ID |
Date |
Author |
Target Material |
Target Oven W.O# |
Source |
Status |
Subject |
|
659
|
Friday, April 26, 2024, 06:19 |
Darwin Ortiz Rosales | TaC | 45447-29 | HP-SIS | Done | TaC coating sintering |
Monday, April 29, 2024, 19:50
Started coating with coating stand.
The coated container was wrapped in 3 Ta foil heatshields.
Vacuum IGP1 initial =9.1 e-07 Torr
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~700A (adjustable)
Heating autoramp starged at 2A/min(1A/30s) on TGHT 100A
Then at 2A/min to =700 A TGHT and 230A TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Monday, April 29, 2024, 20:25
Reached 1810 @700A
Will leave until 1230am |
|
658
|
Thursday, April 04, 2024, 12:07 |
Darwin Ortiz Rosales | TiC | | LP TUBE | Done | 240404TiC sintering/conditioning | Thursday, April 04, 2024, 12:06
Ta container tube, wrapped in 4 Ta foil heat-shields, and loaded with _________ D shaped discs in a 12mm graphite cartridge with usable 11mm
conditioning tube WO = 44692-13 (4th conditioning with this tube)
End-caps on the graphite cartridge have holes for outgassing. One spring each end in the Ta container
initial heating @ 2A/min to 85 A then 2A/min to 120A TGHT
OMEGA slope = 0.99
Vacuum limits up to 400A: 5.0e-04 Torr -- 1.0e-02 Torr
Mas current~400A (1900 C)
Friday, April 05, 2024, 09:04
Ramping to 85A done and pressure trending down. Will continue ramp to 120A
Friday, April 05, 2024, 16:01
Starting rampdown at -2A/min
IGP1= 3.2e-06 Torr
|
|
657
|
Wednesday, April 03, 2024, 06:46 |
Darwin Ortiz Rosales | TiC | | LP TUBE | Done | 240402TiC | Wednesday, April 03, 2024, 06:46
Ta container tube, wrapped in 4 Ta foil heat-shields, and loaded with _________ D shaped discs in a 12mm graphite cartridge with usable 11mm
conditioning tube WO = 44692-13
End-caps on the graphite cartridge have holes for outgassing. One spring each end in the Ta container
initial heating @ 2A/min to 85 A then 2A/min to 120A TGHT
OMEGA slope = 0.99
Vacuum limits up to 400A: 5.0e-04 Torr -- 1.0e-02 Torr
Wednesday, April 03, 2024, 06:49
initial IGP1= 1.28e-06 Torr
Wednesday, April 03, 2024, 09:26
IGP1= 2.3e-05 Torr
TGHT = 78 A, 1.3V
Will continue ramp as planned.
Wednesday, April 03, 2024, 11:37
Ramping at 2A./min to 400A
Wednesday, April 03, 2024, 14:01
expected 1900C at 401A
leaving at 402A for 4 hours. Rampdown start at 4:10 pm at -2A/min |
|
656
|
Thursday, February 29, 2024, 07:40 |
Darwin Ortiz Rosales | TiC | | LP TUBE | Done | 240228TiC conditioning | Thursday, February 29, 2024, 07:40
Ta container tube, wrapped in 4 Ta foil heat-shields, and loaded with _________ D shaped discs in a 12mm graphite cartridge with usable 11mm
conditioning tube WO = 44692-13
End-caps on the graphite cartridge have holes for outgassing. One spring each end in the Ta container
initial heating @ 2A/min to 85 A then 2A/min to 120A TGHT
OMEGA slope = 0.99
Vacuum limits up to 400A: 5.0e-04 Torr -- 1.0e-02 Torr
Thursday, February 29, 2024, 07:43
Initial IGP1= 9.31e-7 Torr
Thursday, February 29, 2024, 17:43
Temperature profile suggests 1900 C at 400A. Now at 400A. Will keep at this current for 4 hours.
manually ramped the last few amps.
