Entry  Thursday, June 11, 2020, 13:01, Darwin Ortiz Rosales, Empty, 44139-12, LP-SIS, Done,  WO#_44139-12_TaC_sintering.PNG
 Thursday, June 11, 2020, 09:56
Previous day (Wednesday June 10, 2020) 
Container coated with TaC and wrapped with 3 Ta heat shields.
Entry  Monday, June 15, 2020, 14:28, Darwin Ortiz Rosales, Empty, 42218-7, HP-SIS, Done, TaC coating/sintering 
 Monday, June 15, 2020, 13:30
Container coated with TaC and wrapped with 3 Ta heat shields.
Desired temperature= 1900 C, Omega Slope set = 0.990, Auto TGHT at 0.2A/min to reach 400A, TGHT
Entry  Friday, July 31, 2020, 11:16, Ferran Boix Pamies, Empty, 41882-1, TARGET BOAT, Done, Thermocouple measurent of boat temperature 
Boat with attached thermocouple type C with AREMCO ceramabond glue installed in evap2 the 30-07-2020
Vacuum 3.2e-6torr in IGP1 after night with the roughing pump and morning with turbo.
TGHT heater on.
Entry  Wednesday, August 05, 2020, 19:14, Ferran Boix Pamies, Empty, 41882-1, TARGET BOAT, Done, Parasitic target cooling test 
 2020-08-05 7.13pm Roughing pump on
2020-08-06 10:48am Turbo was turned on by Marla in the morning. Vacuum IGP1 4e-6Torr. Water leak check performed, everything good to start heating
up target. Waiting for Anders confirmation to start.
Entry  Tuesday, August 11, 2020, 10:17, Ferran Boix Pamies, Empty, 41882-1, TARGET BOAT, In progress, Contamination foils temperature test 
The target was prepared and put under vacuum on 2020-08-10
 
