77
|
Monday, June 17, 2013, 16:59 |
Laura Lambert | SiC | 38481-6 | HP-FEBIAD | Done | Sintering of SiC #29 | Monday, June 17, 2013, 16:57
Target is loaded with 510 SiC discs
Container was previously coated with |
|
78
|
Tuesday, June 18, 2013, 16:40 |
John Wong | SiC | 38481-6 | HP-FEBIAD | Done | Sintering of SiC #29 |
|
|
71
|
Tuesday, April 30, 2013, 11:20 |
Anders Mjos | Empty | 38481-5 | HP-FEBIAD | Done | CTL thermal test | CTL block on T/C F/T Ch 1
Supply on Ch 3
HS Return on Ch 4 |
  |
60
|
Wednesday, March 06, 2013, 10:41 |
Anders Mjos | Empty | 38481-4 | HP-FEBIAD | Done | CTL thermal test | Wednesday, March 06, 2013
The Cool Transfer Line (CTL) test
target is installed for thermal tests. Drawing |
 |
61
|
Wednesday, March 06, 2013, 17:53 |
John Wong | Empty | 38481-4 | HP-FEBIAD | Done | CTL thermal test |
|
  |
62
|
Monday, March 11, 2013, 12:23 |
Anders Mjos | Empty | 38481-4 | HP-FEBIAD | Done | CTL thermal test 2 |
|
|
63
|
Monday, March 11, 2013, 15:59 |
John Wong | Empty | 38481-4 | HP-FEBIAD | Done | CTL thermal test 2 |
|
|
64
|
Wednesday, March 13, 2013, 16:08 |
Anders Mjos | Empty | 38481-4 | HP-FEBIAD | Done | Thermal test | Wednesday, March 13, 2013
Thermocouple channels (see attached
PDF for photos) |
|
65
|
Thursday, March 14, 2013, 12:27 |
Anders Mjos | Empty | 38481-4 | HP-FEBIAD | Done | CTL thermal test 3 (w/o CTL block) | Thursday, March 12, 2013
The CTL was removed and target heated
to 580A / 300A |
 |
68
|
Friday, April 19, 2013, 15:27 |
Anders Mjos | Empty | 38481-4 | HP-FEBIAD | Done | CTL test | Target installed with 4 T/C
The target assembly is ITD0300 with
the CTL Cu cooling block slightly modified. |
|
69
|
Monday, April 22, 2013, 18:49 |
John Wong | Empty | 38481-4 | HP-FEBIAD | Done | CTL test |
|
|
70
|
Tuesday, April 23, 2013, 10:11 |
Anders Mjos | Empty | 38481-4 | HP-FEBIAD | Done | CTL test |
|
  |
17
|
Tuesday, May 15, 2012, 12:26 |
John Wong | SiC | 38481-2 | HP-SIS | Done | Re-condition the HP-SIS SiC target | Tuesday, May 15, 2012, 12:24
The HP-SIS SiC target was made on
Nov 03, 2010. The target consists of |
|
22
|
Friday, May 18, 2012, 12:19 |
Nikita Bernier | SiC | 38481-2 | HP-SIS | Done | Re-condition the HP-SIS SiC target |
|
 |
23
|
Friday, May 18, 2012, 13:17 |
John Wong | SiC | 38481-2 | HP-SIS | Done | Re-condition the HP-SIS SiC target |
|
|
24
|
Tuesday, May 22, 2012, 12:15 |
Nikita Bernier | SiC | 38481-2 | HP-SIS | Done | Re-condition the HP-SIS SiC target |
|
 |
25
|
Tuesday, May 22, 2012, 15:26 |
John Wong | SiC | 38481-2 | HP-SIS | Done | Re-condition the HP-SIS SiC target |
|
|
30
|
Monday, June 11, 2012, 12:26 |
John Wong | SiC | 38481-2 | HP-SIS | Problems | End caps vaporized |
|
|
43
|
Tuesday, August 14, 2012, 15:57 |
John Wong | SiC | 38295-8 | HP-FEBIAD | Done | Testing endcaps inserted /w the new expansion tool | Tuesday, August 14, 2012, 15:44
This SiC target was prepared in May
2011 with the Evaporator#1. The target |
 |
439
|
Wednesday, April 17, 2019, 09:06 |
Marla Cervantes | | 38295-10 | LP-FEBIAD | Done | Graphite insert test | Wednesday, April 17, 2019, 09:03
An uncoated target container was
loaded with a graphite insert and wrapped |
 |
|