TGHT= 400A, 7.3 V OMEGA = 1901C
Thursday, February 29, 2024, 22:20
IGP1=2.1e-6 Torr
started ramping down at -2A/min
|
|
655
|
Wednesday, February 21, 2024, 06:23 |
Darwin Ortiz Rosales | TiC | | LP TUBE | Done | 240220TiC conditioning | Wednesday, February 21, 2024, 06:22
Ta container tube, wrapped in 4 Ta foil heat-shields, and loaded with 201 D shaped discs in a 12mm graphite cartridge with usable 11mm
conditioning tube WO = 44692-13
End-caps on the graphite cartridge have holes for outgassing. One spring each end in the Ta container
initial heating @ 2A/min to 90 A then 1A/min to 120A TGHT
OMEGA slope = 0.99
Vacuum limits up to 400A: 5.0e-04 Torr -- 1.0e-02 Torr
Wednesday, February 21, 2024, 09:12
IGP1 initial = 9e-07 Torr
Starte at 3A/min to 90A
Wednesday, February 21, 2024, 09:21
increased autoramp to 4 A/min until pressure starts rising, then will slow down or pause
Wednesday, February 21, 2024, 09:32
At 74A, paused. Will continue at 2A/min TGHT
Wednesday, February 21, 2024, 09:40
Pausing at 87A.
Wednesday, February 21, 2024, 10:34
pressure dropping. restarting ramp up to 120A at 2A/min
Wednesday, February 21, 2024, 10:37
From previous TiC 220206, will heat up fast until 250A and then at 1A/min until 300A to better resolve out-gassing profile
Wednesday, February 21, 2024, 12:05
Changed ramp to 1A/min to 300A
Wednesday, February 21, 2024, 13:10
Manually ramped up for a while
increased ramp speed to 2A/min
regression line started to match previous one after 1300C
Wednesday, February 21, 2024, 13:16
increased ramp rate to 4A/min to 420A
Wednesday, February 21, 2024, 13:37
Note: the temperature became unrealistic. suspect window condensate. Will use regression and to to 441A
Wednesday, February 21, 2024, 13:54
reached 441A, 7.6V
leaving for 3.5 hours or when pressure drops to 2-3 e-06 Torr
Wednesday, February 21, 2024, 18:56
IGP1=2.9e-06 Torr
starting rampdown at -2A/min |
|
654
|
Wednesday, February 07, 2024, 22:49 |
Darwin Ortiz Rosales | TiC | 44692-11 | LP TUBE | Done | 240206TiC conditioning |
Wednesday, February 07, 2024, 22:36
Ta container tube TaC coated, wrapped in 4 Ta foil heat-shields, and loaded with 320 D shaped discs in a 12mm graphite cartridge with usable 11mm
Endcaps on the graphite cartridge have holes for outgassing
initial heating @ 2A/min to 90 A then 1A/min to 120A TGHT
OMEGA slope = 0.99
Vacuum limits up to 400A: 5.0e-04 Torr -- 1.0e-02 Torr
Thursday, February 08, 2024, 06:18
Starting heat ramp tght
initial pressure = 8.1e-07 Torr IGP1
Thursday, February 08, 2024, 06:54
start of gasoff observed. paused ramp and will continue at 1A/min
Thursday, February 08, 2024, 07:24
lowered TGHT current to 75 A as pressure increasing too rapidly. will leave at this current until pressure drops
Thursday, February 08, 2024, 09:11
continuing ramp to 120A on TGHT
Thursday, February 08, 2024, 09:24
Increasing ramp to 2A/min to 250A on TGHT
Thursday, February 08, 2024, 10:52
Increased ramp to 3A/min to 250A on TGHT
Thursday, February 08, 2024, 11:10
Everything looks good will continue to 300 A at 3A/min TGHT
Thursday, February 08, 2024, 11:33
Pausing heating at 285A, 4.8V TGHT
OMEGA reads 1430C
Will let pressure drop and then proceed ramping slowly @ 0.2A/min
Thursday, February 08, 2024, 13:53
IGP1= 2.4e-06 Torr
OMEGA = 1432 C
ramp at 0.2A/min towards 1550C
Thursday, February 08, 2024, 14:07
pressure very stable. will increase to 0.4 A/min
Thursday, February 08, 2024, 15:24
increasing ramp rate to 1A/min
IGP1 = 2.5e-06 Torr
Thursday, February 08, 2024, 18:05
1900 C on OMEGA
will leave 3-4 hours depending on pressure
Thursday, February 08, 2024, 21:10
No additional pressure peaks observed and pressure on IGP1= 1.9e-06 Torr
TGHT= 460 A, 8.1V
OMEGA= 1860 C
ramp down at -2A/min
|
|
653
|
Monday, January 29, 2024, 16:45 |
Darwin Ortiz Rosales | TaC | | LP-FEBIAD | Done | TaC coating sintering | Monday, January 29, 2024, 16:36
LP FEBIAD
wrapped in 4 Ta heatshields.
