Message ID: 132     Entry time: Friday, June 06, 2014, 16:01
Author: Cameron Hodgins 
Target Material:  
Target Oven W.O#:  
Source: TARGET BOAT 
Status: In progress 
Subject: Sintering several carbides on tantalum foil backing 

Auto-ramp started. Max current = 500 A, voltage = 11.05 V. Current is being increased at 2 A/min. In the first 20 minutes, the pressure went up to about 10E-6 T, but has slowly decreased since then. Everything looks ok. The system will be left until Monday morning (June 9th). 