Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Evaporator_2, Page 28 of 35  Not logged in ELOG logo
    Reply  Thursday, August 08, 2024, 11:17, Marla Cervantes, C, 44139-5 SK, LP TUBE, Done, Graphite foils conditioning GraphiteFoil-Conditioning-EVAP2.JPG


    
        
            Aaron Schmidt wrote:
        
        
            
            Wednesday, August 07, 2024, 15:36: Roughing. Had initially been roughed & TP started w/ Marla CS,
Entry  Tuesday, May 21, 2019, 18:01, Marla Cervantes, , 43943-1, , Done, Graphite foil test 
 Tuesday, May 21, 2019, 17:57
A tantalum tube previously coated with TaC and sintered was loaded with graphite foils.
The mass of the foils was 20.04 g.
Entry  Tuesday, November 24, 2020, 12:56, Marla Cervantes, , 44139-8-SK , TARGET BOAT, Done, Graphite casting conditioning 2020-11-24-IGP1.JPG2020-11-24IGP1-zoom_out.png2020-11-24-IGP1-stable.JPG2020-11-24-ConditioningProcess.JPG
Tuesday, November 24, 2020, 09:23
A batch of 60 discs of 18 mm diameter were loaded in a tantalum tube. The tantalum tube was wrapped with 3 layers of Ta foil for heat shielding
and mounted in the EVAP2. EVAP2 pumped down overnight and Aaron made a leak test this morning (elog 524). 
Entry  Friday, December 02, 2022, 09:50, Darwin Ortiz Rosales, , 45220-12, TARGET BOAT, Done, Grahite disc conditioning 221130-Graphite 
Friday, December 02, 2022, 09:46
297 graphite discs packed into a Ta tube wrapped in four heatshields.
Good vacuum 5.0e-04 Torr
Entry  Wednesday, September 14, 2022, 11:48, Darwin Ortiz Rosales, , , TARGET BOAT, Done, Grahite disc conditioning 220907G 
Wednesday, September 14, 2022, 9:30
A Ta container tube was wrapped with 3 Ta heatshields.
322 graphite discs were loaded.
Entry  Tuesday, July 10, 2018, 16:43, John Wong, Empty, , LP-SIS, Done, For nano-SiC#1  
Tuesday, July 10, 2018, 16:40
Container was flashed with TaC solution and let dry in air. 
No Ta heat shield is used. 
Entry  Monday, November 25, 2019, 11:35, Aaron Schmidt, , , , In progress, Flex - line HS installed 
 Leak noted on previous TaC sintering on HP FEBIAD # 42464-3.
Swapped out gaskets on HS flex line a re-tightened.
Monday, November 25, 2019, 11:31: Roughing.
Entry  Tuesday, November 24, 2020, 08:13, Aaron Schmidt, , , , , Flex - line HS installed 
Monday, November 23, 2020, 17:01: Flex-line HS installed.

Tuesday, November 24, 2020, 08:03: Vacuum @ 9.55e-07T.
Tuesday, November 24, 2020, 08:08: Vacuum Ok
Entry  Monday, March 01, 2021, 13:58, Aaron Schmidt, , , , , Flex - line HS installed 
Flex-Line HS had been fully scrubbed out earlier. All gaskets replaced.
Empty. Quick check for leaks.
Monday, March 01, 2021, 13:57: Roughing.
Entry  Thursday, September 10, 2020, 07:53, Aaron Schmidt, Empty, 41790-8, LP-FEBIAD, Done, Fernando FEBIAD / Anode testing. 
 FEBIAD installed. Anode PS installed. ANODE connected!.
Leak check
Thursday, September 10, 2020, 07:46: Vacuum @ 6.30e-07T
Entry  Monday, February 13, 2012, 16:24, John Wong, , , , Done, Evaporator #2 Commissioned  Evap2_Commissioning_Report.PDF
 Monday, February 13, 2012, 16:21
The Evaporator 2 is now commissioned.  See attachment#1 for the commissioning report or refer to Document #43321.  
Entry  Tuesday, March 20, 2012, 14:35, John Wong, , , , Done, Evap#2 Backing up muffler not connected to the exhaust system. Evap2_backingpump.jpgscroll_pump_exhaust.jpg
 Tuesday, March 20, 2012, 14:22
The Evaporator #2 backing pump (IEVAP2:BP1) muffler has not connected to the exhaust duct.
 See attachment#1 as to where the muffler should be connected to the exhaust ducting system.  
Entry  Tuesday, September 11, 2018, 10:47, Aaron Schmidt, , , , , Evap 2 step discrepancy  PS_Check.docx
 Tuesday, September 11, 2018, 10:45:
TGHT: 53.4 A   TBHT: 57.75
Actual
    Reply  Monday, June 11, 2012, 12:26, John Wong, SiC, 38481-2, HP-SIS, Problems, End caps vaporized Photo_2012-06-11_12_06_19_PM.jpg


    
        
            John Wong wrote:
        
        
            
            
            
Entry  Wednesday, August 14, 2024, 07:23, Marla Cervantes, C, 44139-5 SK, LP TUBE, Problems, EVAP2 Calibration - Vanadium  TP-not_speeding_up.JPG
Tuesday, August 13, 2024, 17:20 Pressure kept increasing when turning the turbo pump on 
Tuesday, August 13, 2024, 18:00 Pressure stayed constant when turning the turbo pump on
    Reply  Wednesday, August 14, 2024, 16:22, Marla Cervantes, C, 44139-5 SK, LP TUBE, Problems resolved, EVAP2 Calibration - Vanadium  


    
        
            Marla Cervantes wrote:
        
        
            
            Tuesday, August 13, 2024, 17:20 Pressure kept increasing when turning the turbo pump on
    Reply  Wednesday, August 14, 2024, 16:24, Marla Cervantes, C, 44139-5 SK, LP TUBE, In progress, EVAP2 Calibration - Vanadium  
 
 


    
        

           Marla Cervantes wrote:
        
        

           
            
            
Entry  Thursday, April 07, 2016, 15:23, John Wong, SiC, , TARGET BOAT, Done, E-spun SiC/PAN thermal treatment  SiC_PAN_1400c.PNGarchiver.PNG
Thursday, April 07, 2016, 15:18
E-spun SiC/PAN fiber mats were produced at UBC.
12%PAN solution; 50% SiC to weight of PAN.
Entry  Thursday, August 05, 2021, 11:18, Darwin Ortiz Rosales, SiC, 44691-2, LP-SIS, Done, Dr blade and non-Dr blade Material Experiment (sintering) image_2021-08-09_221014.png
Thursday, August 05, 2021, 11:10
Total number of foils: 380
Total length packed 13.5 cm
Entry  Tuesday, October 29, 2013, 15:50, Anders Mjos, , , , In progress, Copper bars on TGHT and TBHT Current_and_Voltage.pdf
 Tuesday, October 29, 2013, 15:50: Pumping down
Wednesday, October 30, 2013, 09:32: Turbo started
Wednesday, October 30, 2013, 14:50: The Cu-bars were heated to 600A and 300A for TGHT and TBHT respectively.
ELOG V2.9.2-2455