Will heat at 2A/min to 95A on TGHT and TBHT
Then will heat at 3A/min to 1800 C ~400A on TGHT and 230A on TBHT
Monday, January 29, 2024, 16:45
Initial IGP1= 5e-05 Torr
Monday, January 29, 2024, 20:35
1800C was at TGHT 410A, 6.9V RD and set current 418A
TBHT= 233 RD A, 3.2V
|
|
652
|
Friday, January 26, 2024, 07:06 |
Darwin Ortiz Rosales | TaC | 45447-1 | HP-FEBIAD | Done | TaC coating sintering | Friday, January 26, 2024, 07:05
The coated container was wrapped in 4 Ta foil heatshield and left in evap2 over night to attain vacuum.
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~700A (adjustable)
Heating autoramp starged at 1A/min on TGHT and TBHT to 120A
Then at 2 A/min to =400 A TGHT and 230A TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Initial IGP1= 5.7e-05 Torr
Friday, January 26, 2024, 09:20
Pressure starts increasing at 125 A on TGHT and TBHT. Leaving it to equilibrate then will start ramping at 3A/min (1.5A/30s) to 700A on TGHT and 230A on TBHT
Friday, January 26, 2024, 13:18
leave sintering at 1838C . Will start rampdown at 5 pm.
IGP1= 6.10e-06 Torr
TGHT=680A, 10.14V
TBHT = 230A, 3.13V
Friday, January 26, 2024, 16:52
IGP1 = 3.0e10-6 Torr
OMEGA=1821 C
start rampdown @-2A/min TGHT and -1A/min TBHT |
|
651
|
Thursday, December 14, 2023, 09:58 |
Darwin Ortiz Rosales | SiC | 41369-2 | HP-SIS | Done | 231208SiC conditioning | Thursday, December 14, 2023, 09:53
Target left pumping down in Evap2 overnight.
Initial weight including protective jig = 1474.3 g
Total number of target foils:388
10 analysis discs: 5x 220727-2 labelled as A and 5x 231123-2 labelled as B on the right side (front) of container. Order of discs ABABABABAB.
Total length packed 15.5 cm
container has 3 Ta heat shields including the inner made of three pieces as to cover the center block.
No endcaps inserted to facilitate out-gassing
Ta coated spring at both ends
ramp to 500A @ 1A/min TGHT and to 230A on TBHT
max approx 700A on TGHT and 230A on TBHT (Omega slope set = 0.990)
Then temperature = 1800C
TBHT will be set fixed at 230 A (max). TBHT heated manually and automatically to max.
Good vac at 5.00 e -4 Torr
Bad vac at 5.00 e-2 Torr
IGP1= 9.3e-07 Torr at start of initial ramp.
