  81   Friday, April 10, 2015, 16:25 Keith C NgM9Developmentm9 t2 alignment jobContinued with installation of target jigs:
1) Craned in equipment for alignment
group.
  
  82   Tuesday, April 14, 2015, 08:31 Keith C NgM9Developmentm9 t2 alignment jobYesterday:
1) Addressed mounting issue with
the 15" alignment jig: removed material
 20150414_m9t2_P1030289.JPG20150414_m9t2_P1030290.JPG20150414_m9t2_P1030295.JPG20150414_m9t2_P1030297.JPG 
  83   Thursday, April 16, 2015, 09:17 Keith C NgM9Developmentm9 t2 alignment jobYesterday (Apr 15):
1) Installed TB22265 on to M9 exit
port at 18:48 with no vacuum and left over
 9x 
  84   Friday, April 17, 2015, 15:11 Keith C NgM9Developmentm9 t2 alignment jobToday: Restored filler shielding in T2
M9 Q1Q2 hole.
- Blocks marked with beam direction
 6x 
  113   Thursday, March 15, 2018, 15:48 Keith C NgM9Maintenancem9 t2 alignment jobBlank off removed this morning, video recorded
the T2 flange,B1 flange and B1 vacuum box
interior. Blank off is 150 uSv/h @ .5m, 3
  
  124   Monday, February 24, 2020, 15:13 Keith C NgM9Repairm9 q1q2 repair laser tracker shootBeamlines
shot the position of the M9 T2 port and B1
flange for setting the M9 test stand flanges
 20200224_m9project_P1040686.JPG20200224_m9project_P1040688.JPG 
  112   Tuesday, March 13, 2018, 15:36 Keith C NgM9Standard Operationm9 alignment workSet up shielding canyon for M9 laser tracker
job.
 dms.jpg 
  2   Tuesday, February 14, 2012, 16:29 Keith C NgM20Repairm20 q1 q2 repairWarm cell reconfigured for water leak repair
at coil termination. Radiation surveys done.
M20 Q1 ready for  removal of insulators.
 P1010986.JPG 
  3   Thursday, February 16, 2012, 08:08 Keith C NgM20Repairm20 q1 q2 repairInsulators # 6,7,8 removed from Q1 headers
late afternoon by C Ballard. Ready for removal
and re-brazing of #7 joint some time today.
 P1020003.JPGP1020001.JPG 
  4   Thursday, February 16, 2012, 16:22 Keith C NgM20Repairm20 q1 q2 repairOld #7 coil fitting removed, replaced and
re-brazed today by M Good. Insulators ready
to go back on to magnet coils to be pressure
 IMG_2545.JPGP1020013.JPGP1020028.JPG 
  5   Friday, February 17, 2012, 15:35 Keith C NgM20Repairm20 q1 q2 repairReinstalled ceramic insulators #6 7 8 to
Q1 magnet by C Ballard. #6 and 8 went on
with no issues. The copper tubing on insulator
 P1020033.JPGP1020037.JPGP1020038.JPGP1020035.JPGP1020031.JPG 
  122   Tuesday, September 24, 2019, 14:37 Keith C NgPrimary BeamlinesStandard Operationlead pig radiation surveySurveyed contents of storage flask located
at TNF. The lid was lifted off roughly 12"
up and a pole monitor was swept over the
  
  104   Wednesday, March 08, 2017, 16:05 Keith C NgPrimary BeamlinesRepaircollimator joint repairStarted uncovering the area above the T2
to Q13 joint:
 
 t2m920170308_114226_1136.jpgt2m920170308_151426_1438.jpg 
  105   Thursday, March 16, 2017, 15:50 Keith C NgPrimary BeamlinesRepaircollimator b transition to t2On Monday found leaking joint was the ring
directly downstream of T2. Vacuum group has
been spraying Vacseal (http://www.vacseal.net/Pages/default.aspx)
 20170316_collimatorb_RHB_8023.JPG20170316_collimatorb_RHB_8025.JPG 
  1   Thursday, June 30, 2011, 16:58 John WongPrimary BeamlinesRepairblah blah blahdfdfdfdfdf   
  123   Thursday, October 24, 2019, 14:41 Keith C NgPrimary BeamlinesMaintenanceannotated drawing of 1A Q15 cooling headers Annotated drawing of TBP0425D attempting
to capture the repairs of 1A Q15 triplet
magnet ceramic insulator/coils over the years.
 tbp0425d_revB_acad-magnetinsulatortopheaderassembly_w-repairannotations.pdf 
  126   Thursday, March 19, 2020, 15:42 Keith C NgPrimary BeamlinesDevelopmentVault beamline beam position monitorThe Beam Position Monitor between 1VB1
and 1VM3 has been installed. The indium joints
are leak tight, however the V flanges are
  
  87   Thursday, February 18, 2016, 16:34 Keith C NgPrimary BeamlinesDevelopmentVault beam line 4V disassemblyDisconnected all 4V beamline joints. Parts
for indium joints removed except for the
Q1 to downstream monitor box and monitor
  
  61   Tuesday, February 03, 2015, 16:35 Keith C NgPrimary BeamlinesDevelopmentUCN T1 shutdown workRH bridge has been set up over T1 to Q1Q2
area, see images for radiation survey of
work area. Joint is still intact, work will
 INBOX)3363.jpegINBOX)33632.jpeg 
  62   Wednesday, February 04, 2015, 16:12 Keith C NgPrimary BeamlinesDevelopmentUCN T1 shutdown workUCN T1 work continues:
- Retracted Q1 T1 pindrive, took
34.5 turns. Pins left bolted to T1 monument.
  
ELOG V2.9.2-2455