Wednesday, August 28, 2019, 05:59, Marla Cervantes, , 44062-2-SK, , Done, Graphite insert test
| +
Thursday, August 08, 2024, 11:17, Marla Cervantes, C, 44139-5 SK, LP TUBE, Done, Graphite foils conditioning
|
Tuesday, May 21, 2019, 18:01, Marla Cervantes, , 43943-1, , Done, Graphite foil test
|
Tuesday, November 24, 2020, 12:56, Marla Cervantes, , 44139-8-SK , TARGET BOAT, Done, Graphite casting conditioning   
|
Friday, December 02, 2022, 09:50, Darwin Ortiz Rosales, , 45220-12, TARGET BOAT, Done, Grahite disc conditioning 221130-Graphite
|
Wednesday, September 14, 2022, 11:48, Darwin Ortiz Rosales, , , TARGET BOAT, Done, Grahite disc conditioning 220907G
|
Tuesday, July 10, 2018, 16:43, John Wong, Empty, , LP-SIS, Done, For nano-SiC#1
|
Monday, November 25, 2019, 11:35, Aaron Schmidt, , , , In progress, Flex - line HS installed
|
Tuesday, November 24, 2020, 08:13, Aaron Schmidt, , , , , Flex - line HS installed
|
Monday, March 01, 2021, 13:58, Aaron Schmidt, , , , , Flex - line HS installed
|
Thursday, September 10, 2020, 07:53, Aaron Schmidt, Empty, 41790-8, LP-FEBIAD, Done, Fernando FEBIAD / Anode testing.
|
Monday, February 13, 2012, 16:24, John Wong, , , , Done, Evaporator #2 Commissioned
|
Tuesday, March 20, 2012, 14:35, John Wong, , , , Done, Evap#2 Backing up muffler not connected to the exhaust system. 
|
Tuesday, September 11, 2018, 10:47, Aaron Schmidt, , , , , Evap 2 step discrepancy
| +
Monday, June 11, 2012, 12:26, John Wong, SiC, 38481-2, HP-SIS, Problems, End caps vaporized
| +
Wednesday, August 14, 2024, 07:23, Marla Cervantes, C, 44139-5 SK, LP TUBE, Problems, EVAP2 Calibration - Vanadium
| +
Wednesday, August 14, 2024, 16:22, Marla Cervantes, C, 44139-5 SK, LP TUBE, Problems resolved, EVAP2 Calibration - Vanadium
| +
Wednesday, August 14, 2024, 16:24, Marla Cervantes, C, 44139-5 SK, LP TUBE, In progress, EVAP2 Calibration - Vanadium
|
Thursday, April 07, 2016, 15:23, John Wong, SiC, , TARGET BOAT, Done, E-spun SiC/PAN thermal treatment 
|
Thursday, August 05, 2021, 11:18, Darwin Ortiz Rosales, SiC, 44691-2, LP-SIS, Done, Dr blade and non-Dr blade Material Experiment (sintering)
|
|