Thursday, December 14, 2023, 09:56
Started initial ramp up 1A/min on both heaters
Thursday, December 14, 2023, 11:03
Pressure dropping. Will increase ramp speed to 2A/min on both heaters (1A/30s)
Thursday, December 14, 2023, 11:17
pressure dropping. Increase ramp to 4A/min (2A/30s)
Will stop and ramping for temperature measurements
Thursday, December 14, 2023, 13:28
Increased ramp to 5A/min (2.5A/30s)
Will heat to 703A on TGHT and leave for 4 hours |
|
650
|
Wednesday, December 06, 2023, 09:57 |
Darwin Ortiz Rosales | SiC | 45447-4 | HP-FEBIAD | Done | 231204SiC conditioning | Wednesday, December 06, 2023, 09:47
Target number of foils:370
Analysis discs 16 A and 16B interspersed on the end further from the laser
A are discs produced using new method and B are discs produced using milling.
Total length packed 16 cm (excluding the analysis discs)
container has 3 Ta heat shields (one inner around fins and center block, new type of 1st shield made up of three pieces)
No endcaps inserted to facilitate out-gassing
Ta coated spring at front end
ramp to 120A @ 1A/min TGHT and to 120A on TBHT hold there until pressure drop, then ramp to 500A on TGHT and 230A TBHT.
max approx 700A on TGHT and 230A on TBHT (Omega slope set = 0.990)
Then temperature = 1800C
TBHT will be set fixed at 230 A (max). TBHT heated manually and automatically to max.
Good vac at 5.00 e -4 Torr
Bad vac at 5.00 e-2 Torr
IGP1= 1e-06 Torr at start of initial ramp.
Wednesday, December 06, 2023, 09:56
System left to drop pressure over previous night and now at 120A. waiting for pressure drop.
Wednesday, December 06, 2023, 11:18
increased ramp rate to 2A/min
Wednesday, December 06, 2023, 14:41
increased ramp to 3A/min on TGHT and stopping to allow pressure to stabilize before taking temperature readings
Top temperature 1800C at 710 A but started dropping. Increased current to 750A and left there for 4 hours.
Cool down at -2A/min TGHT and -1A/min TBHT
|
|
649
|
Monday, November 06, 2023, 14:07 |
Darwin Ortiz Rosales | Empty | 45220-4 | LP-SIS | Done | TaC coating sintering | Monday, November 06, 2023, 09:59
The coated container was wrapped in 4 Ta foil heatshields.
Vacuum IGP1 initial =3.1 e-07 Torr
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~400A (adjustable)
Heating autoramp starged at 2A/min(1A/30s) on TGHT 100A
Then at 2A/min to =400 A TGHT and 230A TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Monday, November 06, 2023, 14:07
OMEGA =1852 C
IGP1= 3.14e-06 Torr
TGHT= 399A, 6.6V
TBHT= 233A, 4.1V
Tuesday, November 07, 2023, 12:28
Cooled down previous evening and took out today.
rampdown was @-2A/min for TGHT and -1A/min TBHT |
|
648
|
Friday, October 20, 2023, 07:24 |
Darwin Ortiz Rosales | TaC | 45447-11 | LP-SIS | Done | TaC coating sintering | Friday, October 20, 2023, 07:20
The coated container was wrapped in 4 Ta foil heatshields.
Vacuum IGP1 initial = 9.9 e-07 Torr
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~400A (adjustable)
Heating autoramp starged at 2A/min(1A/30s) on TGHT 100A
Then at 4A/min to =400 A TGHT and 230A TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Friday, October 20, 2023, 07:24
Starting initial ramp
Vacuum IGP1 initial = 9.9 e-07 Torr
Friday, October 20, 2023, 08:55
After initial pressure bump continued heating at 1A/min to 120A to observe any other possible pressure bump.
