surfaces, did initial scraping of T2 flange. (see videos on