ID Date Author Target Material Target Oven W.O# Source Status Subjectdown Text Attachments
  454   Wednesday, August 28, 2019, 05:59 Marla Cervantes 44062-2-SK DoneGraphite insert testWednesday, August 28, 2019, 06:00
A graphite insert (with conical
  
  669   Thursday, August 08, 2024, 11:17 Marla CervantesC44139-5 SKLP TUBEDoneGraphite foils conditioning

    

       
            
 GraphiteFoil-Conditioning-EVAP2.JPG 
  445   Tuesday, May 21, 2019, 18:01 Marla Cervantes 43943-1 DoneGraphite foil test Tuesday, May 21, 2019, 17:57
A tantalum tube previously coated
with TaC and sintered was loaded with graphite
  
  525   Tuesday, November 24, 2020, 12:56 Marla Cervantes 44139-8-SK TARGET BOATDoneGraphite casting conditioningTuesday, November 24, 2020, 09:23
A batch of 60 discs of 18 mm diameter
were loaded in a tantalum tube. The tantalum
 2020-11-24-IGP1.JPG2020-11-24IGP1-zoom_out.png2020-11-24-IGP1-stable.JPG2020-11-24-ConditioningProcess.JPG 
  606   Friday, December 02, 2022, 09:50 Darwin Ortiz Rosales 45220-12TARGET BOATDoneGrahite disc conditioning 221130-GraphiteFriday, December 02, 2022, 09:46
297 graphite discs packed into a
Ta tube wrapped in four heatshields.
  
  591   Wednesday, September 14, 2022, 11:48 Darwin Ortiz Rosales  TARGET BOATDoneGrahite disc conditioning 220907GWednesday, September 14, 2022, 9:30
A Ta container tube was wrapped with
3 Ta heatshields.
  
  414   Tuesday, July 10, 2018, 16:43 John WongEmpty LP-SISDoneFor nano-SiC#1 Tuesday, July 10, 2018, 16:40
Container was flashed with TaC solution
and let dry in air. 
  
  470   Monday, November 25, 2019, 11:35 Aaron Schmidt   In progressFlex - line HS installed Leak noted on previous TaC sintering
on HP FEBIAD # 42464-3.
Swapped out gaskets on HS flex line
  
  524   Tuesday, November 24, 2020, 08:13 Aaron Schmidt    Flex - line HS installedMonday, November 23, 2020, 17:01: Flex-line
HS installed.

Tuesday, November 24, 2020,
  
  532   Monday, March 01, 2021, 13:58 Aaron Schmidt    Flex - line HS installedFlex-Line HS had been fully scrubbed out
earlier. All gaskets replaced.
Empty. Quick check for leaks.
  
  506   Thursday, September 10, 2020, 07:53 Aaron SchmidtEmpty41790-8LP-FEBIADDoneFernando FEBIAD / Anode testing. FEBIAD installed. Anode PS installed.
ANODE connected!.
Leak check
  
  3   Monday, February 13, 2012, 16:24 John Wong   DoneEvaporator #2 Commissioned  Monday, February 13, 2012, 16:21
The Evaporator 2 is now commissioned.
 See attachment#1 for the commissioning
 Evap2_Commissioning_Report.PDF 
  7   Tuesday, March 20, 2012, 14:35 John Wong   DoneEvap#2 Backing up muffler not connected to the exhaust system. Tuesday, March 20, 2012, 14:22
The Evaporator #2 backing pump (IEVAP2:BP1)
muffler has not connected to the exhaust
 Evap2_backingpump.jpgscroll_pump_exhaust.jpg 
  419   Tuesday, September 11, 2018, 10:47 Aaron Schmidt    Evap 2 step discrepancy  Tuesday, September 11, 2018, 10:45:
TGHT: 53.4 A   TBHT: 57.75
Actual
 PS_Check.docx 
  30   Monday, June 11, 2012, 12:26 John WongSiC38481-2HP-SISProblemsEnd caps vaporized

    

       
            
 Photo_2012-06-11_12_06_19_PM.jpg 
  670   Wednesday, August 14, 2024, 07:23 Marla CervantesC44139-5 SKLP TUBEProblemsEVAP2 Calibration - Vanadium Tuesday, August 13, 2024, 17:20 Pressure
kept increasing when turning the turbo pump
on 
 TP-not_speeding_up.JPG 
  671   Wednesday, August 14, 2024, 16:22 Marla CervantesC44139-5 SKLP TUBEProblems resolvedEVAP2 Calibration - Vanadium

    

       
            
  
  672   Wednesday, August 14, 2024, 16:24 Marla CervantesC44139-5 SKLP TUBEIn progressEVAP2 Calibration - Vanadium  
 


    
  
  289   Thursday, April 07, 2016, 15:23 John WongSiC TARGET BOATDoneE-spun SiC/PAN thermal treatment Thursday, April 07, 2016, 15:18
E-spun SiC/PAN fiber mats were produced
at UBC.
 SiC_PAN_1400c.PNGarchiver.PNG 
  553   Thursday, August 05, 2021, 11:18 Darwin Ortiz RosalesSiC44691-2LP-SISDoneDr blade and non-Dr blade Material Experiment (sintering)Thursday, August 05, 2021, 11:10
Total number of foils: 380
Total length packed 13.5 cm
 image_2021-08-09_221014.png 