Message ID: 756     Entry time: Thursday, August 29, 2019, 14:47
Author: Fernando Maldonado 
Target/No.#:  
Source:  
Station:  
Module:  
Target Oven W.O#:  
Heat Shield W.O#: Ferran's heat shield 
Status: Problems/Solutions 
Subject: Rewiring-Baking out 

Thursday, August 29, 2019, 14:47 : Changing back to the nominal wiring 

Thursday, August 29, 2019, 17:01: TIS changed to Ferran's heat shield. 

Thursday, August 29, 2019, 17:02: 9-pin FT redone.

Friday, August 30, 2019, 00:28: Turbos on 

Friday, August 30, 2019, 00:36: IG1 on. 

Tuesday, September 03, 2019, 09:09: RGA on. Vacuum stable @ 2.1e-6T 

Tuesday, September 03, 2019, 15:00. Wire redone. Crosschecked by Arthur Leung. 

Tuesday, September 03, 2019, 15:16: Turbos tripped. TSG:CG1A above 50 mTorr 


Wednesday, September 04, 2019, 09:34 : Turbos on.  After the bakeout it will be better to have TSG:CG1A checked.

Wednesday, September 04, 2019, 09:43: IG1 on 

Wednesday, September 04, 2019, 09:45: RGA on 

Wednesday, September 04, 2019, 12:42 : Waterlines opened. No response on RGA. Vaccum stable @ 3.1e-6 T

Wednesday, September 04, 2019, 14:53 : Auto-ramping TGHT / TBHT to 100/ 100 A @ 4 A/min.

Wednesday, September 04, 2019, 16:04:  Auto-ramping TGHT / TBHT to 250/ 250 A @ 4 A/min.

Wednesday, September 04, 2019, 17:33: Final auto-ramping of the day TGHT / TBHT to 290/ 290 A @ 4 A/min. Vacuum stable@2.7e-7T

NB: Ferran's HS doesn't have an extraction electrode. Since the purpose of the heating is to "baked-out" the system, this is actually great as the shine will go downstream the beamline.


Thursday, September 05, 2019, 08:05:  Auto-ramping TGHT  to 580 A @ 2 A/min. Vacuum stable @2.97e-7T

Thursday, September 05, 2019, 09:30: TGHT PS is voltage-limited @440A and 5.2V. Stopping auto-ramping to increase the voltage limit to 7.7 (from previous screenshots).

Thursday, September 05, 2019, 09:31: Auto-ramping TGHT to 580A @ 2A/min.

Wednesday, May 15, 2019, 08:58: Optics/ HV on.

Monday, September 09, 2019, 16:05: Optics set. IV4 open.

Monday, September 09, 2019, 17:26: BIAS / EE / EZL @ 30 / -1.5 / 13 kV.

Twenty minutes w/o sparks

Monday, September 09, 2019, 17:52 Optics/HV off


Tuesday, September 10, 2019, 10:05:  Auto-cooling 4A/min

Tuesday, September 10, 2019, 13:27: IV4 closed.

Tuesday, September 10, 2019, 13:27: IG1 off. RGA off

Tuesday, September 10, 2019, 13:28: Turbos off


Wednesday, September 11, 2019, 09:21: Venting.

Wednesday, September 11, 2019, 09:24 HS waterline purged

Wednesday, September 11, 2019, 10:54:  Cleaned the interior of chamber with methanol and Kim-wipes. Some dust and debris were removed with

Wednesday, September 11, 2019, 10:54 : Adding EE to the Assy.

Wednesday, September 11, 2019, 11:03: Roughing.

Wednesday, September 11, 2019, 11:35: Turbos on

Wednesday, September 11, 2019, 11:47: Turbos at  speed.

Wednesday, September 11, 2019, 11:48: IG1 on

Wednesday, September 11, 2019, 11:54: RGA on


Friday, September 13, 2019, 08:56: RGA off. IG1 off.

Friday, September 13, 2019, 08:56: Turbos off


Monday, September 16, 2019, 08:11: Venting

Monday, September 16, 2019, 09:58: Assembly removed.