Friday, October 20, 2023, 09:05
increased ramp to 4A/min to 400 TGHT and 230 TBHT
Friday, October 20, 2023, 09:35
OMEGA=1280 C
TGHT= 221.5 A, 3.24V
TBHT=228.9, 3.9V
Friday, October 20, 2023, 10:22
OMEGA 1852 C at TGHT = 390A, 6.5 V ; TBHT = 232 A, 4.0 V
Will leave for 4 hours
Friday, October 20, 2023, 14:16
About to start rampdown
TGHT @ -2A/min
TBHT@ -1A/min
Final OMEGA = 1840 C
IGP1 = 1.83e-06 Torr |
|
647
|
Thursday, October 05, 2023, 12:47 |
Aaron Schmidt | Ta | 45220-3 | LP-SIS | In progress | Conditioning Ta#68 (Spare) | Ta#(Spare) LP-SIS target description:
Total Ta foils = 470 [6x20 packs + 350 single discs]
Foil Thickness = 0.033mm (0.0013") avg Measured.
Target material batch: Ta 2023-1 Mt'l PO# TR-2022-03028
Target density = 12.515 g/cm3
Target length = 4.97 cm
Total Mass = 62.202 g [Incl foils + Ta wire on 6 packs]
Total mass w/ Target oven = 461g (w/ end caps)
Discs in target are arranged as follows: 1pack / 75 singles / 1pack / 100 singles / 2packs / 100 singles / 1pack / 75 singles / 1pack
Dimpling direction on foils/ Packs. --> Center <--
End caps installed (Not expanded). No Ta foil heat shield added
Was labelled Ta#67 until the Thin foil target 45447-14 became so.
Thursday, October 05, 2023, 12:44: Roughing.
Thursday, October 05, 2023, 13:10; TP1 on.
Thursday, October 05, 2023, 13:11: TGHT / TBHT test. Tap up to 5 / 5 A & back to 0 A. Ok.
Thursday, October 05, 2023, 13:13: Slope Set @ 0.98
Friday, October 06, 2023, 05:54: Auto-ramping TGHT / TBHT to 580 / 230 A @ 2 A per min.
Friday, October 06, 2023, 11:50: TGHT / TBHT @ 580 / 230 A (568 / 233 A). Auto-ramping TGHT to 630 A @ 2 A per min (640 A w/ offset). Temperature @ 1716 C. Vacuum @ 2.76e-06T.
Friday, October 06, 2023, 12:20: TGHT / TBHT @ 630 / 230 A (618 / 233 A). Auto-ramping TGHT to 650 A @ 2 A per min (640 A w/ offset). Temperature @ 1809 C. Vacuum @ 3.77e-06T.
Friday, October 06, 2023, 12:37: TGHT / TBHT @ 650 / 230 A (638 / 233 A). Auto-ramping TGHT to 665 A @ 2 A per min (650 A w/ offset). Temperature @ 1844 C.
Friday, October 06, 2023, 12:53: Tapped up to TGHT / TBHT @ 670/ 230 A (657 / 233 A). Temperature @ 1880 C. Vacuum @ 4.94e-06T.
Friday, October 06, 2023, 12:57: Tapped TGHT to 675. TGHT / TBHT @ 675 / 230 A (662 / 233 A). Temperature @ 1889 C. Vacuum @ 5.03e-06T.
Friday, October 06, 2023, 13:00: Tapped TGHT to 682. TGHT / TBHT @ 682 / 230 A (669 / 233 A). Temperature @ 1901 C. Vacuum @ 5.46e-06T. Desired Temperature reached.
Friday, October 06, 2023, 13:01: Auto-cooling @ 2 A per min.
Tuesday, October 10, 2023, 08:37: PS & TP off. |
|
646
|
Wednesday, September 20, 2023, 14:26 |
Aaron Schmidt | Ta | 45220-5 | LP-SIS | In progress | Conditioning Ta#66 | Ta#66 LP-SIS target description:
Total Ta foils = 470 [6x20 packs + 350 single discs]
Foil Thickness = 0.033mm (0.0013") avg Measured.
