Entry  Thursday, June 25, 2015, 16:20, Laura Lambert, ZrC, 41177-2, LP-SIS, In progress, Sintering back-up ZrC 
    Reply  Monday, June 29, 2015, 07:05, John Wong, ZrC, 41177-2, LP-SIS, Done, Sintering back-up ZrC Screen_Shot_2015-06-29_at_7.14.12_AM.png
Message ID: 223     Entry time: Thursday, June 25, 2015, 16:20     Reply to this: 224
Author: Laura Lambert 
Target Material: ZrC 
Target Oven W.O#: 41177-2 
Source: LP-SIS 
Status: In progress 
Subject: Sintering back-up ZrC 

 Thursday, June 25, 2015, 16:14

Total number of foils: 422 discs

Total mass of materials [incl graphite foils]: 

Total length packed: 12.0cm

Container has one Ta heat shield.

No endcaps inserted to allow outgassing

Two TaC coated Ta wires formed into a spring inserted either end to avoid ZrC expansion of materials.

Currently being pumped down.


 Friday, June 26, 2015, 11:44

HS water valves opened.

No leaks detected.

Initiating ramp up.


 Friday, June 26, 2015, 14:44

EVAP2 was tapped up manually to 50A.

Vacuum tripped evap off.

Tapping back up manually now...


 Friday, June 26, 2015, 15:53

Tapped up manually to 45A for both TGHT and TBHT

IGP1 = 4.8e-5 Torr

Will initiate auto-ramp at 0.2A/min and 0.1A/min for the TGHT and TBHT respectively once vacuum settled down and stable.

Max setpoints set to 520A and 230A for the TGHT and TBHT respectively.

Good Vacuum = 3.0e-5 Torr. Bad Vacuum = 4.0e-5 Torr.


 