ID |
Date |
Author |
Target Material |
Target Oven W.O# |
Source |
Status |
Subject |
Text |
 |
8
|
Tuesday, March 20, 2012, 14:39 |
John Wong | BeO | Target boat #1 | | Done | Sintering BeO pellets |
|
|
7
|
Tuesday, March 20, 2012, 14:35 |
John Wong | | | | Done | Evap#2 Backing up muffler not connected to the exhaust system. | Tuesday, March 20, 2012, 14:22
The Evaporator #2 backing pump (IEVAP2:BP1)
muffler has not connected to the exhaust |
 |
6
|
Monday, March 19, 2012, 17:10 |
Nikita Bernier | BeO | Target boat #1 | | Done | Sintering BeO pellets | Monday, March 19, 2012, 17:04
Target boat contains 4 BeO pellets |
|
5
|
Thursday, March 01, 2012, 14:42 |
John Wong | | | | | IEVAP2:TGHT/TBHT max current setpoint issue | Thursday, March 01, 2012, 14:35
Both the IEVAP2:TBHT and IEVAP2:TGHT
maximum current setpoints on the vacuum page |
|
4
|
Tuesday, February 28, 2012, 11:00 |
John Wong | Empty | Test oven | LP-SIS | Done | Measuring temperatures, currents & voltages | Tuesday, February 28, 2012, 10:36
Two thermocouples were inserted through
the left side of the copper heat shield, |
|
3
|
Monday, February 13, 2012, 16:24 |
John Wong | | | | Done | Evaporator #2 Commissioned | Monday, February 13, 2012, 16:21
The Evaporator 2 is now commissioned.
See attachment#1 for the commissioning |
|
2
|
Thursday, July 21, 2011, 17:33 |
Pierre Bricault | | | | Maintenance | | Rick mentioned to me that the evaporator is
ready for the next steps of the commissioning
process.
|
|
1
|
Monday, March 28, 2011, 12:40 |
John Wong | | | | | Under Construction | Evaporator #2 is still under construction.
For further information please contact Jens
Lassen. |
|
|