Target material batch: Ta 2023-1 Mt'l PO# TR-2022-03028
Target density = 12.446 g/cm3
Target length = 5.0 cm
Total Mass = 62.230 g [Incl foils + Ta wire on 6 packs]
Total mass w/ Target oven= g (w/ end caps)
Discs in target are arranged as follows: 1pack / 75 singles / 1pack / 100 singles / 2packs / 100 singles / 1pack / 75 singles / 1pack
Dimpling direction on foils/ Packs. --> Center <--
End caps installed (Not expanded). No Ta foil heat shield added
Desired temperature 1900C
Wednesday, September 20, 2023, 14:18: Roughing.
Wednesday, September 20, 2023, 14:35: TP Started.
Wednesday, September 20, 2023, 14:43: TP on.
Wednesday, September 20, 2023, 14:45: TGHT / TBHT raised to 5 / 5 A & lowered. Quick check ok.
Thursday, September 21, 2023, 07:47: Auto-ramping TGHT / TBHT to 580 / 230 A @ 2 A per min. Vacuum @ 8.30e-07T.
Thursday, September 21, 2023, 09:54: Slope set to 0.98
Thursday, September 21, 2023, 13:42: TGHT / TBHT @ 580 / 230 A (568 / 233 A). Auto-ramping TGHT to 630 A @ 2 A per min (640 A w/ offset). Temperature @ 1748 C. Vacuum @ 2.47e-06T.
Thursday, September 21, 2023, 14:10: TGHT / TBHT @ 630 / 230 A (618 / 233 A). Auto-ramping TGHT to 650 A @ 2 A per min (640 A w/ offset). Temperature @ 1843 C. Vacuum @ 3.30e-06T.
Thursday, September 21, 2023, 14:23: TGHT / TBHT @ 650 / 230 A (638 / 233 A). Auto-ramping TGHT to 660 A @ 2 A per min (648 A w/ offset). Temperature @ 1879 C. Vacuum @ 3.77e-06T.
Thursday, September 21, 2023, 14:29: Tapped TGHT to 662. TGHT / TBHT @ 662 / 230 A (649 / 233 A). Temperature @ 1903 C. Vacuum @ 4.08e-06T. Desired Temperature reached.
Thursday, September 21, 2023, 14:33: Auto-cooling started @ 1 A per min.
Monday, September 25, 2023, 08:09: Turbo pump off. |
|
645
|
Tuesday, September 12, 2023, 09:54 |
Darwin Ortiz Rosales | TaC | 41369-2 | HP-SIS | Done | TaC coating sintering | Tuesday, September 12, 2023, 09:51
The coated container was wrapped in 3 Ta foil heatshield and left in evap2 over night to attain vacuum.
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~700A (adjustable)
Heating autoramp starged at 1A/min on TGHT and TBHT to 120A
Then at 2 A/min to =400 A TGHT and 230A TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Initial IGP1= 2.7e-06 Torr
Tuesday, September 12, 2023, 7:00
Started autoramp @1A/min to 120A on both TGHT and TBHT
Tuesday, September 12, 2023, 09:53
Heating ramp set to 230A for both TGHT and TBHT. Rate at 2A/min for both heaters.
Tuesday, September 12, 2023, 11:21
Continued ramp on TGHT at 2A/min to 335A and now setting to 3A/min (1.5A/30s)
Tuesday, September 12, 2023, 11:47
|
TGHT |
|
Temperature ( C ) |
Voltage (V) |
Current (A) |
1205 |
5.5 |
392.0 |
Continue ramping @3A/min on TGHT
Tuesday, September 12, 2023, 13:33
Reached 1840 C at TGHT =677A and 10.5V
Will keep for 4 hours |
|
644
|
Thursday, August 31, 2023, 07:09 |
Darwin Ortiz Rosales | TaC | 45447-4 | HP-FEBIAD | Done | TaC coating sintering | Thursday, August 31, 2023, 07:07
The coated container was wrapped in 3 Ta foil heatshields.
