ID |
Date |
Author |
Target/No.# |
Source |
Station |
Module |
Target Oven W.O# |
Heat Shield W.O# |
Status |
Subject |
Text |
|
|
679
|
Tuesday, August 21, 2018, 12:54 |
Anders Mjos | | | | | | | Problems/Solutions | 9-pin connection configuration | Pin configuration between top 9-pin connector
on Source Tray and terminal in high voltage
rack. Measured 2018-08-21 by Aaron and Anders |
|
|
285
|
Tuesday, March 19, 2013, 19:13 |
Sebastian Raeder | | | | | | | Problems/Solutions | 9 Pin connector rewired to match wiring in TM4 | The 9 Pin connector was rewired in the
ISAC teststand to match the wiring in TM4
The wiring from the connection board |
|
|
244
|
Tuesday, December 11, 2012, 13:27 |
Sebastian Raeder | | | | | | | | 9 PIN connector | A Sub D 9 Pin connector on a HV insulator
was installed on Port Q of the target box
at the teststand. The insulator is leak tested |
|
|
913
|
Monday, March 21, 2022, 13:59 |
Carla Babcock | | | | | | | | 3rd mass marker test | 3rd version of the mass marker target has
been installed. This one is further back
on the heat shield, and has a longer ceramic |
|
|
286
|
Thursday, March 21, 2013, 15:05 |
Sebastian Raeder | SiC#28 | | ITE | TM4 | | | Done | 2nd heating of SiC#28 LP-RFQ - short resolved |
|
|
|
324
|
Monday, July 22, 2013, 14:08 |
Anders Mjos | | | | | | | Problems/Solutions | 20V 60A COIL PS installed for FEBIAD Coil Test | By Ray. Note that controls have not been
updated yet. |
|
|
707
|
Monday, January 21, 2019, 10:55 |
Aaron Schmidt | | | | | | | | 2019 Anode tests FM-1 | Monday, January 21, 2019, 10:50: RGA on.
Monday, January 21, 2019, 10:54:
Waterlines opened. No response on RGA. Vacuum |
|
|
870
|
Wednesday, April 14, 2021, 10:21 |
Luca Egoriti | P2N test - Apr 2021 | HP-SIS | | | | | In progress | P2N test - Electrical reconfiguration | Wednesday, April 14, 2021, 10:18
Work started to bring the ATTS PS
inside the ITS HV cage. HV grounding rod |
|
|
37
|
Tuesday, February 28, 2012, 11:04 |
Pierre Bricault | | | | | | | | | Calibrating the gas valve |
|
|
161
|
Friday, August 10, 2012, 15:57 |
Pierre Bricault | | | | | | | | | Test high voltage to 30 kV ok
Test gas valve open at 6.1 V
Test Ne leak ok |
|
|
177
|
Friday, August 17, 2012, 12:53 |
Pierre Bricault | | | | | | | Done | | Test completed.
exel file on My Documents in folder
FEBIAD Test Aout2012/TestFEBIAD |
|
|
194
|
Thursday, September 06, 2012, 09:23 |
Friedhelm Ames | NB#7 | | | | | | | | start high voltage and heaters |
|
|
652
|
Thursday, March 29, 2018, 10:58 |
Carla Babcock | | | | | | | | | Started with Anode at 25V and coil at 0A,
bias at 30kV. (attachment 1)
Ramped coil to 60A (0.4V) (attachment |
6x |
|
834
|
Thursday, December 17, 2020, 08:16 |
Carla Babcock, Alexander Shkuratoff | | | | | | | | | Ramping up to 75kV. Started drawing current
at 63.5kV this time.
Now at 75kV, drawing 5uA of current. |
|
|
955
|
Thursday, January 12, 2023, 09:04 |
Aaron Schmidt | | LP-SIS | | | 44691-14 | 44378-20 | In progress | | Test for Aurelia L. Empty LP-SIS w/ end
caps in. Right side expanded.
Thermocouples installed (R - L): |
|
|
1006
|
Wednesday, April 24, 2024, 16:21 |
Dave Neilson | | LP-SIS | | | 44691-8 | 45235-26 | | | Wednesday, April 24, 2024, 16:20:
Target assembly installed.
Wednesday, April 24, 2024, 16:20: |
|
|
1032
|
Thursday, November 28, 2024, 13:47 |
Isaiah Rabuka | | | | | | | | | November 28, 2024 1:46PM
Checked in on sample in ATTS. |
|
|
1034
|
Tuesday, December 03, 2024, 15:49 |
Isaiah Rabuka | | | | | | | | | Tuesday,
December 03, 2024, 15:48 |
|
|
1035
|
Wednesday, December 04, 2024, 15:43 |
Isaiah Rabuka | | | | | | | | | Wednesday,
December 04, 2024, 15:42 Depressurized the |
|
|
1037
|
Thursday, December 05, 2024, 14:06 |
Isaiah Rabuka | | | | | | | | | Thursday, December 05, 2024, 14:05
Pressurized ATTS with argon, swapped out
samples, and repressurized and heated chamber. |
|