29
|
Tuesday, January 29, 2013, 16:28 |
Keith C Ng | Primary Beamlines | Repair | 1A triplet repair (ground fault) | Restored shielding over 1A triplet chase.
Uncovered Q16 and set up RH bridge |
|
|
28
|
Monday, January 28, 2013, 16:28 |
Keith C Ng | Primary Beamlines | Repair | 1A triplet repair (ground fault) | Rad survey map from last Friday (25 January)
here.
|
6x |
|
27
|
Friday, January 25, 2013, 15:15 |
Keith C Ng | Primary Beamlines | Repair | 1A triplet repair (ground fault) | Today: Uncovered 1A triplet cable chase
and reconfigured shielding. D. Preddy will
continue with diagnosing ground fault on |
|
|
26
|
Thursday, January 24, 2013, 17:05 |
Keith C Ng | Primary Beamlines | Repair | 1A triplet repair (ground fault) | Continued with work on finding ground fault
on 1A triplet;
|
|
|
25
|
Wednesday, January 23, 2013, 15:51 |
Keith C Ng | Primary Beamlines | Repair | 1A triplet repair (ground fault) | Continued work on finding ground fault
in 1A triplet magnets;
|
|
|
24
|
Tuesday, January 22, 2013, 16:02 |
Keith C Ng | Primary Beamlines | Repair | 1A triplet repair | 1.5 day work delay due to plant group unavailable
on the 21st of January. Gardner air compressor
was being moved. |
|
|
23
|
Friday, January 18, 2013, 14:40 |
Keith C Ng | Primary Beamlines | Repair | 1A triplet repair | Completed uncovering
shielding and RH setup over 1A Q14 triplet
area, see photo for RH setup. |
|
|
22
|
Wednesday, January 16, 2013, 17:03 |
Keith C Ng | Primary Beamlines | Repair | 1A triplet repair | Moved 18' blocks away from triplet area
in preparation for uncovering triplet. Plastic
laid down up stream of t2 target station |
|
|
21
|
Tuesday, January 15, 2013, 16:37 |
Keith C Ng | Primary Beamlines | Maintenance | 1AVA8 valve o ring replacement | Job completed today and shielding block
over valve restored.
- He leak checked valve and accessible |
|
|
20
|
Monday, January 14, 2013, 16:36 |
Keith C Ng | Primary Beamlines | Maintenance | 1AVA8 valve o ring replacement | continued with o ring replacement, replaced
all relevant o ring seals on valve (valve
body seal and actuator arm dynamic seals). |
|
|
19
|
Friday, January 11, 2013, 15:44 |
Keith C Ng | Primary Beamlines | Maintenance | 1AVA8 valve o ring replacement | Assisted vacuum group with removing 1AVA8:
- uncovered valve area and set up
remote handling bridge over valve. |
|
|
18
|
Wednesday, October 24, 2012, 11:53 |
Keith C Ng | M9 | Repair | M9 T2 blank off complete | Shielding around m9 t2 restored as of 11:45,
vacuum levels still the same since 19 October.
- Work permit returned. |
|
|
17
|
Monday, October 22, 2012, 15:48 |
Keith C Ng | M9 | Repair | M9 T2 clean up and shield restoration | Today;
Restoring shielding at M9 T2 area
and cleaning up RH setup. |
|
|
16
|
Friday, October 19, 2012, 18:21 |
Grant Minor | M9 | Development | 8" double-ring test samples of EPDM and BUNA-N (Nitrile) | Today I picked up two 2FT x 4Ft x 0.125"
thick strips of stock EPDM and BUNA-N (Nitrile)
material from BC Rubber Supply. A copy |
|
|
15
|
Friday, October 19, 2012, 16:48 |
Keith C Ng | M9 | Repair | M9 T2 Joint Repair cont. | Today:
Cleaned up work site and removed
extraneous poles and tooling. Radioactive |
|
|
14
|
Thursday, October 18, 2012, 16:28 |
Keith C Ng | M9 | Repair | M9 T2 joint repair cont. | Today:
Completed leak check of M9 T2 area:
joint(s) are He leak tight. Remote He lines |
|
|
13
|
Thursday, October 18, 2012, 08:26 |
Keith C Ng | M9 | Repair | M9 T2 joint repair cont. | Yesterday:
Installed indium blank off at M9
T2 joint and pumped down at 15:20 to 15:45 |
|
|
12
|
Tuesday, October 16, 2012, 19:50 |
Grant Minor | M9 | Repair | M9T2 Joint Repair - Status Update 16 Oct 2012 | See attached. |
|
|
11
|
Tuesday, October 16, 2012, 19:47 |
Grant Minor | M9 | Repair | Inspection of failed double-indium thru-ring TB22148 | See inspection notes attached for failed
M9T2 double-indium thru-ring TB22148, inspected
on Oct 15th 2012. |
|
|
10
|
Monday, October 15, 2012, 17:03 |
Keith C Ng | M9 | Repair | M9 T2 joint repair cont. | Today:
- Removed pins and removed indium
through ring. Joint fully open at 14.5 to |
|