2020-08-11 10:16am The pressure is 1e-6Torr. Leak checked performed, water on no problem. Starting to set target heating curve. 1A/10s up to 300A 
Entry  Wednesday, August 12, 2020, 11:57, Marla Cervantes, Empty, 44489-9, TARGET BOAT, Done, Pristine Ta tube calibration 
 Short oven loaded with additional hardware are spacers into the flex-line HS.
A Ta short tube was wrapped with 3 tantalum foils,
a tantalum cap was inserted in both sides of the Ta tube, the caps weren't sealed.
Entry  Sunday, August 30, 2020, 18:28, Marla Cervantes, Empty, 44489-13, , Done, TaC coating/sintering 
 Sunday, August 30, 2020, 06:47
A short tantalum tube was coated with TaC and wrapped with 3 layers of Ta,
a Ta cap was inserted to the end of the tube to be able to measure the temperature during heating
Entry  Saturday, September 05, 2020, 21:33, Marla Cervantes, Empty, , , Done, Pristine Ta tube calibration 
Saturday, September 05, 2020, 12:56
A Ta tube was wrapped with 3 tantalum foils,
a tantalum cap was inserted in both sides of the Ta tube, the caps weren't sealed.
Entry  Thursday, September 10, 2020, 07:53, Aaron Schmidt, Empty, 41790-8, LP-FEBIAD, Done, Fernando FEBIAD / Anode testing. 
 FEBIAD installed. Anode PS installed. ANODE connected!.
Leak check
Thursday, September 10, 2020, 07:46: Vacuum @ 6.30e-07T
Entry  Thursday, September 17, 2020, 16:11, Marla Cervantes, Empty, 44139-9, LP-SIS, Done, TaC coating/sintering 
 Thursday, September 17, 2020, 16:10
An LP-SIS was wrapped with 3 Ta layers, and installed in the EVAP2
Desired temperature= 1900 C, Omega Slope = 0.990
Entry  Friday, October 09, 2020, 09:50, Ferran Boix Pamies, Empty, 44139-7-SK, TARGET BOAT, Done, Tests, radiation gun for parasitic target 
 2020-10-09 9:48 The target was installed the day before and left pumping over night. IGP1=4.7e-7Torr. leak check when water on, ok. Setting ramp
up
 2020-10-09 10:16 Ramping up the target to 50A, 1.5A/30s. All good. Going to 200A same rate.
Entry  Tuesday, October 13, 2020, 11:15, Ferran Boix Pamies, Empty, 44139-7-SK, TARGET BOAT, Done, foil heating 
 2020-10-13 11:13 Target was left under vacuum over the weekend. IGP1: 1.6e-7T water on- leak check ok. Ramping up 2A/30s to 100A.
 2020-10-13 11:47 All ok at 100A. Ramping up, 1A/10s to 200A.
 2020-10-13 12:08 All ok at 200A. Temp tc on foil 200degC. Ramping up, 1A/10s to 300A.
Entry  Thursday, October 15, 2020, 18:51, Ferran Boix Pamies, Empty, 44139-7-SK, TARGET BOAT, Done, heat gun plus parasitic target thermal comissioning. 
 2020-10-15 18:51 : Setup installed during the day. Pumped down to IGP1:1.5e-5T , water leak check ok. Ramping up to 100A. 
 2020-10-15 19:30 : A heating element was showing bad signs and failed very early. ramping down and venting. 
Entry  Friday, October 16, 2020, 16:31, Luca Egoriti, Empty, , TARGET BOAT, In progress, HPOG annealing 
Friday, October 16, 2020, 11:30
 Target mounted in EVAP2. Pump down started
Friday, October 16, 2020, 12:05
Entry  Tuesday, October 27, 2020, 10:25, Ferran Boix Pamies, Empty, 44139-7-SK, TARGET BOAT, Done, parasitic target commissioning 
 2020-10-27 10:24 setup introduced yesterday. Pumping over night IGP1: 5.7e-7T. Water leak check ok. Performing heating elements check.
 2020-10-27 10:43 Heating elements check show low cooling. Ramping up target 1A/15s to 200A.
 2020-10-27 11:54 all ok 200A, thermocouples show room temperature on cartridge and heat shield. Ramping up target 2A/10s to 300A.
Entry  Monday, November 02, 2020, 18:32, Ferran Boix Pamies, Empty, 44139-7-SK, TARGET BOAT, Done, HEA heat treatment 20201104_102925.jpg20201104_144831.jpg
2020-11-02 6:32: roughing on
2020-11-02 7:21: Turbo on for a while, IGP1:1.8e-5T . water leak check ok.
2020-11-02 7:47: IGP1:1e-5T . Ramping up target heater to 200A, 1A/10s.
Entry  Wednesday, November 04, 2020, 17:31, Ferran Boix Pamies, Empty, 41882-2, TARGET BOAT, Done, Parasitic target graphite outgassing. 
 2020-11-04 17:31: target installed with boat containing graphite container for outgassing. Roughing pump on.
 2020-11-04 17:49 turbo on, leaving it pumping over night.
 2020-11-05 11:32 leak check ok. Ramping up target to 200A 2A/10s.
Entry  Thursday, November 05, 2020, 15:13, Ferran Boix Pamies, Empty, 41882-2, TARGET BOAT, Done, cleaning treatment. 
 2020-11-05 15:44 empty and naked boat in for heating up system and clean up. Turbo on.
 2020-11-06 16:58 IGP1:4e-7T leak check ok. Ramping up target to 500A. 1A/10s.
 2020-11-09 12:43 The target was left at 1500degC during the weekend. 
Entry  Friday, February 26, 2021, 09:28, Ferran Boix Pamies, Empty, none, , Done, Parasitic target thermal tests 
 Tests were performed with external power supply. No target boat or container.
Small power on heating small heating elements on parasitic target attached on isac heatshield with water cooling on. 
 
Entry  Tuesday, March 23, 2021, 11:28, Marla Cervantes, Empty, 44489-6, , Done, Re-coating test 3 
Objective: Coating the inner surface of a short tantalum boat with rhenium.
Result:

    The wire snnaped around 376 W (53 A, and 7.09 V) and 2170 °C (measured with filament pyrometer)
    The tube does not