767
|
Thursday, October 31, 2019, 11:37 |
Fernando Maldonado | | | | | | | Problems/Solutions | Probing anode bias supply on the service cap | Thursday, October 31, 2019, 10:41: Cage
removed. Tape put on the limit switches.
Anode interlock bypassed. |
|
768
|
Thursday, October 31, 2019, 13:22 |
Fernando Maldonado | | | | | | | Problems/Solutions | 9pin connector not fully in contact with baseplate | Thursday, October 31, 2019, 13:20: After
inspecting the interior, the 9 pin bracket
was found not making full contact with the |
|
769
|
Friday, November 01, 2019, 16:01 |
Fernando Maldonado | | LP-SIS | | | 41790-9 | 43515-9 | In progress | Peek seal tests on UCx#30 HS | Friday, November 01, 2019, 15:47: A symbiotic
peek seal assembly was installed on
the manipulator grip to verify the temperature |
|
770
|
Friday, November 08, 2019, 14:21 |
Aaron Schmidt | | LP-SIS | | | 41790-9 | 43515-9 | In progress | Nitrogen Bottle leak test | Friday, November 01, 2019, 14:00: Nitrogen
bottle installed. Purged waterlines HS /
FS#5. Purge done in conjunction with SiC#38 |
|
771
|
Friday, November 15, 2019, 10:35 |
Aaron Schmidt | | | | | | | | Pump down empty Chamber | Friday, November 15, 2019, 09:35: Roughing.
Friday, November 15, 2019, 10:34:
Turbo pumps on. |
|
772
|
Friday, November 22, 2019, 19:06 |
Fernando Maldonado, Ferran Boix Pamies | | | | | | | | PEEK seal tests | Friday, November 22, 2019, 19:02:
The new design for the PEEK irradiation will
be tested. |
|
773
|
Wednesday, November 27, 2019, 16:01 |
Fernando Maldonado | | | | | | | Problems/Solutions | New Controller for TP6 | Wednesday, November 27, 2019, 15:31: During
HV tests, bias was around 55kV when a spark
occur and almost immediately the controller |
|
774
|
Monday, December 02, 2019, 16:01 |
Fernando Maldonado | | | | | | | In progress | Ferran irradiation copper end plate tests (aka MIST) | Friday: Test to validate Ferran's assembly.
The plan is to ramp up to operating current,
apply high voltage, and possibly extract |
|
775
|
Friday, December 20, 2019, 07:59 |
Aaron Schmidt | | | | | | | | Holiday TS shut down | Friday, December 20, 2019, 07:58: Turn
off ion gauges. Shut off turbo pumps TP6,
TP2, TP1A, & TP1B. Close backing valves. |
|
776
|
Friday, January 03, 2020, 11:56 |
Anders Mjos | | | | | | | Problems/Solutions | Upgrading BIAS Power Supply | A new power supply was installed today
by John Chow. Due to differences in pin configuration
of the controls, a change to the cabling |
|
778
|
Tuesday, January 21, 2020, 13:45 |
Aaron Schmidt | | | | | | | Problems/Solutions | RGA Communications error | Tuesday, January 21, 2020, 13:42: The RGA
was unable to connect. Typically connects
on COM4, however it did not register. RGA |
|
779
|
Thursday, January 23, 2020, 16:05 |
Anders Mjos | | | | | | | Problems/Solutions | Vacuum tripped due to PLC/EPICS for for the new BIAS | Thursday, January 23, 2020, 16:05: Restarting
vacuum and TPs |
|
780
|
Friday, January 24, 2020, 16:01 |
Anders Mjos | | | | | | | Problems/Solutions | Upgrading BIAS Power Supply |
|
|
783
|
Tuesday, February 11, 2020, 14:27 |
Aaron Schmidt | | | | | | | | Pump down empty Chamber | Tuesday, February 11, 2020, 14:27: UC#32
HS removed.
Tuesday, February 11, 2020, 14:27: |
|
784
|
Wednesday, February 12, 2020, 11:04 |
Aaron Schmidt | | LP-SIS | | | 41790-9 | 43515-1 | In progress | Conditioning HS | Using a broken LP-FEBIAD oven for out gassing.
Tentative UC#31*
Wednesday, February 12, 2020, 10:57: |
|
786
|
Thursday, February 27, 2020, 07:20 |
Aaron Schmidt | | | | | | | | FS#3 - Fitting change out | Thursday, February 27, 2020, 07:10: Swapped
out an old brass fitting on the supply line
going into FS#3 - Line K. |
|
788
|
Wednesday, March 04, 2020, 17:15 |
Fernando Maldonado | | | | | | | Problems/Solutions | Emittance rig communication | Wednesday, March 04, 2020, 17:13: EPICS
page indicated a sucesful scan but data was
empty. |
|
791
|
Friday, March 27, 2020, 11:30 |
Aaron Schmidt | | | | | | | | Vacuum loss / spike / Shutdown | The ISAC was left with the turbo pumps
and water supplies running. Just the power
supplies off. Monday, March, 23, 2020. |
|
792
|
Tuesday, April 07, 2020, 10:53 |
Anders Mjos | | | | | | | | Vacuum loss / spike / Shutdown |
|
|
793
|
Tuesday, May 19, 2020, 06:01 |
Aaron Schmidt | | | | | | 42972-8 | Problems/Solutions | Leak check / Troubleshoot | https://elog.triumf.ca/TIS/Test-Stand/791
|
|