Entry  Monday, February 18, 2013, 16:43, John Wong, Empty, , LP-SIS, Done, Sintering TaC coating on the RFQ target container SiC#28_-_LPSIS-RFQ.pngSintering_of_TaC.PNGautorampingdown_10.PNG
 Monday, February 18, 2013, 16:28
The RFQ target container is coated with TaC and ready to be sintered.  No Ta-heat shields are used.  This container will be used for
the SiC#28-LPSIS-RFQ. 
Entry  Friday, February 22, 2013, 15:55, John Wong, SiC, , LP-SIS, Done, Sintering SiC#28-RFQ RFQ_SiC#28_-production_process.mp4
Friday, February 22, 2013, 15:49
The LP-SIS RFQ target container was previously coated with TaC and sintered up to ~1500C (TGHT @ 600A, TBHT @ 300A). 
The container is loaded with 325 discs of SiC, a total of 10.9cm in length. 
Entry  Monday, March 04, 2013, 17:41, John Wong, Empty, LP-SIS RFQ ver 2.0, , , Testing LPSIS RFQ ver 2.0 
 Monday, March 04, 2013, 17:39
This is the 2nd modified target container for RFQ LPSIS.  The container will be heated up to 650A TGHT and 150A on TBHT.  No Ta-heat
shield is being used.  
    Reply  Wednesday, March 06, 2013, 17:53, John Wong, Empty, 38481-4, HP-FEBIAD, Done, CTL thermal test rampingup_1.PNGrampingup_2.PNGautorampingdown_23.PNG


    
        
            Anders Mjos wrote:
        
        
            
            Wednesday, March 06, 2013
    Reply  Monday, March 11, 2013, 15:59, John Wong, Empty, 38481-4, HP-FEBIAD, Done, CTL thermal test 2 autorampingup_110.PNG


    
        
            Anders Mjos wrote:
        
        
            
            
            
              
Entry  Thursday, April 11, 2013, 14:20, John Wong, Empty, 39165-6, LP-SIS, Done, Coating target oven /w TaC & sintering for UCx#6 
Monday, April 08, 2013, 17:39
Target container is coated with TaC; the container will be used for the UCx#6 target. 
No Ta-heat shields are used.
    Reply  Monday, April 22, 2013, 18:49, John Wong, Empty, 38481-4, HP-FEBIAD, Done, CTL test 


    
        
            Anders Mjos wrote:
        
        
            
            Target installed with 4 T/C
Entry  Tuesday, May 14, 2013, 17:15, John Wong, Empty, 38481-6, HP-FEBIAD, Done, SinteringTaC coating 
Tuesday, May 14, 2013, 17:04
Target oven is coated with TaC, and wrapped with 3-Ta heat shields.
TGHT and TBHT will be ramped up to 820A and 300A, respectively.
Entry  Tuesday, May 28, 2013, 17:50, John Wong, , Target Boat #2 , , Done, Sintering TaC coated end caps 
Tuesday, May 28, 2013, 17:36
The target containers endcaps were coated with TaC solution and let dry. 
Each cap is wrapped with a small piece of graphite foil and inserted in the target boat.
    Reply  Tuesday, June 18, 2013, 16:40, John Wong, SiC, 38481-6, HP-FEBIAD, Done, Sintering of SiC #29 


    
        
            Laura Lambert wrote:
        
        
            
            Monday, June 17, 2013, 16:57
Entry  Monday, July 22, 2013, 15:03, John Wong, Empty, 38634-7, LP-SIS, Done, Sintering empty target oven coated with TaC for UCx#7 
Monday, July 22, 2013, 15:00
Target container is coated with TaC - this container will be used for UCx#7.
Container is wrapped with 3 layers of Ta, including the back-block.
    Reply  Thursday, August 08, 2013, 17:28, John Wong, NiO, 39530-6, HP-FEBIAD, Done, Sintering NiO # 2 


    
        
            Laura Lambert wrote:
        
        
            
            Thursday, August 08, 2013, 15:19
Entry  Wednesday, August 21, 2013, 12:30, John Wong, Ta, 38817-10, HP-SIS, Done, Conditioning Ta target  Ta#41_conditioning.PNG
Wednesday, August 21, 2013, 12:28
Container is filled with 400 discs of Ta foils, and wrapped with 3 layers of Ta heat shields.
No caps are inserted during the conditioning. 
Entry  Tuesday, August 27, 2013, 17:01, John Wong, , targetboat (TaC coated), , Done, Sintering TaC coated regular caps  Sintering__endcap_.jpg
Tuesday, August 27, 2013, 16:48
Target boat is filled with TaC coated endcaps (brown) and some partial sinterred ones (gray) from before.  (see attachment#1).
The container is wrapped with Ta heat-shield.
Entry  Tuesday, September 17, 2013, 11:21, John Wong, Nb, target boat #3 (brand new!) , , , Nb thermo treatment (Bob's samples)  Nb_sample_setup.PNGNb_800C.PNG
Tuesday, September 17, 2013, 11:14
Target boat contains 5 Nb discs.  3 discs are wraps with 0.001" thin of Nb foil (99.8% pure), and 2 are wraps with 0.001" Ta foil
(see attachment#1)
    Reply  Thursday, September 19, 2013, 17:02, John Wong, Nb, target boat #3 (brand new!) , , , Nb thermo treatment (Bob's samples)  


    
        
            Laura Lambert wrote:
        
        
            
            
            
    Reply  Friday, September 20, 2013, 14:59, John Wong, Nb, target boat #3 (brand new!) , , , Nb thermo treatment (Bob's samples)  


    
        
            John Wong wrote:
        
        
            
            Tuesday, September 17, 2013, 11:14
    Reply  Monday, September 23, 2013, 16:18, John Wong, Nb, target boat #3 (brand new!) , , , Nb thermo treatment (Bob's samples)  


    
        
            John Wong wrote:
        
        
            
            
            
Entry  Thursday, September 26, 2013, 15:17, John Wong, Empty, 39814-VI-?, LP-IG-LIS, Done, Sintering empty target oven coated with TaC for UCx#8 UCx#8_container_TaC_coat_sintering.PNG
Thursday, September 26, 2013, 13:04
The LP-IG-LIS target container is coated with TaC. 
Container is wrapped with 3 layers of Ta heat shield and about to go through the sintering process.
Entry  Friday, October 04, 2013, 16:21, John Wong, Empty, , LP-SIS, Done, Sintering TaC coating on a LP target container to be used for C-grv tube test  LP_C_grv_tempcurve.PNGLP_C_grv_TGHT632_1960C.PNG
Friday, October 04, 2013, 15:37
A LP target container is coated with TaC.  The container is wrapped with 3 layers to heat shield.  
This container will be used for the graphite tube test.  