Tuesday, May 28, 2013, 17:36
The target containers endcaps were coated with TaC solution and let dry.
Each cap is wrapped with a small piece of graphite foil and inserted in the target boat.
The chamber is currently being pumped down.
The HS cooling water valve will be opened tomorrow; any leak will be inspected.
When the vacuum is good, TGHT will be ramped up to 580A.
Wednesday, May 29, 2013, 17:06
HS water valve was opened early this morning; no leaks were detected.
TGHT has stepped up to 50A. IG is currently at 2.0e-6Torr.
Initiated auto-ramping at 1.0A/min.
Thursday, May 30, 2013, 11:12
TGHT reached to 580. The end caps have been heated at that current for more than 7 hrs.
IG is coming down, currently at 8e-7 Torr.
Auto-cooling initiated, ramping down at 2A/min .
|