  239   Thursday, August 20, 2015, 17:15 John WongTa HP-SISDoneConditioning Ta#46 Target

    

       
            
  
  238   Thursday, August 20, 2015, 10:07 Laura LambertTa HP-SISIn progressConditioning Ta#46 Target

    

       
            
  
  237   Wednesday, August 19, 2015, 17:26 John WongTa HP-SISIn progressConditioning Ta#46 Target

    

       
            
  
  236   Tuesday, August 18, 2015, 16:02 Laura LambertTa HP-SISIn progressConditioning Ta#46 TargetTuesday, August 18, 2015, 15:53
Target consists of 505 discs.
Total packed length 3.4cm.
  
  235   Thursday, August 06, 2015, 15:45 Laura LambertEndcaps TARGET BOATDoneSintering TaC coating on Ta endcaps Thursday, August 06, 2015, 15:36
The endcaps are stacked together
with a punched out disc of graphite foil
 round2_july_batch_(1).jpground2_july_batch_(2).jpground2_july_batch_(3).jpgsingle_round_sintering_(1).jpgsingle_round_sintering_(2).jpg 
  234   Tuesday, August 04, 2015, 12:04 Laura LambertTa TARGET BOATDoneTest for homogeneity: Sintering TaC coating on a Ta tube

    

       
            
 Temp_measurements_of_new_port_window_for_2nd_OMEGA.xlsxIMG_20150806_151719182.jpgIMG_20150806_151748536.jpg 
  233   Friday, July 31, 2015, 15:51 John WongTa TARGET BOATIn progressTest for homogeneity: Sintering TaC coating on a Ta tube Friday, July 31, 2015, 15:39
A Ta tube was coated with TaC.  The
inner of the tube was filled with TaC solution
 Screen_Shot_2015-07-31_at_3.46.10_PM.png 
  232   Friday, July 31, 2015, 15:10 John Wong   MaintenanceInstalled leftside portFriday, July 31, 2015, 15:09
The left side port was installed
on the evaporator #2.  Leak check was
  
  231   Thursday, July 30, 2015, 17:07 John Wong   MaintenanceConnect NALCW to EVAP1  Thursday, July 30, 2015, 17:02
EVAP1 cooling system is now on the
NALCW.  The city water has been removed
  
  230   Monday, July 13, 2015, 11:54 Laura LambertEndcaps40282-5TARGET BOATProblemsSintering TaC coating on Ta endcaps Monday, July 13, 2015, 11:53
A Ta foil is placed in the target
 endcaps_july_14_2015.JPGIMG_20150715_102332633.jpgIMG_20150715_102240364_HDR.jpgIMG_20150715_102631676.jpg 
  229   Monday, July 06, 2015, 16:30 Laura LambertEmpty41369-2LP-SISDoneSintering TaC coating container

    

       
            
 July_10_2015_-_2nd_round_sintering_-_coating_(1).jpgJuly_10_2015_-_2nd_round_sintering_-_coating_(2).jpgJuly_10_2015_-_2nd_round_sintering_-_coating_(3).jpgJuly_10_2015_-_2nd_round_sintering_-_coating_(4).jpg 
  228   Monday, July 06, 2015, 12:07 John WongEmpty41369-2LP-SISIn progressSintering TaC coating container

    

       
            
 Screen_Shot_2015-07-06_at_11.52.16_AM.png 
  227   Tuesday, June 30, 2015, 09:50 Laura LambertEmpty41369-2LP-SISIn progressSintering TaC coating container

    

       
            
 LP-SIS_july3_2015_(1).jpgLP-SIS_july3_2015_(2).jpgLP-SIS_july3_2015_(3).jpgLP-SIS_july3_2015_(4).jpg 
  226   Monday, June 29, 2015, 23:42 John WongEmpty41369-2LP-SISIn progressSintering TaC coating container

    

       
            
  
  225   Monday, June 29, 2015, 16:18 Laura LambertEmpty41369-2LP-SISIn progressSintering TaC coating container Monday, June 29, 2015, 16:17
Target container is coated with
  
  224   Monday, June 29, 2015, 07:05 John WongZrC41177-2LP-SISDoneSintering back-up ZrC

    

       
            
 Screen_Shot_2015-06-29_at_7.14.12_AM.png 
  223   Thursday, June 25, 2015, 16:20 Laura LambertZrC41177-2LP-SISIn progressSintering back-up ZrC Thursday, June 25, 2015, 16:14
Total number of foils: 422 discs
  
  222   Thursday, June 25, 2015, 16:13 Laura LambertSiC38817-6HP-SISDoneRUSH! SiC backup target undergoes sintering process

    

       
            
 IMG_20150625_152233125.jpgIMG_20150625_152256456.jpg 
  221   Tuesday, June 23, 2015, 12:26 John WongSiC38817-6HP-SISIn progressRUSH! SiC backup target undergoes sintering processTuesday, June 23, 2015, 12:21
Target container is loaded with 485
discs of SiC with packed length of 17.4cm. 
  
  220   Tuesday, June 23, 2015, 10:18 Laura LambertEmpty38817-6HP-SISDoneRUSH! Sintering TaC coated container for SiC

    

       
            
  