  756   Thursday, August 29, 2019, 14:47 Fernando Maldonado     Ferran's heat shieldProblems/SolutionsRewiring-Baking outThursday, August 29, 2019, 14:47 : Changing
back to the nominal wiring 
Thursday, August 29, 2019, 17:01:
  
  757   Monday, September 16, 2019, 10:05 Fernando Maldonado      Problems/SolutionsAlignment pin reinstalled Monday, September 16, 2019, 10:03:
The rightmost alignment pin has been reinstalled
(see picture attached). It was previously
 20190916_095937.jpg 
  765   Monday, October 28, 2019, 09:24 Fernando Maldonado      Problems/SolutionsTSG:CG1A checked with local readerMonday, October 28, 2019, 09:22: The local
reader indicated 42 mTorr while EPICS showed
51mTorr.
  
  766   Wednesday, October 30, 2019, 14:50 Fernando Maldonado      Problems/SolutionsCathode bias mode configurationWednesday, October 30, 2019, 14:49: John
C. changed the polarity of the anode power
supply to negative, and Fernando M. rewired
  
  767   Thursday, October 31, 2019, 11:37 Fernando Maldonado      Problems/SolutionsProbing anode bias supply on the service capThursday, October 31, 2019, 10:41: Cage
removed. Tape put on the limit switches.
Anode interlock bypassed.
  
  768   Thursday, October 31, 2019, 13:22 Fernando Maldonado      Problems/Solutions9pin connector not fully in contact with baseplateThursday, October 31, 2019, 13:20: After
inspecting the interior, the 9 pin bracket
was found not making full contact with the 
 20191031_130003.jpg20191031_130028.jpg 
  769   Friday, November 01, 2019, 16:01 Fernando Maldonado LP-SIS  41790-9 43515-9 In progressPeek seal tests on UCx#30 HSFriday, November 01, 2019, 15:47: A symbiotic 
peek seal assembly  was installed on
the manipulator grip to verify the temperature
 UC#30-plus-peak-seal.docxTS-2019-11-01-16-22.rgaTS-2019-11-04-16-12.rgaTS-2019-11-05-08-30.rga 
  773   Wednesday, November 27, 2019, 16:01 Fernando Maldonado      Problems/SolutionsNew Controller for TP6Wednesday, November 27, 2019, 15:31: During
HV tests, bias was around 55kV when a spark
occur and almost immediately the controller
  
  774   Monday, December 02, 2019, 16:01 Fernando Maldonado      In progressFerran irradiation copper end plate tests (aka MIST)Friday: Test to validate Ferran's assembly.
The plan is to ramp up to operating current,
apply high voltage, and possibly extract
  
  788   Wednesday, March 04, 2020, 17:15 Fernando Maldonado      Problems/SolutionsEmittance rig communicationWednesday, March 04, 2020, 17:13: EPICS
page indicated a sucesful scan but data was
empty.
  
  797   Thursday, June 25, 2020, 08:57 Fernando MaldonadoTest FEBIADHP-FEBIAD  38295-842752-5DoneFEBIAD development part 1/3 Reminder. Mini
pump still linked to SV1. DO NOT OPEN SV2!!!
  
  798   Tuesday, June 30, 2020, 21:59 Fernando MaldonadoTest FEBIADHP-FEBIAD  38295-8 42752-5 DoneFEBIAD development part 2/3 Reminder. Mini pump
still linked to SV1. DO NOT OPEN SV2!!!
  
  799   Monday, July 06, 2020, 05:28 Fernando MaldonadoTest FEBIAD HP-FEBIAD  38295-8 42752-5 DoneFEBIAD development part 3/3Reminder. Mini pump still linked
to SV1. DO NOT OPEN SV2!!!
  
  825   Wednesday, December 02, 2020, 16:18 Fernando Maldonado      DoneGas delivery system upgradeYesterday, December 1st, I successfully
installed and tested the gas system inside
the faraday cage.
  
  838   Thursday, January 14, 2021, 08:31 Fernando Maldonado      In progressGas delivery system upgrade

    

       
            
 new-gauge.png 
  839   Wednesday, January 20, 2021, 11:30 Fernando Maldonado      DoneCathode bias mode configuration confirmed

    

       
            
  
  840   Thursday, January 21, 2021, 10:10 Fernando Maldonado LP-SIS  44139-1044378-2DoneEnergy spread calibration - SIS with TBHT negatively biased Thursday, January 21, 2021, 10:05:
Anodeless Negative Bias On Surface Ion 
Source, or ANBOSIS (still working on the
  
  841   Thursday, January 21, 2021, 10:55 Fernando Maldonado      DoneUpdated Good Vac value for TSG:IG1On Tuesday the hard good vacuum level was
changed from 7e-6 T to 1e-5 T
to allow larger leak rates when testing FEBIAD.
  
  843   Monday, February 01, 2021, 08:38 Fernando Maldonado LP-SIS  44139-10 44378-2 FailedEnergy spread calibrationMonday, February 01, 2021, 08:38 : The
anode seems to be shorted but we can still
test the  amount of dispersion at the
 ESC_-_Jan_29_start.docxESC_-__Feb_3_start.docxER-580-230-30kV-m7.txtEr-580-230-30kV-m133.txt 
  844   Thursday, February 04, 2021, 18:48 Fernando Maldonado LP-SIS  44139-10 44378-2 Problems/SolutionsEnergy spread calibration with SISThe system was vented to  make clearance
on the waterlines as a very small continuous
discharge was observed.
 6x 