  660   Tuesday, May 08, 2018, 10:36 Aaron Schmidt LP-FEBIAD  41790-942752-5In progressC-seal Test2 C-Seals installed with SS springs
on water blocks. The SS springs are also
used in the module.
  
  661   Tuesday, May 22, 2018, 08:48 Anders Mjos      Problems/SolutionsTSG:TP1A not runningPump found off on Tuesday morning.
Tuesday, May 22, 2018, 08:40: Starting
TP1A
  
  662   Thursday, May 24, 2018, 08:38 Anders Mjos      Problems/SolutionsVenting beamline for IG6 replacementThursday, May 24, 2018, 08:38: TPs stopped
Thursday, May 24, 2018, 09:18: Venting
Thursday, May 24, 2018, 14:30: IG6
  
  663   Thursday, May 24, 2018, 15:28 Anders Mjos      Problems/SolutionsReconfigured FEBIAD coil for testing new source trayThursday, May 24, 2018: Configured coil
to be (-) E&F, (+) G&H. Water should
be supplied to both terminals in either configuration.
  
  664   Monday, May 28, 2018, 08:46 Aaron Schmidt LP-FEBIAD TM241790-942752-5In progressNew TM source tray swap out. Monday, May 28, 2018, 08:45: Venting. Prep
For removal.
Close FS#8. Clean up water
 New_TM_Source_Tray_2018.docxTS-2018-05-30-06-30.rgaER-580-310-30kV-m28.txtER-580-320-30kV-M39.txt2018_TM2_Source_Tray_in_Test_Stand_-_Test_Results.docx 
  665   Monday, June 04, 2018, 16:02 Anders Mjos      Problems/SolutionsMB1 timeoutMass separator magnet timed out. Tried
reconfigure. Called Kyle from  controls who
power cycled the CANbus card. This resolved
  
  666   Wednesday, June 06, 2018, 14:01 Aaron Schmidt      Problems/SolutionsEmittance scanner (E-rig) communication issues.Wednesday, June 06, 2018, 13:50:
It was noted yesterday during the
TM2 Source HV tests that the E-rig was not
  
  667   Thursday, June 07, 2018, 09:21 Aaron Schmidt      Problems/SolutionsPump down empty chamber. Anode checkTM2 Source tray still in.
Thursday, June 07, 2018, 09:20: Roughing.
Thursday, June 07, 2018, 12:42: Turbo
 20180608_100402.jpg20180608_100835.jpg20180608_100840.jpg20180613_080550.jpg20180613_080605.jpg 
  668   Tuesday, June 12, 2018, 11:38 Aaron Schmidt      In progressSource Tray re-installationRe-installation of the ISAC Test Stand
Source tray. The TM2 ST was removed.
Tuesday, June 12, 2018, 10:15: Disconnect
 TS_Source_Tray_re-installed_2018_-_(Leak_found).docx 
  669   Tuesday, June 19, 2018, 10:30 Aaron Schmidt      DoneRGA repairMonday, June 18, 2018, 10:00: RGA removed
from ISAC TS. Handed to Travis C. Communications
issues found
  
  670   Thursday, June 21, 2018, 16:32 Anders Mjos LP-FEBIAD  41790-942752-5In progressHeating targetThursday, June 21, 2018, 16:30: Short between
ANODE and EE. Do not use until repaired.
Thursday, June 21, 2018, 16:32: Ramping
 TS-2018-06-19-10-30.rgaTS_Source_tray_2018_-_Check_2.docx 
  672   Monday, July 09, 2018, 10:44 Aaron Schmidt LP-FEBIAD  41790-942752-5In progressCoil Test July Monday, July 09, 2018, 10:43: Rouging.
Monday, July 09, 2018, 13:14: Turbo
pumps on.
  
  673   Thursday, July 12, 2018, 08:24 Aaron Schmidt LP-FEBIAD  41790-942752-5In progressPower outage / restartPower outage (07/11/2018 @ approx 21:53)
shut down the test stand.
  
  674   Thursday, July 12, 2018, 10:11 Aaron Schmidt LP-FEBIAD  41790-942752-5In progressCoil Test #5 *** REVIEW Elog entry #673 Power
outage & restart ***
Thursday, July 12, 2018, 10:10: Opened
  
  677   Friday, August 10, 2018, 10:56 Aaron Schmidt      Problems/SolutionsNew PS installation and Cathode BIAS setFriday, August 10, 2018, 10:25: Remove
TBHT 500 PS and replace with TBHT 600 PS.
Friday, August 10, 2018, 10:50: Switch
  
  678   Tuesday, August 14, 2018, 11:03 Aaron Schmidt LP-SIS  41177-342752-6 Voltage Tests (Ta target)Tuesday, August 14, 2018, 10:55: Auto ramping
TGHT @ 6 A per min to 40 A.
Tuesday, August 14, 2018, 11:03:
  
  679   Tuesday, August 21, 2018, 12:54 Anders Mjos      Problems/Solutions9-pin connection configurationPin configuration between top 9-pin connector
on Source Tray and terminal in high voltage
rack. Measured 2018-08-21 by Aaron and Anders
  
  680   Wednesday, August 22, 2018, 15:20 Aaron Schmidt LP-SIS  41177-3  Voltage Tests (Ta Target)  Wires reconfigured / set 
Wednesday, August 22, 2018, 13:10:
Roughing. 
  
  681   Wednesday, August 29, 2018, 11:36 Aaron Schmidt       Epics / putty crash.Wednesday, August 29, 2018, 11:35: EPIC's
crashed.... epically.
Unable to restart Putty or TS controls.
  
  682   Friday, August 31, 2018, 10:16 Aaron Schmidt      Problems/SolutionsRGA connection loss.Friday, August 31, 2018, 10:10: The RGA
will not re-connect to the computer. Manually
turned it off while under vacuum to protect
  