Entry  Monday, January 14, 2013, 18:18, Friedhelm Ames, , , , , , , , TMS:CBC1 not working 
The optics at the teststand has been switched on, but TMS:CBC1 is not working. A fault report has been send to controls.
Entry  Tuesday, May 21, 2013, 19:38, Friedhelm Ames, , , , , , , Problems/Solutions, magnet power supply water leak 
The cyclotron operators discovered a water leak in the magnet power supply. The water is valved off and the power is off. A fault report has been issued
to the power supplies group.
Entry  Wednesday, June 12, 2013, 20:38, Friedhelm Ames, , , , , , , Problems/Solutions, target heater power supply removed 
The target heater power supply at the teststand has been removed to replace one in ITE.
Entry  Monday, June 29, 2015, 16:51, Friedhelm Ames, , , , , , , Problems/Solutions, TSG:BV1B closed 
found TSG:TP1B tripped off. Closed TSG:BV1B as pressure at TSG:iG1 was rising. Pressure is coming down again.

Tuesday, June 30, 2015 by AM
Found the control cable not completely inserted. Inserted cable, which tripped TP1A. Started both turbo pumps again.
Entry  Wednesday, August 25, 2021, 15:30, Ferran Boix Pamies, , , , , , , , Thermocouple high voltage test 
Wednesday, August 25, 2021, 15:29: Roughing.

Thursday, August 26, 2021, 04:11: IG1 switched on. Vacuum @ 8.35e-06T - AS 
Thursday, August 26, 2021, 14:04 Water on, no spike in vacuum. IG1:2.6e-6T
Entry  Monday, November 27, 2023, 16:09, Ferran Boix Pamies, , LP-SIS, , , 45220-2, 45235-13, In progress, HV power surge test plus mass scans 
Monday, November 27, 2023, 16:09  Roughing
Monday, November 27, 2023, 17:22 Both turbos are on, leaving vacuum over night.
Tuesday, November 28, 2023, 09:28  after pumping over night IG1 is at .15e-6 T. Water cooling on.
Entry  Friday, August 09, 2024, 21:08, Ferran Boix Pamies, Ta#67 Thin foils , LP-SIS, ITE, TM4, 45447-14 , 45235-10, In progress, Ta#67 thin foil retesting ITE-TM4-Ta#67-LP-SIS_Thin_Foil.docx
Friday, August 09, 2024, 21:07 Insulators, retainer and Re foil have been replaced, source cup machined so the ion source does not short against it.
Venting TS now.
Friday, August 09, 2024, 22:17 Roughing.
Entry  Friday, November 22, 2019, 19:06, Fernando Maldonado, Ferran Boix Pamies, , , , , , , , PEEK seal tests 
 Friday, November 22, 2019, 19:02: The new design for the PEEK irradiation will be tested.
Blinds were removed and a new LP-SIS assembly with a modify heatshield was installed. Three termocuples installed.
Friday, November 22, 2019, 19:04: Roughing 
Entry  Wednesday, March 21, 2018, 14:11, Fernando Maldonado, , LP-FEBIAD, , , 395530-3, 42752-2, In progress, Test FEBIAD  10x
Tests on coil, temperature and the use of silver bolts.
(3) Vented silver bolts on the TBHT and (2) Full silver bolts on the coil
Wednesday, March 21, 2018, 14:10: Roughing.
Entry  Thursday, April 19, 2018, 12:55, Fernando Maldonado, , , , , , , Done, Re-wiring Anode PS 20180420_104954.jpg
Thursday, April 19, 2018, 12:52: Pin J1 was reconnected into the anode power supply. All jumpers were put back to remote control.
NOTE: the cable EXTLKT is still not connected. I will ask Carla about this one.
Thursday, April 19, 2018, 18:00: Cable EXTLKT connected.
Entry  Wednesday, June 19, 2019, 17:25, Fernando Maldonado, , , , , , , Done, Thermocouple connection 
Wednesday, June 19, 2019, 17:13  Ferran and Fernando tested the 9-pin connector to have a reading on a thermocouple following the connections used
by Aurelia (see elog 721).
Wednesday, June 19, 2019, 17:24: Test succesful!
Entry  Monday, June 24, 2019, 15:41, Fernando Maldonado, , , , , , , Problems/Solutions, TMS:Q3 polarity 
Monday, June 24, 2019, 15:25: Current quadrupole polarities:

    
        
             

           Top/Bottom
            North/South
        
    
    
Entry  Tuesday, June 25, 2019, 17:19, Fernando Maldonado, , , , , , , Problems/Solutions, Burnt cables on top of the test stand 20190625_154015.jpg20190625_153834.jpg20190625_165001.jpg
Tuesday, June 25, 2019, 16:15: While inspecting the 9-pin connection with Ferran, it was noticed how two braided cables were burnt out pretty bad to
the point they were separated in half (see attached pictures).  Additionally the plastic insulator for the anode wire was melted.
Tuesday, June 25, 2019, 16:30: Braided cables need to be changed and anode wire redone. 
Entry  Thursday, June 27, 2019, 09:51, Fernando Maldonado, , , , , , , Problems/Solutions, Melted cables changed 
See elog 737 

    
        
            Fernando
Entry  Tuesday, July 02, 2019, 18:25, Fernando Maldonado, , , , , , , Done, Blank on FEBIAD gas line installed 20190702_182254.jpg
 Tuesday, July 02, 2019, 18:24: A blind is installed  on the FEBIAD gas line (see attached picture)  to rule out the possibility
of  gases entering the TIS.
Entry  Monday, July 15, 2019, 15:59, Fernando Maldonado, P2N, , , , , , Done, Re-wiring on service cap. 
Monday, July 15, 2019, 15:54 : TBHT high current cables moved to Coil feedthroughs.
Coil high current cables moved to TBHT feedthroughs.
Resistor across  Coil feedthroughs E and F are now moved between TBHT feedthroughs A and B.
Entry  Tuesday, July 16, 2019, 10:28, Fernando Maldonado, P2N, , , , , , , P2N 1200 A test 
Tuesday, July 16, 2019, 10:27: The idea of this run is to have the full 600 A from TGHT and the full 600 A from TBHT.
This will done based on the rewiring done previously (see entry 745)
Tuesday, July 16, 2019, 12:16: Jumper cable F-H burning while target was at 600 A total. Ramp up aborted and auto-cooling started to remove the
Entry  Friday, July 19, 2019, 13:48, Fernando Maldonado, , , , , , , Problems/Solutions, RMP0A and FC6 gains signal redirection to another channel 
After submitting a fault report (FR - ISAC Fault 12461) a Work Permit was issued (WP - C2019-07-19-1),
Controls tunnel the faulty signal to another ADC by removing signal no longer used at the Test Stand.
Test successful with a constant current power supply in the range 1 nA-40 nA.
Entry  Wednesday, August 07, 2019, 15:19, Fernando Maldonado, , , , , , , Problems/Solutions, Test stand inspection 
Wednesday, August 07, 2019, 15:12:  Arthur helped inspected the electric connections on the TS.
One of the coil  positive waterlines  was touching a HS waterline. Manually adjusted them to have a  better clearance.
 
Entry  Thursday, August 15, 2019, 16:33, Fernando Maldonado, , , , , , , Problems/Solutions, 9-pin connection modification 
Thursday, August 15, 2019, 16:17: Q FT undone to remove the connection to the 9-pin
The idea is to change the cables to have individual signals. This will allow 4 thermocouple readings.
NB: The FT is not vacuum tight as of now  (gasket needs to be replaced and flange needs to be tight)