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~500A (adjustable)
Heating autoramp starged at 1A/min on TGHT and TBHT to 120A
Then at 2 A/min to =400 A TGHT and 230A TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Initial IGP1= 7.7e-07 Torr
Thursday, August 31, 2023, 12:29
OMEGA=1238 C
IGP1=1.4e-06 Torr
Continue ramp
ramp @ 4A/min (2A/30s)
Thursday, August 31, 2023, 12:50
IGP1= 2.23e-06 Torr
OMEGA=1392 C
Thursday, August 31, 2023, 13:04
IGP1=2.7e-06 Torr
OMEGA=1443 C
Thursday, August 31, 2023, 13:18
IGP1= 3.8e-06 Torr
OMEGA=1537 C
Thursday, August 31, 2023, 14:38
OMEGA=1852C |
|
643
|
Tuesday, August 29, 2023, 12:47 |
Darwin Ortiz Rosales | TaC | 45220-10 | LP-SIS | Done | TaC coating sintering | Tuesday, August 29, 2023, 12:46
The coated container was wrapped in 4 Ta foil heatshields.
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~400A (adjustable)
Heating autoramp starged at 2A/min(1A/30s) on TGHT 100A
Then at 4A/min to =400 A TGHT and 230A TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Tuesday, August 29, 2023, 12:49
Initial heating start
IGP1= 6.0 e-06 Torr
Tuesday, August 29, 2023, 14:31
Paused ramping to take reading
IGP1= 5.98e-06 Torr
OMEGA = 1500 C
Tuesday, August 29, 2023, 15:24
OMEGA 1866 C
IGP1= 6.6e-6 Torr
|
|
642
|
Saturday, August 26, 2023, 09:41 |
Darwin Ortiz Rosales | TaC | 45220-10 | LP-SIS | Done | TaC coating sintering |
Saturday, August 26, 2023, 09:39
The coated container was wrapped in 4 Ta foil heatshields.
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~400A (adjustable)
Heating autoramp starged at 2A/min(1A/30s) on TGHT 100A
Then at 4A/min to =400 A TGHT and 230A TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Initial IGP1= 8.7e-07 Torr
Saturday, August 26, 2023, 10:54
IGP1= 1.2e-06 Torr
Start ramp up at 4A/min on both heaters (2A/30s) until TGHT = 400A and TBHT=230A
Saturday, August 26, 2023, 11:32
Paused ramp to allow temperature to stabilize and record data
OMEGA= 1396 C
IGP1= 2.47e-06 Torr
Saturday, August 26, 2023, 11:52
Paused ramp to record data
OMEGA = 1544 C
IGP1=3.4e-06 Torr
Saturday, August 26, 2023, 12:09
Paused ramp to record data
OMEGA = 1653
IGP1 = 4.5e-06 Torr
Saturday, August 26, 2023, 12:33
Omega went up to 1878C. Lowered the current on TGHT to reach OMEGA = 1857 C
Will keep until 430 pm
IGP1- 3.4e-06 Torr
Saturday, August 26, 2023, 16:10
ramping down at -2A/min tght 1A/min tbht
1837 C OMEGA
|
|
641
|
Thursday, August 24, 2023, 14:18 |
Aaron Schmidt | Nb | 45447-9 | LP-IG-LIS | In progress | Conditioning Nb#11 | Nb#11 LP-IG-LIS target description:
Total Ta foils = 470 [6x20 packs + 350 single discs]
Foil Thickness = 0.025mm (0.001")
Target density = 7.13 g/cm3
Target length = 3.53 cm
Total Mass = 25.165 g [Incl foils + Ta wire on 6 packs]
Total mass w/ Target oven= 434 g (w/ end caps)
Discs in target are arranged as follows: 1pack / 75 singles / 1pack / 100 singles / 2packs / 100 singles / 1pack / 75 singles / 1pack
Dimpling direction on foils/ Packs. --> Center <--
End caps installed (Not expanded). No Ta foil heat shield added
Final desired temperature = 1900C.
