Entry  Friday, December 20, 2019, 07:59, Aaron Schmidt, , , , , , , , Holiday TS shut down 
Friday, December 20, 2019, 07:58: Turn off ion gauges. Shut off turbo pumps TP6, TP2, TP1A, & TP1B. Close backing valves.
Friday, December 20, 2019, 08:06: PV1 & PV2 off. RP1 & RP2 off.

Monday, January 06, 2020, 09:35: Restarting TS. RP1 & RP2 on. (BIAS PS upgraded / Note: https://elog.triumf.ca/TIS/Test-Stand/776 ).
Entry  Friday, January 03, 2020, 11:56, Anders Mjos, , , , , , , Problems/Solutions, Upgrading BIAS Power Supply 
A new power supply was installed today by John Chow. Due to differences in pin configuration of the controls, a change to the cabling is required. Contacted
controls (Julie) for support.
Entry  Tuesday, January 21, 2020, 13:45, Aaron Schmidt, , , , , , , Problems/Solutions, RGA Communications error 
Tuesday, January 21, 2020, 13:42: The RGA was unable to connect. Typically connects on COM4, however it did not register. RGA Offline.
Brought in a separate RGA. Was able to connect & see the 2nd RGA ID on COM4. Removed 2nd RGA.
We likely need to replace / repair our communication chip again.
Entry  Thursday, January 23, 2020, 16:05, Anders Mjos, , , , , , , Problems/Solutions, Vacuum tripped due to PLC/EPICS for for the new BIAS 
Thursday, January 23, 2020, 16:05: Restarting vacuum and TPs
    Reply  Friday, January 24, 2020, 16:01, Anders Mjos, , , , , , , Problems/Solutions, Upgrading BIAS Power Supply 


    
        
            Anders Mjos wrote:
        
        
            
            A new power supply was installed today by John Chow. Due to differences in pin configuration of the
Entry  Tuesday, February 11, 2020, 14:27, Aaron Schmidt, , , , , , , , Pump down empty Chamber 
Tuesday, February 11, 2020, 14:27: UC#32 HS removed.
Tuesday, February 11, 2020, 14:27: Roughing.

Wednesday, February 12, 2020, 09:05: Venting.
Entry  Thursday, February 27, 2020, 07:20, Aaron Schmidt, , , , , , , , FS#3 - Fitting change out 
Thursday, February 27, 2020, 07:10: Swapped out an old brass fitting on the supply line going into FS#3 - Line K. 
Replaced w/ SS fitting for interchangeability w/ other lines in case a bypass is needed.
Entry  Wednesday, March 04, 2020, 17:15, Fernando Maldonado, , , , , , , Problems/Solutions, Emittance rig communication 
Wednesday, March 04, 2020, 17:13: EPICS page indicated a sucesful scan but data was empty.
Wednesday, March 04, 2020, 17:13: Power suppply didn't respond to the voltage sweep
Wednesday, March 04, 2020, 17:14: Problem most likely similar to elog entry 531.
Entry  Friday, March 27, 2020, 11:30, Aaron Schmidt, , , , , , , , Vacuum loss / spike / Shutdown Mar_27_-_2020_-_Vacuum_Trip.docx
The ISAC was left with the turbo pumps and water supplies running. Just the power supplies off. Monday, March, 23, 2020.
Check daily

Thursday, March 26, 2020, 13:25: Vacuum ok at 3.2e-07T. All status ok.
    Reply  Tuesday, April 07, 2020, 10:53, Anders Mjos, , , , , , , , Vacuum loss / spike / Shutdown 


    
        
            Aaron Schmidt wrote:
        
        
            
            The ISAC was left with the turbo pumps and water supplies running. Just the power supplies off. Monday,
Entry  Tuesday, May 19, 2020, 06:01, Aaron Schmidt, , , , , , 42972-8, Problems/Solutions, Leak check / Troubleshoot May_19-20_Leak_check_-_FS#3.docxMess_inside_TS_-_1.jpgMess_inside_TS_-_2.jpgBlock_water_leak_visible.jpg
 https://elog.triumf.ca/TIS/Test-Stand/791
https://elog.triumf.ca/TIS/Test-Stand/792
Tuesday, May 19, 2020, 06:01: Venting. 
Entry  Monday, July 20, 2020, 11:40, Aaron Schmidt, (Empty-Test), , , , 44160-1, 43822-2, In progress, Conditioning Test P2N P2N_-_1_-_July-20-22-2020.docx
Salts added: 
Cs - 15 uL
Li - 10 uL
Entry  Tuesday, July 28, 2020, 13:27, Aaron Schmidt, , , , , , , Problems/Solutions, Water leak on magnet PS 
 Fault: 13334
Tuesday, July 28, 2020, 12:00: Leak discovered in ISAC Test Stand MB1 PS. Appears
to be coming from hose barb soldered connection to heat sink of pass bank. Pass bank will need to be disassembled and heat sink soldered on a workbench.
Entry  Wednesday, August 05, 2020, 10:01, Aaron Schmidt, , , , , , , Problems/Solutions, Roughing pump swap out. 
Wednesday, August 05, 2020, 10:00: TP6 & TP2 off. IG6 off.
Wednesday, August 05, 2020, 12:20: RP2 swapped with a smaller roughing pump from the hot lab.
Wednesday, August 05, 2020, 12:25:  Roughing.
Entry  Tuesday, August 18, 2020, 10:00, Aaron Schmidt, , , , , , , , IDP15 Scroll pump installed - RP1 replaced 
PN: X3815-64000
SN: MY2005SA02
Description: IDP15 Scroll pump, Std.
Entry  Wednesday, August 19, 2020, 08:52, Aaron Schmidt, , , , , , , , Leak check / Troubleshoot Aug_19_-_2020_Leak_Check..docx
Wednesday, August 19, 2020, 08:52: Purging all lines, except FS#5, It was already purged / closed.
Wednesday, August 19, 2020, 11:24: Vacuum @ 1.76e-06T.
Wednesday, August 19, 2020, 11:29: FS#2 opened. Observable vacuum spike noted. vacuum @ 2.2e-06T. Purge & Close.
Entry  Tuesday, August 25, 2020, 07:23, Aaron Schmidt, , , , , , , Problems/Solutions, Beam line side vacuum trip 
Tuesday, August 25, 2020, 07:07: Beam line side of the TS appears to have tripped? Open BV6 & BV2.
Tuesday, August 25, 2020, 07:15: Beam line side TP6 & TP2 on.
Tuesday, August 25, 2020, 07:16: Venting Chamber side
Entry  Tuesday, September 01, 2020, 14:01, Aaron Schmidt, , , , , , , Done, New tubing installed on loops 
Tuesday, September 01, 2020, 14:00: 
New tubing installed.
Blue on FS#4 loop (A)(B)
Entry  Monday, November 02, 2020, 08:52, Aaron Schmidt, , , , , , , Problems/Solutions, Leak check / Troubleshoot Nov-2-2020_Leak.docx
Monday, November 02, 2020, 08:46:
Large Vacuum spike noted 5:30 approx. Tripped TS. On tail end of the Nb#9 conditioning run. HV & heating were completed last week
Monday, November 02, 2020, 08:47: Vacuum @ 2.66e-06T.
Entry  Tuesday, November 10, 2020, 12:13, Aaron Schmidt, , , , , 43044-13, 44378-1, In progress, Pump down empty chamber / Leak. 
U-Loop installed on FS#5
Tuesday, November 10, 2020, 12:13: Roughing.
Tuesday, November 10, 2020, 12:57: TP1B on