Message ID: 741     Entry time: Tuesday, July 02, 2019, 18:25
Author: Fernando Maldonado 
Target/No.#:  
Source:  
Station:  
Module:  
Target Oven W.O#:  
Heat Shield W.O#:  
Status: Done 
Subject: Blank on FEBIAD gas line installed 

 Tuesday, July 02, 2019, 18:24: A blind is installed  on the FEBIAD gas line (see attached picture)  to rule out the possibility of  gases entering the TIS.