  586   Monday, May 22, 2017, 09:43 Aaron Schmidt HP-FEBIAD-CTL     Tri-Coil CTL-FEBIAD test IVMonday, May 22, 2017, 09:41: Roughing.
Monday, May 22, 2017, 10:00: Turbo
pumps started.
 CTL_FEBIAD_Test_IV.docxTS-2017-05-22-10-07.rgaTS-2017-05-25-15-42.rga 
  588   Friday, June 02, 2017, 15:57 Aaron SchmidtSiC#36HP-FEBIAD-CTLITWTM241369-1042132-6/9 Conditioning SiC#36Friday, June 02, 2017, 15:20: Coil loose
(Remove lid, Tighten and place lid again)
Friday, June 02, 2017, 15:52: Roughing
 9x 
  590   Tuesday, June 06, 2017, 09:22 Aaron Schmidt       Pump down empty chamberTuesday, June 06, 2017, 09:21: roughing.

Friday, June 09, 2017, 08:50:
Ion gauge off. Turbo pumps off.
  
  591   Wednesday, June 07, 2017, 12:49 Aaron Schmidt       Gas bottles Gas bottles for FEBIAD testing were
exchanged yesterday around 1:30. One Neon
& one Argon bottle were removed.
  
  593   Friday, June 16, 2017, 11:23 Aaron Schmidt       Pump down empty chamber.Friday, June 16, 2017, 11:22: roughing.
Friday, June 16, 2017, 14:28: Turbo
pumps on
  
  598   Monday, July 17, 2017, 09:58 Aaron Schmidt HP-SIS  42218-842738-1 Target cleaning test (Long) HP-SIS CC Clean    HP-SIS_CC_Clean_(Long).docxOMEGA_OM-DAQPRO-5300_27-Jul-17_10.25.04.dlpTS-2017-07-24-10-40.rga 
  599   Monday, July 17, 2017, 10:04 Aaron Schmidt HP-SIS  42218-1042738-1 Target cleaning test HP-SIS Full Clean    HP-SIS_Full_Clean_(Short).docxTS-2017-07-27-10-40.rga 
  606   Monday, September 25, 2017, 14:10 Aaron Schmidt       Pump down empty chamberMonday, September 25, 2017, 14:10: Roughing.

Wednesday, September 27,
2017, 08:23: Turbo pumps on
  
  608   Tuesday, October 10, 2017, 13:10 Aaron Schmidt       Gas bottlesTuesday, October 10, 2017, 09:30: 
Install/swap gas bottles. Elog.
Removed smallest Neon leak. Neon
  
  612   Tuesday, October 24, 2017, 11:38 Anders Mjos       FEBIAD coil magnetic field measurmentwith Fernando
Tuesday, October 24, 2017: Testing
setup with triple coil
 FEBIAD_Coil_Field_Measurement_2017-10-25.xlsx171025-First-Run.xlsx 
  619   Thursday, December 21, 2017, 15:12 Anders Mjos       Powered down devicesPowered down vacuum gauge and turbo pump
controllers
  
  629   Wednesday, February 07, 2018, 08:46 Aaron Schmidt       BIAS Power supply installationWednesday, February 07, 2018, 08:40: A
75 kV Glassman power supply was installed
in the rack for use in further HV testing.
 BIAS_PS_off_top_switch.jpgBIAS_PS_70kV_rear_bottom.jpgBIAS_PS_70kV_Front_bottom.jpg 
  631   Thursday, February 08, 2018, 16:54 Carla Babcock       EZL strange behaviourThursday, February 08, 2018, 16:54
Testing the HV bias I found that
the einzel lens was behaving strangely. When
  
  632   Friday, February 09, 2018, 08:57 Carla Babcock       TSGBIASSAFETY ok interlockFriday, February 09, 2018, 08:25   
Disconnected the AC power chain from the
old bias supply but now cannot turn on the
  
  633   Tuesday, February 13, 2018, 12:17 Carla Babcock       Ramping up bias to 60kV with conditioning station supplyRamped up to 60kV with the new power supply,
same as what we did last time with the standard
test stand bias supply (see entry #627 ).
 vacuumbias_13022018.PNG 
  634   Tuesday, February 13, 2018, 16:47 Carla Babcock       Ramping to 63kV - some sparksSparks at 62kV on the bias.
Turned it down, turned it back up
and got a spark at 60kV.
  
  635   Friday, February 16, 2018, 15:21 Carla Babcock       Cleaned HV cage - trying bias againI vacuumed inside the HV cage, though it
has many small areas that are difficult to
access so I am not sure how great a job I
  
  636   Monday, February 19, 2018, 08:30 Carla Babcock       TMSTP6 offFound TMSTP6 off, restarted it, seems fine
now (drawing 0.8A)
  
  637   Monday, February 19, 2018, 14:01 Carla Babcock       Attempts to get to higher voltages, summarized.The test stand holds up to 63kV, however
at voltages over 54kV there are small discharges,
rising to a continuous level around 60kV.
  
  638   Tuesday, February 20, 2018, 09:04 Carla Babcock       Trying HV with rubber corona shieldTuesday, February 20, 2018, 09:01: Sparks
at 62.5kV after a couple minutes. Sounds
like they were in the EE spark gap but don't
  