Replacement for Nb#10
Thursday, August 24, 2023, 14:16: Roughing.
OMEGA slope = 0.98.
Thursday, August 24, 2023, 14:31: Turbo pump started.
Thursday, August 24, 2023, 14:41: TGHT / TBHT PS on. Manually test @ 5 / 5 A. ok. Tap back to 0 A.
Thursday, August 24, 2023, 18:26: Vacuum @ 4.35e-06T. Auto-ramping TGHT / TBHT to 580 / 230 A @ 2 A per minute.
Thursday, August 24, 2023, 22:00: TGHT / TBHT @ 414 / 230 A (406 / 233 A - Offset). Auto-ramping TGHT to 580 A @ 2 A per min continued. Temperature @ 1353 C. Vacuum @ 4.03e-06T.
Thursday, August 24, 2023, 23:29: TGHT / TBHT @ 580 / 230 A (569 / 233 A). Auto-ramping TGHT to 610 A @ 2 A per min (approx 600 A w/ offset). Temperature @ 1708 C. Vacuum @ 6.61e-06T.
Thursday, August 24, 2023, 23:49: TGHT / TBHT @ 610 / 230 A (598 / 233 A). Auto-ramping TGHT to 630 A @ 2 A per min (620 A w/ offset). Temperature @ 1765 C. Vacuum @ 7.22e-06T.
Friday, August 25, 2023, 00:04: TGHT / TBHT @ 630 / 230 A (618 / 233 A). Auto-ramping TGHT to 650 A @ 2 A per min (640 A w/ offset). Temperature @ 1808 C. Vacuum @ 7.54e-06T.
Friday, August 25, 2023, 00:16: TGHT / TBHT @ 650 / 230 A (638 / 233 A). Auto-ramping TGHT to 670 A @ 2 A per min (660 A w/ offset). Temperature @ 1845 C. Vacuum @ 7.72e-06T.
Friday, August 25, 2023, 00:27: TGHT / TBHT @ 670 / 230 A (657 / 233 A). Auto-ramping TGHT to 680 A @ 2 A per min (668 A w/ offset). Temperature @ 1880 C. Vacuum @ 8.46e-06T.
Manually tap up to temperature.
Friday, August 25, 2023, 00:34: TGHT / TBHT @ 682 / 230 A (669 / 233 A). Temperature @ 1900-1901 C. Vacuum @ 8.59e-06T. Desired Temperature Reached.
Friday, August 25, 2023, 00:37: Auto-cooling @ 2 A per min.
Friday, August 25, 2023, 06:15:
Friday, August 25, 2023, 07:40: PS & TP off.
|
|
640
|
Tuesday, August 22, 2023, 09:35 |
Darwin Ortiz Rosales | TaC | 44692-11 | TARGET BOAT | Done | TaC coating sintering (second coating on same tube) | Tuesday, August 22, 2023, 09:29
The coated container was wrapped in 4 Ta foil heatshields.
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 2 hours
Final Current TBHT= N/A
Final TGHT current= ~400A (adjustable)
Heating autoramp starged at 2A/min(1A/30s) on TGHT 100A
Then at 4A/min to =400 A.
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
IGP1 initial =2.2e-06 Torr
Tuesday, August 22, 2023, 10:25
IGP1= 2.31e-06 Torr
TGHT 98.0 A (RD), 1.35 V
Start ramping at 2A/min to 400A
Tuesday, August 22, 2023, 11:54
Reached 1860 @ TGHT = 353A, 6.16V (RD) Will leave for 2 hours
Tuesday, August 22, 2023, 14:07
1853C OMEGA
TGHT = 353 A, 6.2 V (RD)
IGP1= 2.88E-06 Torr
Starting ramp-down at -2A/min
Saturday, August 26, 2023, 09:37
Note: the coating looks really good . The second sintering on the second coating was 2 hours. Will test the coating during graphite material conditioning. |
|