  Evaporator_2, Page 27 of 34  Not logged in ELOG logo
  ID Date Author Target Material Target Oven W.O#down Source Status Subject Text Attachments
  133   Monday, June 09, 2014, 13:56 Cameron Hodgins  TARGET BOATIn progressSintering several carbides on tantalum foil backingManually changed current from 500 to 615
A, monitoring the temperature. Temperature
went from 1657 C up to 1838 C. Pressure increased
  
  134   Monday, June 09, 2014, 17:15 Cameron Hodgins  TARGET BOATIn progressSintering several carbides on tantalum foil backing Target boat is now being cooled at
1 A/min from the starting point (616 A) down
to 0 A. 
  
  150   Tuesday, August 05, 2014, 13:13 Laura LambertEmpty TARGET BOATIn progressSintering TaC coated end caps Tuesday, August 05, 2014, 12:02
The target container end caps were
coated with TaC spray and let dry.
 aug5-2014.jpg 
  151   Tuesday, August 05, 2014, 17:20 John Wong  TARGET BOATIn progressSintering TaC coated end caps

    

       
            
  
  153   Thursday, August 07, 2014, 10:13 Laura Lambert  TARGET BOATFailedSintering TaC coated end caps

    

       
            
  
  159   Thursday, October 02, 2014, 11:26 John WongEmpty  MaintenanceBroken insulators  Thursday, October 02, 2014, 11:22
It was found that after the last
process, Evap#2 has broken insulators - the
  
  161   Friday, October 03, 2014, 13:02 Anders MjosEmpty  MaintenanceBroken insulators

    

       
            
 NewInsulators.jpgBrokenInsulators.jpg 
  164   Thursday, October 09, 2014, 15:59 John WongNb TARGET BOATIn progressConditioning Nb target (for Bob) Thursday, October 09, 2014, 15:56
The target boat contains 5 samples
of Nb discs.  Each disc is wrapped with
  
  166   Thursday, October 09, 2014, 17:41 John WongNb TARGET BOATDoneConditioning Nb targets (for Bob) Thursday, October 09, 2014, 17:36
Target boat consists of 5 Nb discs. 
Each disc is wrapped with Nb foil, and to
 samples@1400C.png 
  168   Tuesday, November 04, 2014, 16:20 John WongSiC TARGET BOATIn progressTEST: Fabrication of SiC & Determine phase transformation 3C vs 6HTuesday, November 04, 2014, 16:08
The purpose of this experiment is
to improve the fabrication of SiC. 
  
  170   Monday, November 10, 2014, 13:55 Laura LambertEmpty LP-SISDoneSintering TaC coating container for UCx#11 [2nd container]Monday, November 10, 2014, 13:51
target container was sprayed with
TaC on friday and sintered over the weekend.
  
  172   Wednesday, November 26, 2014, 14:09 Laura Lambert   MaintenanceOMEGA-IR dark patch and backing pump trip Wednesday, November
26, 2014, 13:47
 IR_focus.jpeg 
  173   Thursday, December 11, 2014, 10:20 Laura Lambert   Maintenancewater supply shut off for lab closure over holidays Thursday, December 11, 2014, 10:17
water supply and return valves closed
for lab closure over the holidays.
  
  174   Wednesday, January 14, 2015, 13:46 Anders MjosEmpty  MaintenancePumping down for water leak test Wednesday, January 14, 2015, 13:46:
Roughing
Wednesday, January 14, 2015, 14:57:
  
  175   Thursday, January 22, 2015, 14:21 Anders MjosEmpty  Problems resolvedCG1A replaced See previous e-log entry
for details
  
  194   Friday, May 22, 2015, 11:44 Laura LambertEmpty TARGET BOATIn progressSintering TaC coating on Ta target boat Friday, May 22, 2015, 11:43
A target boat was sprayed with
  
  207   Thursday, June 04, 2015, 11:10 Laura LambertEmpty LP-IG-LISIn progressSintering TaC coating container for UCx Thursday, June 04, 2015, 9:07
Container was sprayed with TaC and
let dry.
  
  208   Friday, June 05, 2015, 12:19 John WongEmpty LP-IG-LISIn progressSintering TaC coating container for UCx

    

       
            
  
  218   Thursday, June 18, 2015, 11:39 Rick Maharaj    Installation of Extraction Electrode Insulator - New MaterialTuesday June 16, 2015
An Extraction Insulator ITD0381 made
from a different grade of AiN was installed
  
  231   Thursday, July 30, 2015, 17:07 John Wong   MaintenanceConnect NALCW to EVAP1  Thursday, July 30, 2015, 17:02
EVAP1 cooling system is now on the
NALCW.  The city water has been removed
  